Boiler replacement method statement example: gas combi boiler swap, occupied house

HSE five steps · CDM 2015
You write this
Remove an existing domestic gas combi boiler and install a new wall-hung combi boiler in an occupied house, including draining and refilling the system, flue installation and termination, and the electrical connection, carried out by a Gas Safe registered engineer.
You get this
Halewood Heating Services Ltd will remove an existing domestic gas combi boiler and install a new wall-hung combi boiler in an occupied house at 8 Beechcroft Close, Sheffield S11 7D** (project ref HHS-3164), including draining and refilling the system, flue installation and termination, and the electrical connection, carried out by a Gas Safe registered engineer. The work is for Mrs J. Okafor, who is the client and principal contractor, and is planned for one day starting Tue 23 Jun 2026 with 2 operatives. The author is R. Naylor, Gas Safe Registered Engineer. The household stays in the house, so the work area is kept segregated, gas and electricity are isolated and proved before any disconnection, and the work is done to the manufacturer's instructions and the Gas Safe (Installation and Use) Regulations 1998. Items to confirm before work starts: (1) the full postcode, as it is shown as S11 7D**; (2) the age of the house and the wall construction where the flue and bracket fixings go; (3) any asbestos survey or information held by Mrs Okafor for the boiler area and flue route; (4) the flue route, termination position and whether the existing flue is horizontal or vertical; (5) the location of the gas emergency control valve, the electrical isolation point and a safe drain point for system water; (6) the competence and first aid training of the second operative; (7) the tools to be used to cut or core the flue hole. R. Naylor confirms these with Mrs Okafor on the pre-start walk-round on the morning of Tue 23 Jun 2026, before any isolation or drilling starts.

Generated for an example job to show the format. Make your own site-specific version and have a competent person review it.

Document details
ContractorHalewood Heating Services Ltd
AuthorR. Naylor, Gas Safe Registered Engineer (reg. no. held on card)
Client / Principal ContractorMrs J. Okafor
Site8 Beechcroft Close, Sheffield S11 7D**
Project referenceHHS-3164
Start / durationTue 23 Jun 2026 / 1 day

1. Scope of works

Halewood Heating Services Ltd will remove an existing domestic gas combi boiler and install a new wall-hung combi boiler in an occupied house at 8 Beechcroft Close, Sheffield S11 7D** (project ref HHS-3164), including draining and refilling the system, flue installation and termination, and the electrical connection, carried out by a Gas Safe registered engineer. The work is for Mrs J. Okafor, who is the client and principal contractor, and is planned for one day starting Tue 23 Jun 2026 with 2 operatives. The author is R. Naylor, Gas Safe Registered Engineer. The household stays in the house, so the work area is kept segregated, gas and electricity are isolated and proved before any disconnection, and the work is done to the manufacturer's instructions and the Gas Safe (Installation and Use) Regulations 1998. Items to confirm before work starts: (1) the full postcode, as it is shown as S11 7D**; (2) the age of the house and the wall construction where the flue and bracket fixings go; (3) any asbestos survey or information held by Mrs Okafor for the boiler area and flue route; (4) the flue route, termination position and whether the existing flue is horizontal or vertical; (5) the location of the gas emergency control valve, the electrical isolation point and a safe drain point for system water; (6) the competence and first aid training of the second operative; (7) the tools to be used to cut or core the flue hole. R. Naylor confirms these with Mrs Okafor on the pre-start walk-round on the morning of Tue 23 Jun 2026, before any isolation or drilling starts.

2. Sequence of works

Method statement, safe system of work

  1. Before the day, ask Mrs Okafor for any asbestos survey, building age information or previous work records for the boiler area and flue route. Agree a start time and tell the household that gas, hot water and heating will be off for part of the day.
  2. On arrival, show Gas Safe ID cards to Mrs Okafor, walk the job and confirm the items listed in the scope. Agree which rooms the operatives will use, where the household will stay clear, and where children and pets will be kept.
  3. Asbestos pre-start check under Regulation 5 of the Control of Asbestos Regulations 2012: check any register or survey for the boiler area, flue route and drilling positions. If the house was built before 2000 or its age is unknown and nothing covers the area, do not drill or break into the fabric until the client has had the area checked by a competent person. Stop-work rule: if suspect material is found at any point, stop, keep people away, make the area safe and report it to Mrs Okafor and Halewood Heating Services Ltd before work carries on.
  4. Brief both operatives on this method, the emergency arrangements and their roles. Both sign the briefing sheet.
  5. Protect the route from the front door to the kitchen/utility and the floor around the boiler with dust sheets or floor protection. Set up tools and materials in a tidy area, with nothing left where the household may reach it.
  6. Check the existing installation before touching it: look for signs of spillage or poor flue condition, check for gas smell, and note the condition of the existing flue and pipework.
  7. Isolate the electrical supply to the boiler at the source and lock it off. Prove dead with a voltage indicator that meets GS38 and has been proved on a known source before and after. Turn off the gas at the appliance valve and the emergency control valve as needed. Isolate the water supply to the boiler.
  8. Allow the system to cool. Connect the hose to the drain point and drain the system to a suitable outlet. Check for scalding water and leaks. Keep a bucket and absorbent towels ready.
  9. Disconnect the pipework and flue from the old boiler. Cap off open gas pipework immediately. With the second operative, lift the old boiler off the wall using a two-person lift and remove it from the house.
  10. Fix the new boiler bracket and form the flue hole using drills, a core drill or a saw with on-tool extraction or water suppression. Keep the household out of the room. Vacuum dust with an H-class or M-class vacuum. Stop and report if suspect material is found.
  11. Hang the new combi boiler with two people. Fit the isolation valves and connect the pipework. Where solder is used, use a heat shield mat, check behind and around the pipework, keep a fire extinguisher at hand and check the area after the work. Press fittings are used where they are suitable and do not need a flame.
  12. Install the flue and termination to the manufacturer's instructions. Make good and seal the hole. Check the flue terminal position against the manufacturer's clearances, and keep the ground below clear while working outside.
  13. Make the electrical connection to BS 7671 and the manufacturer's instructions. Complete and record the dead tests before re-energising.
  14. Refill and vent the system, fill the system inhibitor to the manufacturer's instructions, and check all joints for leaks.
  15. Restore gas and electricity. Carry out a gas tightness test with the gauge and purge the gas supply. Commission the boiler to the manufacturer's instructions and use the flue gas analyser to check combustion and flue integrity. Do not leave the boiler running if any reading is not satisfactory.
  16. Check the household has a working CO alarm in the right place and advise Mrs Okafor if not. Demonstrate the boiler controls, hand over the paperwork and complete the Building Regulations notification and warranty registration.
  17. Clean up with a vacuum, never dry sweeping. Remove all waste and the old boiler from site. Check the work area and drain point, thank the household and confirm with Mrs Okafor that the work area is clear.

3. Risk assessment

Built on the HSE five steps, MHSWR 1999 regulation 3 and the hierarchy of control.

  1. Occupied house: household members (Mrs Okafor, family, visitors and any pets) entering the work area, touching hot pipework, tools, open pipework or materials

    Low
    Who / how
    Mrs Okafor and any other occupants, including children, older or vulnerable people and pets, who could be burned, cut, trip over tools, or be exposed to dust and fumes
    Existing controls
    Gas Safe registered engineer in charge; operatives wear ID
    L×S
    3×3=9
    Additional controls
    Agree the work area and the route with Mrs Okafor at the pre-start walk. Close the kitchen/utility door where possible and keep the household and pets out of the room while gas is off and while drilling or soldering. Tools, materials and chemicals are kept in the work area or the van, never left unattended. Dust sheets and floor protection are laid. No operative leaves open pipework or an unfinished appliance unattended. Safety boots and gloves worn by operatives.
  2. Live gas: gas escape, fire or explosion when disconnecting the old boiler, making new connections and re-establishing the supply

    Medium
    Who / how
    Operatives, Mrs Okafor, household members and neighbours, who could suffer burns, blast injuries or fatal injury
    Existing controls
    Work by Gas Safe registered engineer under the Gas Safe (Installation and Use) Regulations 1998
    L×S
    3×5=15
    Additional controls
    Isolate at the emergency control valve and the appliance valve, and cap off open pipework straight away. Check for gas smell before starting. No naked flame, smoking or ignition sources while pipework is open. Ventilate the room. Carry out a gas tightness test and purge to the manufacturer's instructions and standards before re-lighting. Check the meter and emergency control valve are accessible before starting. Use leak detection fluid on all joints. Use the gas tightness test gauge only if calibrated and in date. Keep an extinguisher accessible.
  3. Carbon monoxide and combustion products spilling from an incorrectly fitted or terminated flue, or poor combustion

    Medium
    Who / how
    Mrs Okafor and all household members, who could suffer CO poisoning from the day of installation onwards, which can be fatal
    Existing controls
    Gas Safe registered engineer; manufacturer's instructions
    L×S
    2×5=10
    Additional controls
    Fit and terminate the flue to the manufacturer's instructions, checking clearances to openings and boundaries. Seal and support all flue joints and check all seals. Use the flue gas analyser to check combustion readings and flue integrity at commissioning, and do not hand over the boiler if readings are not satisfactory. Confirm a working CO alarm is in place and tell Mrs Okafor about the symptoms of CO poisoning. Tell the household not to use the boiler if there are any problems.
  4. Live electricity: contact with live conductors when isolating the boiler and making the electrical connection

    Medium
    Who / how
    Operatives and household members, who could receive an electric shock or burns, which can be fatal
    Existing controls
    18th Edition qualified operative; Electricity at Work Regulations 1989
    L×S
    3×5=15
    Additional controls
    Isolate at the consumer unit or fused spur and lock off with a warning notice. Prove dead with a GS38 compliant voltage indicator proved before and after use. Do not work on or near live parts. Check cable routes before drilling to avoid hidden cables. Make the connection to BS 7671 and complete dead tests before re-energising. Tell the household the supply is off and not to switch it on. Insulated tools used where a risk of contact remains.
  5. Live water: scalding from hot system water when draining, flooding and damage to the house when disconnecting and refilling

    Low
    Who / how
    Operatives and household members, through scalds and slips, and Mrs Okafor through damage to her property
    Existing controls
    Hose and bucket in the van
    L×S
    3×3=9
    Additional controls
    Allow the system to cool before draining. Isolate the water supply and agree the drain point before starting. Run the hose to a suitable outlet and secure it. Keep towels and a bucket ready, and lay absorbent sheets under joints. Drain slowly and have the second operative watch the hose. Check all joints for leaks before leaving. Dispose of dirty water as set out in the environmental section. Gloves and eye protection worn.
  6. Manual handling of the old and new boilers and pipework in the kitchen/utility and through the house

    Medium
    Who / how
    Operatives, who could suffer back, shoulder or other musculoskeletal injury, or trap hands or drop the boiler
    Existing controls
    Two operatives on the job
    L×S
    4×3=12
    Additional controls
    Check the weight of the new boiler in the manufacturer's instructions and plan under the Manual Handling Operations Regulations 1992. Remove the boiler casing and any other parts to reduce the load. Use a two-person lift and a sack truck where possible. Clear and check the route from the van to the boiler position. Use a lifting method that avoids awkward reaches. Take breaks between heavy lifts. Gloves and safety boots worn.
  7. Working at height from a step ladder to reach the flue, the boiler on the wall and high-level pipework

    Low
    Who / how
    Operatives, who could fall and suffer serious injury
    Existing controls
    Step ladder in good condition
    L×S
    3×4=12
    Additional controls
    Under the Work at Height Regulations 2005, keep work at height to a minimum and do as much as possible from the floor. Check the step ladder before use and use it on firm, level ground with the legs fully open. Keep three points of contact and do not overreach. Use a ladder suited to short duration work only and do not use it for heavy or two-handed tasks. Use a second operative to foot the ladder where needed. Keep the household away from the ladder. For flue termination outside, use a suitable stable platform if the step ladder is not suitable.
  8. Respirable crystalline silica (RCS) dust from drilling, coring or fixing into masonry, brick, block or mortar for the flue hole and bracket fixings

    Medium
    Who / how
    Operatives doing the work, and Mrs Okafor and any household members nearby, who could breathe the dust and suffer long-term lung disease
    Existing controls
    Cordless drill; dust sheets
    L×S
    3×4=12
    Additional controls
    Plan the work to reduce cutting and drilling, for example by using the existing flue hole or the minimum number of fixings. Use on-tool extraction with an M-class or H-class vacuum or water suppression on every drill, core drill or saw used on these materials. Keep others out of the room and close the door. Clean up with an H-class or M-class vacuum, never by dry sweeping or compressed air. Then wear RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven. Controlled under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE guidance: Construction Information Sheet CIS36 'Construction dust'. The RCS workplace exposure limit is 0.1 mg/m3 (8-hour TWA) in HSE EH40/2005.
  9. Disturbing unidentified asbestos-containing materials when drilling, cutting or removing existing building fabric, old flue pipes, boxing, or boiler insulation or gaskets

    Medium
    Who / how
    Operatives, Mrs Okafor and household members, who could breathe asbestos fibres, with serious long-term lung disease
    Existing controls
    Gas Safe registered engineer; experience of older properties
    L×S
    2×5=10
    Additional controls
    Check before work starts under Regulation 5 of the Control of Asbestos Regulations 2012: ask Mrs Okafor for any asbestos register, survey or information for the boiler area and flue route. If the house was built before 2000 or its age is unknown, and the intrusive area is not covered, a refurbishment survey of that area is needed before drilling or breaking into the fabric. Stop-work rule: if suspect material is found, stop, keep people away, close the room and report it to Mrs Okafor and Halewood Heating Services Ltd before work carries on. Do not sweep, vacuum or handle suspect material. This is a check to be made, not a finding.
  10. Fire from the blowtorch when soldering copper joints near combustible materials, and flux fumes

    Low
    Who / how
    Operatives and household members, through burns, fire spread and fume inhalation
    Existing controls
    Fire extinguisher in the van
    L×S
    3×4=12
    Additional controls
    Use press fittings where they are suitable, so no flame is needed. Where soldering is needed, use a heat resistant mat and shield, remove or protect combustibles, and keep a fire extinguisher at hand. Open windows for ventilation. Check behind the work after soldering and leave the area for a time before leaving. Keep the household out of the work area. Gloves and safety glasses worn.
  11. Flue termination and external wall penetration: damage to the structure, falling debris, hot flue gases and tools falling to the ground outside

    Low
    Who / how
    Operatives, Mrs Okafor, household members and neighbours or passers-by outside, through falling tools or debris, or damage to the house
    Existing controls
    Gas Safe registered engineer; manufacturer's flue instructions
    L×S
    2×3=6
    Additional controls
    Mark out the flue position and check clearances to windows, doors, boundaries and the ground before drilling. Check for cables and pipes within the wall. Keep the ground below the work clear and the household away. Seal and make good around the flue. Tell the client about the final flue position. Safety boots and gloves worn.
  12. Slips, trips and falls over tools, hoses, cables, dust sheets, spilled water and materials in the hallway and kitchen/utility

    Low
    Who / how
    Operatives and household members, who could be injured by falling
    Existing controls
    Operatives tidy as they go
    L×S
    3×2=6
    Additional controls
    Plan the work area and route before starting. Keep walkways clear and use trailing cable-free cordless tools where possible. Secure dust sheets so they do not slip. Wipe up water straight away. Tidy at the end of each task. Wear safety boots with good grip.
  13. Noise and vibration from drilling and coring, and dust and debris in the eyes

    Low
    Who / how
    Operatives and household members nearby, through short-term noise exposure and eye injury
    Existing controls
    Cordless drill; short duration of use
    L×S
    3×2=6
    Additional controls
    Under the Control of Noise at Work Regulations 2005, keep drilling and coring to the minimum and tell the household beforehand. Use the correct sharp bit and keep tool use short. Pick a time of day for noisy work that suits the household. Safety glasses worn and hearing protection if noise is high.
  14. Cuts, scrapes and burns from sharp pipe ends, boiler casing, flue components and hot pipes

    Low
    Who / how
    Operatives, through cuts, abrasions and burns
    Existing controls
    Hand tools in good condition
    L×S
    3×2=6
    Additional controls
    Deburr and file pipe ends before fitting. Allow hot pipework and components to cool before handling. Use the correct tool for each task. Keep a sharp blade guarded when not in use. Gloves worn as backup, and first aid kit in the van.

4. COSHH assessment

Built on COSHH 2002 regulations 6 and 7 and HSE guidance L5.

Check each entry against the supplier's Safety Data Sheet before work starts. Take workplace exposure limits from HSE EH40/2005.

Respirable crystalline silica (RCS) dust created by drilling, coring or fixing into masonry, brick, block or mortar

Task or use
Core drilling or cutting the flue hole and drilling for the boiler bracket fixings in the wall
Route of exposure
Inhalation of fine dust. Eye contact with dust.
Who could be harmed
The operatives doing the work and anyone nearby breathing the dust, including Mrs Okafor and household members. Long-term exposure can cause serious and irreversible lung disease.
Hazards
Breathing in fine silica dust over time can cause silicosis, lung cancer and chronic obstructive pulmonary disease. Effects may not show for years. Dust in the eyes can irritate them.
Controls
  1. Eliminate or reduce the dust by planning the work to keep drilling and cutting to a minimum, for example using the existing flue hole where suitable.
  2. Use on-tool extraction with an M-class or H-class vacuum or water suppression on every drill, core drill and saw used on masonry.
  3. Keep others out of the room while the dust is being created and close the door.
  4. Clean up with an H-class or M-class vacuum, never by dry sweeping or compressed air.
  5. Limit the amount of drilling and the time spent exposed to it.
PPE
  • RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven, to the specification the HSE guidance gives.
  • Safety glasses.
  • Disposable or washable overalls, with dust not blown off clothes.
Storage and disposal
Collect dust in the vacuum and seal it in a heavy duty bag for disposal as construction waste in line with local arrangements. Wash or change dusty overalls before going home.
First aid and spillage
If dust gets in the eyes, rinse with clean water for at least 10 minutes and get medical advice if irritation continues. If someone has breathing problems, move them to fresh air and get medical advice. Clean up dust with the vacuum only.
Health surveillance
None is expected for a single-day job with these controls. Halewood Heating Services Ltd should consider respiratory surveillance if operatives are regularly exposed to silica across their work.
Check against the Safety Data Sheet
Silica dust comes from the work rather than a product, so check the drilling or coring equipment and extraction manufacturers' instructions for the correct vacuum class and filter. Confirm workplace exposure limits against HSE EH40/2005 before work starts. Controlled under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).

Flux and solder

Task or use
Soldering copper pipe joints for the boiler connections, only where press fittings are not used
Route of exposure
Inhalation of fumes, skin contact, eye contact and ingestion from dirty hands.
Who could be harmed
The operative soldering and anyone nearby, through irritation from flux, and fumes from heating flux.
Hazards
Hazards depend on the product, so check section 2 of its Safety Data Sheet. Flux commonly irritates skin and eyes, and heating flux gives off fumes that can irritate the airways.
Controls
  1. Eliminate the substances by using press fittings where they are suitable, so no flux or solder is needed.
  2. Substitute with a lower hazard flux if the Safety Data Sheet shows a better option.
  3. Ventilate the room well by opening windows and doors, and keep the household out of the room.
  4. Use only the amount of flux needed, avoid breathing in the fumes and keep the soldering time short.
  5. Wash hands before eating, drinking or smoking.
PPE
  • Gloves of the type given in the Safety Data Sheet.
  • Safety glasses.
  • RPE only if the Safety Data Sheet or the assessment shows it is needed, to the specification in the Safety Data Sheet.
Storage and disposal
Keep in the original container with a closed lid, in the van or a locked area away from heat and the household. Take empty or part-used containers and waste solder away with other waste and follow the Safety Data Sheet disposal advice.
First aid and spillage
Skin: wash with soap and water. Eyes: rinse with clean water for at least 10 minutes and get medical advice. If fumes cause discomfort, move to fresh air. Wipe up spills with absorbent material and dispose of it as waste.
Health surveillance
None expected for a one-day job. Check the Safety Data Sheet for any skin or respiratory surveillance requirements.
Check against the Safety Data Sheet
Before work starts, get the supplier's Safety Data Sheets for the flux and solder used. Confirm hazard statements in section 2, the gloves and any RPE needed, and the storage and disposal advice. Check any workplace exposure limits in HSE EH40/2005. Assessed under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).

System inhibitor

Task or use
Adding inhibitor to the refilled heating system
Route of exposure
Skin contact, eye contact, splashes and ingestion from dirty hands. Inhalation if misted.
Who could be harmed
The operative adding the inhibitor, and Mrs Okafor and household members if there is a spill.
Hazards
Hazards depend on the product, so check section 2 of its Safety Data Sheet. Such products can irritate the skin and eyes.
Controls
  1. Use a ready-to-use or low hazard product where the manufacturer allows it.
  2. Measure and dose carefully and use a sealed injection method or funnel to avoid splashing.
  3. Keep the household and pets away while dosing and do not leave containers unattended.
  4. Limit the quantity brought into the house to what the job needs.
PPE
  • Gloves and safety glasses to the specification in the Safety Data Sheet.
Storage and disposal
Keep in the original, labelled container with the lid closed and out of reach of children and pets. Take unused product and empty containers away and dispose of them as the Safety Data Sheet states.
First aid and spillage
Skin: wash with soap and water. Eyes: rinse with clean water for at least 10 minutes and get medical advice. If swallowed, do not induce vomiting and get medical advice, taking the container. Contain a spill with absorbent material, keep it out of drains, and dispose of it as waste.
Health surveillance
None expected for a one-day job with these controls.
Check against the Safety Data Sheet
Get the supplier's Safety Data Sheet before work starts. Confirm hazard statements in section 2, the gloves and eye protection needed, the dosing rate, and storage, spillage and disposal advice. Check any workplace exposure limits in HSE EH40/2005. Assessed under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).

Old system water and sludge drained from the existing heating system

Task or use
Draining down the system and disconnecting the old boiler
Route of exposure
Skin contact, eye contact from splashes, and ingestion from dirty hands.
Who could be harmed
Operatives draining the system, and Mrs Okafor and household members if water spills.
Hazards
The water may be hot, dirty, and contain sludge and old treatment chemicals. Check the product used in the system if it is known, and its Safety Data Sheet, section 2.
Controls
  1. Allow the system to cool before draining to remove the scald risk.
  2. Drain through a hose to a suitable outlet and keep splashing to a minimum.
  3. Use a bucket and absorbent towels to catch drips from the old boiler.
  4. Keep the household out of the area and wash hands before eating or drinking.
PPE
  • Gloves and safety glasses to the specification in the Safety Data Sheet of any treatment product known to be in the system.
Storage and disposal
Dispose of the water as set out in the environmental section. Put any sludge in a sealed container and take it away with waste, not to a drain.
First aid and spillage
Skin: wash with soap and water. Eyes: rinse with clean water for at least 10 minutes and get medical advice. Scalds: cool with running water for at least 20 minutes and get medical advice. Mop up spills straight away.
Health surveillance
None expected.
Check against the Safety Data Sheet
Ask Mrs Okafor whether any inhibitor or cleaner has been used in the system, and if so get its Safety Data Sheet and check section 2 hazards and disposal. Assessed under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).

5. Plant & equipment

  • Hand tools
  • Flue gas analyser (calibrated and in date)
  • Gas tightness test gauge
  • Cordless drill with on-tool dust extraction or water suppression for masonry
  • Core drill or saw for the flue hole, with extraction or water suppression, if needed
  • M-class or H-class vacuum
  • Hose for draining
  • Step ladder (checked before use)
  • GS38 compliant voltage indicator and proving unit
  • Blowtorch with heat resistant mat and shield (if soldering)
  • Fire extinguisher
  • Sack truck

6. Materials / COSHH

Combi boiler, flue kit, copper/plastic pipe and fittings, isolation valves, flux and solder or press fittings, and system inhibitor. Hazardous substances are the flux and solder, the system inhibitor, old system water and sludge, and silica dust from drilling masonry. Each has its own COSHH assessment above. Safety Data Sheets must be at hand on site.

7. PPE

  • Safety boots with good grip (BS EN ISO 20345)
  • Work gloves suited to the task (BS EN 388), and chemical resistant gloves for inhibitor and flux
  • Safety glasses (BS EN 166)
  • FFP3 face-fit tested RPE for drilling and coring masonry (BS EN 149)
  • Hearing protection if noise is high (BS EN 352)
  • Knee pads
  • Overalls

8. Competence & training

R. Naylor and the second operative work under Halewood Heating Services Ltd. The Gas Safe registered engineer holds the relevant Gas Safe registration, including CCN1 (core domestic gas safety) and CENWAT (natural gas water heaters, including combination boilers), with the registration number held on the Gas Safe card. The operative carrying out the electrical connection holds the 18th Edition (BS 7671). Both operatives are briefed on this RAMS and sign before starting. The competence and first aid training of the second operative are to be confirmed by R. Naylor with Halewood Heating Services Ltd on the pre-start walk.

9. Permits

  • Gas isolation, controlled by the Gas Safe registered engineer, with the emergency control valve and appliance valve shut and the supply confirmed off
  • Electrical isolation, controlled by the engineer, with the supply locked off, tested dead and a warning notice in place
  • Client's agreement from Mrs Okafor for access, isolations and the loss of heating and hot water. No other formal permits are expected.

10. Access & egress

Access and egress are via the front door to the kitchen/utility where the boiler is sited. Agree the route with Mrs Okafor and protect floors and walls on it. Keep the route clear of tools and materials so the household and operatives can get out. Do not prop doors with tools or leave open pipework on the route. Park the van so it does not block neighbours or the emergency route. Keep the front door and the exit from the kitchen/utility clear at all times.

11. Welfare

Client facilities (toilet and hand washing) are by arrangement with Mrs Okafor, to be agreed at the pre-start walk. Operatives also have vehicle-based provisions. Wash hands before eating, drinking or smoking, and after handling flux, inhibitor and dust. Take breaks away from the work area.

12. First aid

A first aid kit is kept in the van. The first aider on site is to be confirmed by R. Naylor before work starts. Report all injuries to Halewood Heating Services Ltd and record them in the accident book. For serious injury call 999. Cool scalds and burns under cold running water for at least 20 minutes.

13. Emergency procedures

Gas escape or smell of gas: no ignition sources or switches, open windows and doors, shut the emergency control valve if safe, evacuate everyone from the house and call the National Gas Emergency Service on 0800 111 999. Suspected carbon monoxide (headache, dizziness, nausea, collapse): switch off the appliance, open windows, get everyone out into fresh air and call 999. Fire: raise the alarm, get everyone out, call 999 and only use an extinguisher if safe. Electric shock: isolate the supply if safe, do not touch the casualty until it is safe, and call 999. Major leak: isolate the water supply and mop up. Suspect asbestos: stop work, keep people away and report it. Mrs Okafor is told the nearest exit and assembly point at the pre-start walk.

14. Environmental

Dispose of drained system water to a foul drain or as the inhibitor's Safety Data Sheet states, never to a surface water drain or garden. Remove the old boiler, pipework, packaging and other waste from site and take it away as scrap metal or waste in line with the waste duty of care. Contain dust with extraction and a vacuum, and clean up with an H-class or M-class vacuum. Keep chemicals in sealed containers and out of drains. Keep noisy work to sensible hours and tell the household and neighbours beforehand. Take the used flux, solder and inhibitor containers off site. Route the boiler condensate to a suitable discharge as set out in the manufacturer's instructions.

This document was AI-generated as a drafting aid. It is not a substitute for professional health & safety advice. It must be reviewed, verified and made site-specific by a competent person before use, briefed to all operatives, and updated when site conditions or the method change. The provider accepts no liability for use of this document on site.

Boiler replacement method statement: what it covers