Bricklaying method statement example: cavity extension wall to first floor

HSE five steps · CDM 2015
You write this
Build a cavity brick-and-block external wall for a single-storey domestic extension, up to first-floor level, working from a mobile access tower and proprietary working platform on an occupied site.
You get this
Cornerstone Brickwork Ltd (project ref CBW-4471) will build a cavity brick-and-block external wall for a single-storey domestic extension, up to first-floor level, working from a mobile access tower and proprietary working platform on an occupied site at 7 Priory Close, Leeds LS8 2R** (full postcode to be confirmed). The client and principal contractor is Mr & Mrs Ellison. Work starts Mon 15 Jun 2026 and is planned for 10 days with 3 operatives, supervised by D. Hargreaves (Site Supervisor, NVQ Level 2 Bricklaying). The family will be living in the house throughout, so the work area is fenced off from the occupants, the tower is set up and used to the manufacturer's instructions, and brick and block cutting is done with water suppression and dust controls. Items to confirm before work starts: (1) the full site postcode and the client's contact for the pre-start walk, confirmed by D. Hargreaves with Mr & Mrs Ellison; (2) the age of the existing house and whether the client holds an asbestos register or management survey for the work area, confirmed with the client before any work touches the existing wall; (3) whether the new wall has to be tied, toothed or fixed into the existing house wall, confirmed by the supervisor on the pre-start walk; (4) ground conditions and levels where the tower will stand, confirmed by the supervisor on the pre-start walk; (5) the tower height and configuration, and the manufacturer's assembly guide, confirmed by the PASMA-trained tower erector before erection; (6) whether the cement mixer and saw are 110V electric or petrol, and where the power supply comes from, confirmed by the supervisor on day one before setting up; (7) the type of cavity insulation to be fitted, so its safety data sheet can be checked, confirmed by the supervisor before ordering; (8) how materials will be delivered and where they will be stored, confirmed with the client before the first delivery; (9) whether any occupants are children, elderly or otherwise vulnerable, and which WC the operatives may use, confirmed with Mr & Mrs Ellison at the pre-start walk.

Generated for an example job to show the format. Make your own site-specific version and have a competent person review it.

Document details
ContractorCornerstone Brickwork Ltd
AuthorD. Hargreaves, Site Supervisor (NVQ Level 2 Bricklaying)
Client / Principal ContractorMr & Mrs Ellison
Site7 Priory Close, Leeds LS8 2R**
Project referenceCBW-4471
Start / durationMon 15 Jun 2026 / 10 days

1. Scope of works

Cornerstone Brickwork Ltd (project ref CBW-4471) will build a cavity brick-and-block external wall for a single-storey domestic extension, up to first-floor level, working from a mobile access tower and proprietary working platform on an occupied site at 7 Priory Close, Leeds LS8 2R** (full postcode to be confirmed). The client and principal contractor is Mr & Mrs Ellison. Work starts Mon 15 Jun 2026 and is planned for 10 days with 3 operatives, supervised by D. Hargreaves (Site Supervisor, NVQ Level 2 Bricklaying). The family will be living in the house throughout, so the work area is fenced off from the occupants, the tower is set up and used to the manufacturer's instructions, and brick and block cutting is done with water suppression and dust controls. Items to confirm before work starts: (1) the full site postcode and the client's contact for the pre-start walk, confirmed by D. Hargreaves with Mr & Mrs Ellison; (2) the age of the existing house and whether the client holds an asbestos register or management survey for the work area, confirmed with the client before any work touches the existing wall; (3) whether the new wall has to be tied, toothed or fixed into the existing house wall, confirmed by the supervisor on the pre-start walk; (4) ground conditions and levels where the tower will stand, confirmed by the supervisor on the pre-start walk; (5) the tower height and configuration, and the manufacturer's assembly guide, confirmed by the PASMA-trained tower erector before erection; (6) whether the cement mixer and saw are 110V electric or petrol, and where the power supply comes from, confirmed by the supervisor on day one before setting up; (7) the type of cavity insulation to be fitted, so its safety data sheet can be checked, confirmed by the supervisor before ordering; (8) how materials will be delivered and where they will be stored, confirmed with the client before the first delivery; (9) whether any occupants are children, elderly or otherwise vulnerable, and which WC the operatives may use, confirmed with Mr & Mrs Ellison at the pre-start walk.

2. Sequence of works

Method statement, safe system of work

  1. Before work starts, the supervisor walks the site with Mr & Mrs Ellison to confirm the items listed in the scope, agree the work area, the exclusion zone, the WC arrangement and the delivery and storage points, and note any occupants who are children or vulnerable.
  2. Pre-start asbestos check: obtain and read the client's asbestos register or management survey for the work area. If the house is pre-2000 or its age is unknown and the register does not cover the area where the new wall meets the existing building, arrange a refurbishment and demolition survey of that area before any drilling, cutting or chasing of the existing fabric. Do not start intrusive work until this is done.
  3. Hold a site induction for all 3 operatives covering this RAMS, the exclusion zone, emergency arrangements, the stop-work rule for suspect asbestos material, and who the first aider is. Everyone signs the briefing sheet.
  4. Set up the work area. Erect heras-type or similar fencing and signage across the work area and the rear garden route. Keep the side gate route and the occupants' access clear and separate from the working area, and agree a safe route for occupants to any garden, shed or outbuilding.
  5. Set up the mixing and cutting area on firm level ground away from the occupants' windows, doors and routes. Position the cement mixer and the water-fed saw, with a safe 110V supply through an RCD, cables lifted or protected, and a hand wash and eye wash station nearby.
  6. Receive and store deliveries. Keep the delivery vehicle and the pallets out of the occupants' routes, use a banksman if reversing, store bricks and blocks on firm level ground away from the fence line and cover cement and sand.
  7. Check the ground where the tower will stand, then erect the mobile access tower and proprietary working platform using only PASMA-trained operatives. Follow the manufacturer's assembly guide, fit all outriggers or stabilisers, braces and guardrails, and brake the castors. Complete the inspection record before first use.
  8. Set out the wall line, check levels and the DPC position, and lay the DPC to the agreed detail.
  9. Mix mortar in the designated area using the water-first method, keeping dust to a minimum. Use pre-measured or ready-mixed mortar where possible.
  10. Build the inner block and outer brick leaves in lifts. Keep each day's lift within the height the supervisor sets for wind and stability, brace or prop fresh walls when left overnight or in wind, and keep the cavity clear of dropped mortar.
  11. Fit wall ties at the specified spacing and fix the cavity insulation as the wall rises, handling it as the supplier's guidance says.
  12. Cut bricks and blocks with the water-fed saw only. Do not dry cut. Keep others out of the cutting area, and use an H-class or M-class vacuum for dust clean-up, never dry sweeping or compressed air.
  13. Raise the tower platform as the wall rises, only with the platform cleared of people and materials, following the manufacturer's instructions. Never move the tower with anyone or anything on it. Keep materials on the platform within the safe working load.
  14. Keep the work area tidy throughout the day. Clear loose bricks, off-cuts, mortar droppings and tools from walkways, the platform and the exclusion zone at each break and at the end of the shift.
  15. At the end of each day, secure the wall against wind, lock off or isolate the power, make the tower safe against unauthorised climbing, store tools and materials, close the side gate and confirm the exclusion fencing is intact.
  16. On completion, clear surplus materials and waste, remove the tower in the reverse order of assembly, wash down the area without letting mortar or washings reach drains, and hand the area back to Mr & Mrs Ellison.

3. Risk assessment

Built on the HSE five steps, MHSWR 1999 regulation 3 and the hierarchy of control.

  1. Fall from height from the mobile access tower and working platform while laying brick and block up to first-floor level

    Medium
    Who / how
    Bricklayers and labourers working on the tower or platform, who could suffer serious head, spinal or fatal injuries
    Existing controls
    PASMA-trained operatives, proprietary tower and platform
    L×S
    3×5=15
    Additional controls
    Avoid work at height where possible by building the lower lifts from ground level. Erect and use the tower strictly to the manufacturer's assembly guide with full guardrails, toe boards, braces and a fully boarded platform, and only on firm level ground. Fit stabilisers or outriggers and lock castors before use. A competent person inspects the tower before first use, after any change or adverse weather, and at least weekly, and records it as required by the Work at Height Regulations 2005. Access only by the internal ladder or stair, no climbing the frame, no leaning out, no stepping onto the wall or using stepladders or bricks to gain extra height. Keep the platform clear of excess materials. Safety footwear with good grip as the last line of defence.
  2. Tower instability or overturning due to soft or uneven ground, wind, overloading or moving the tower with people or materials on it

    Medium
    Who / how
    Operatives on the tower, occupants and others near the base, who could be struck or crushed
    Existing controls
    PASMA-trained erectors, manufacturer's guide
    L×S
    3×5=15
    Additional controls
    Check the ground where the tower will stand and put down spreader boards on soft or uneven surfaces. Keep to the permitted height-to-base ratio, tie or ballast as the manufacturer says, and fit all outriggers. Set a safe working load for the platform and brief it to all operatives, with no stockpiling on the platform. Never move the tower with people or materials on it. Stop work and clear the tower in high or gusty wind, and tie the tower to the structure if the manual allows. The Work at Height Regulations 2005 apply.
  3. Falling bricks, blocks, tools, mortar and debris from the platform or wall, striking people below

    Medium
    Who / how
    Operatives and occupants, including children, in the garden or passing the work area, who could suffer head and other injuries
    Existing controls
    Platform toe boards
    L×S
    3×4=12
    Additional controls
    Keep the exclusion zone fenced beneath and around the tower so nobody can walk under it. Keep the toe boards in place and do not stack materials above their height. Tether or bag tools, pass materials up by hand or hoist rather than throwing, and clear the platform at every break and end of the day. Schedule overhead work when the occupants are not near the work area. Safety helmets worn by those in the work area as backup.
  4. Occupied site: the household, visitors, children, pets and delivery drivers moving around the work area, rear garden and side gate access route

    Medium
    Who / how
    Mr & Mrs Ellison, any children or vulnerable relatives, visitors and delivery drivers, who could be struck by materials, trip over tools or hoses or enter the work area
    Existing controls
    Side gate access, occupants' routes kept clear
    L×S
    3×4=12
    Additional controls
    Fence off the whole work area with robust fencing and signs, and lock the side gate when no one is on site. Agree with Mr & Mrs Ellison a separate safe route for any access to the garden, shed or house, and brief them at the pre-start walk. Keep tools, cables and chemicals out of reach of children and pets at all times, and never leave the work area unattended without the fencing intact. Do not allow occupants into the work area, and stop work if anyone enters it. Keep noise and dust away from windows and doors by positioning the mixer and saw well clear of them.
  5. Manual handling of bricks, blocks, mortar boards, cement and sand bags, and insulation, including lifting up to the platform

    Medium
    Who / how
    All operatives, from back, shoulder, hand and arm strain and musculoskeletal injury
    Existing controls
    Experienced bricklayers
    L×S
    4×3=12
    Additional controls
    Plan the work to reduce lifting: use lighter blocks where the specification allows, have material delivered close to the work area, and use a hoist or wheelbarrow rather than carrying where practical. Keep loads at a weight each operative can lift safely under the Manual Handling Operations Regulations 1992, use mechanical handling for heavy dense blocks rather than relying on two-person lifts, and keep materials at waist height on stands or boards. Rotate tasks between operatives, take regular breaks and stack materials to avoid stooping. Report aches early. Gloves for grip as backup.
  6. Respirable crystalline silica (RCS) dust from cutting bricks, blocks and mortar, mixing sand and cement, and any drilling or fixing into existing masonry

    Medium
    Who / how
    Operatives doing the work and anyone nearby, including the household, breathing the dust, risking long-term lung disease such as silicosis, lung cancer and COPD
    Existing controls
    Water-fed saw available
    L×S
    4×4=16
    Additional controls
    Plan the work to reduce cutting and drilling, for example by using whole bricks and blocks and planning coursing. Use the water-fed saw on every cut and keep the water on, and fit on-tool extraction (M-class or H-class vacuum) or water suppression on any drill, chaser or other saw used on masonry. Cut outdoors in the designated area, away from windows and doors, and keep others away while cutting. Clean up with an H-class or M-class vacuum, never dry sweeping or compressed air. Wet down dry cement and sand spills. Then RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven. This follows the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE Construction Information Sheet CIS36 'Construction dust'. The RCS workplace exposure limit is 0.1 mg/m3 (8-hour TWA) in HSE EH40/2005.
  7. Wet cement and mortar contacting skin and eyes, and dry cement dust

    Low
    Who / how
    Bricklayers and labourers, who could suffer chemical burns, dermatitis and eye injury
    Existing controls
    Gloves and washing facilities
    L×S
    3×3=9
    Additional controls
    Use pre-bagged or ready-mixed mortar where practical to cut dust and handling. Mix with water first and add cement gently to keep dust down, and keep the mixing area away from the household. Keep a wash station with clean water and an eye wash bottle at the mixing point, wash skin promptly after contact and at breaks, and use barrier cream. Provide skin checks, and report any redness or soreness early. Follow COSHH 2002 and the supplier's Safety Data Sheet. Nitrile-coated or waterproof gauntlet gloves, long sleeves, eye protection and waterproof boots as backup.
  8. Noise from the water-fed saw, cement mixer and hand tools

    Low
    Who / how
    Operatives and the household, who could suffer hearing damage or distress
    Existing controls
    None specific
    L×S
    3×3=9
    Additional controls
    Choose the quietest suitable equipment and keep it maintained, locate the mixer and saw as far from the house and neighbours as practical, and limit the time of use. Limit noisy tasks to normal working hours and agree the times with Mr & Mrs Ellison. Rotate operatives on noisy tasks. Assess noise levels against the Control of Noise at Work Regulations 2005 action values, and provide hearing protection where the saw is used, to a suitable BS EN 352 specification.
  9. Contact with the saw blade and cement mixer moving parts, and electric shock from the power supply, cables and water used near electrical equipment

    Medium
    Who / how
    Operatives using the equipment, and anyone nearby, who could be cut, entangled, electrocuted or burned
    Existing controls
    Trained operatives
    L×S
    3×5=15
    Additional controls
    Use equipment that is in good order, fitted with guards, and used only by trained operatives under the Provision and Use of Work Equipment Regulations (PUWER) 1998. Use 110V equipment through a transformer and RCD, or battery tools where possible. Check cables and plugs before use, route cables off the ground and away from water, and keep connections out of wet areas. Isolate the power before clearing blockages or changing blades and keep guards in place. Stop and report damaged equipment. Follow the Electricity at Work Regulations 1989. Eye protection and gloves suitable for the task as backup.
  10. Slips, trips and falls at ground level from mortar, water, loose bricks, cables, hoses and uneven ground in the rear garden

    Low
    Who / how
    Operatives and occupants, who could suffer sprains, fractures and cuts
    Existing controls
    Operatives' good housekeeping
    L×S
    4×3=12
    Additional controls
    Plan storage so materials and equipment have set areas away from walkways. Lay boards or hardcore over soft or muddy ground, keep the side gate route clear, and keep cables and hoses lifted or in covers. Clear debris and mortar droppings regularly and at the end of each day, and control water from the saw so it does not pool. Maintain adequate lighting. Safety boots with good grip as backup.
  11. Freshly built wall collapsing or being blown over in wind, or being struck by materials or the tower before the mortar has gained strength

    Medium
    Who / how
    Operatives, the household and others close to the wall, who could be struck or crushed
    Existing controls
    Experienced bricklayers
    L×S
    2×5=10
    Additional controls
    Limit the height of each day's lift to what the supervisor judges safe for the wall length, wind exposure and mortar strength, and do not build faster than the mortar sets. Brace or prop unrestrained wall ends and tall freestanding sections, and cover the top of the wall at the end of each day and in rain. Keep people outside the fall zone of the wall in high wind and do not stack materials against fresh work. Stop work in strong gusts. Safety helmets and boots as backup.
  12. Disturbing unidentified asbestos-containing materials when the new wall is tied, toothed or fixed into the existing house, or when existing walls, soffits or textured coatings are drilled, cut or chased

    Medium
    Who / how
    Operatives, the household and anyone nearby, who could breathe in fibres and develop serious lung disease later
    Existing controls
    None until the check is made
    L×S
    2×5=10
    Additional controls
    Before work starts, check the client's asbestos register or management survey for the work area, as required by the Control of Asbestos Regulations 2012 (Regulation 5, identifying asbestos before work). If the building was built before 2000 or its age is not confirmed, and the register does not cover the area, a refurbishment and demolition survey of that area is needed first. Brief all operatives. Stop-work rule: if suspect material is found, stop, keep people away, do not disturb it, and report it to the supervisor and Mr & Mrs Ellison before work carries on. This is a check to be made, not a finding that asbestos is present.
  13. Cuts, abrasions and eye injuries from bricks, blocks, wall ties, trowels, cut edges, and flying fragments from cutting and bolstering

    Low
    Who / how
    Operatives, who could suffer hand cuts, lacerations and eye injuries
    Existing controls
    Gloves and eye protection
    L×S
    3×3=9
    Additional controls
    Keep tools sharp, in good condition and stored safely, and cut with the water-fed saw instead of a hammer and bolster where possible. Position wall ties and offcuts so they do not stick out, keep waste in a skip or bag and clear it often, and make sure no one works below while others cut or trim. Cut-resistant gloves (BS EN 388) and safety glasses or goggles (BS EN 166) as backup.
  14. Adverse weather: wind, rain, cold, heat and strong sun while working on the tower and in the garden

    Low
    Who / how
    Operatives, who could suffer slips, falls from the platform, cold or heat stress and sunburn
    Existing controls
    Operatives monitor conditions
    L×S
    3×3=9
    Additional controls
    Check the forecast daily and plan the work so exposed tower work happens in calmer weather. Stop tower work in high or gusty wind or lightning, rain that makes the platform slippery, or when visibility is poor. Cover the wall and materials overnight. Provide drinking water and shade, schedule breaks in heat and cold, and use sunscreen. Weatherproof and warm clothing as backup.
  15. Deliveries and unloading of bricks, blocks, sand and cement, including vehicle movements near the house and the occupants' routes

    Low
    Who / how
    Operatives, the household, drivers and passers-by, who could be struck by vehicles or loads or suffer crush injuries
    Existing controls
    Delivery arranged in advance
    L×S
    2×4=8
    Additional controls
    Agree delivery times and the drop-off point at the pre-start walk, keep the household clear during unloading, and use a trained banksman for reversing. Do not stack pallets higher than the stable height, keep them level and out of walkways. If a lorry-mounted crane is used, the supplier's lifting operation must comply with the Lifting Operations and Lifting Equipment Regulations (LOLER) 1998, and nobody stands under the load. Hi-vis clothing and safety boots as backup.

4. COSHH assessment

Built on COSHH 2002 regulations 6 and 7 and HSE guidance L5.

Check each entry against the supplier's Safety Data Sheet before work starts. Take workplace exposure limits from HSE EH40/2005.

Cement and mortar (cement and sand)

Task or use
Mixing mortar in the cement mixer and laying brick and block for the cavity wall
Route of exposure
Skin contact, eye contact and inhalation of dust when handling dry cement and sand
Who could be harmed
Bricklayers and labourers mixing and laying mortar. Anyone nearby, including the household, could breathe in dust or get splashes on their skin.
Hazards
Wet cement is alkaline and can cause skin burns, dermatitis and serious eye damage. Dry cement dust can irritate the nose, throat and lungs. The exact hazards depend on the product, so check section 2 of the supplier's Safety Data Sheet.
Controls
  1. Eliminate or reduce the need to mix on site by using ready-mixed or pre-bagged mortar where practical.
  2. Substitute low-dust or reduced-chromate products where available.
  3. Mix in a designated area away from the house and the occupants' routes, adding water first to keep dust down, and use the mixer with its guard in place.
  4. Limit quantities mixed at one time and the time anyone is exposed, and keep others away from the mixing area.
  5. Provide a wash station with clean water and an eye wash bottle at the mixing area, and keep it topped up.
  6. Wash skin promptly after contact, use barrier cream, and do not wear contaminated clothing or boots.
PPE
  • Waterproof, cement-resistant gloves to the specification in the Safety Data Sheet
  • Eye protection to BS EN 166 against splashes and dust
  • Long sleeves and waterproof boots
  • Dust mask or RPE only as the Safety Data Sheet and the risk assessment require
Storage and disposal
Store bags dry, off the ground, covered and away from the household. Dispose of set mortar and empty bags as construction waste through the skip or licensed carrier. Do not wash out the mixer or tools where the washings could reach drains or soil.
First aid and spillage
Skin: remove contaminated clothing and wash the area thoroughly with clean water, then seek medical help if burns or irritation develop. Eyes: flush with clean water immediately for at least 10 minutes and get medical advice. Spillage: scoop up dry spills carefully without making dust, and let wet spills set before removing them.
Health surveillance
Basic skin checks are needed for operatives who regularly handle wet cement because of the risk of dermatitis. Operatives report any skin problem at once and the supervisor arranges a check.
Check against the Safety Data Sheet
Before work starts, get the Safety Data Sheet for the cement and mortar products and confirm the hazard statements in section 2, the PPE specification, first aid measures and disposal advice. Take workplace exposure limits from HSE EH40/2005. Confirm the products to be used with the supervisor. This assessment follows COSHH 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).

Respirable crystalline silica dust from cutting bricks, blocks and mortar, and any drilling or fixing into masonry

Task or use
Cutting facing bricks and concrete blocks with the water-fed cut-off saw or masonry bench saw, and cleaning up dust and waste
Route of exposure
Inhalation of fine dust, and eye contact
Who could be harmed
Operatives cutting and cleaning up, and anyone nearby, including the household, who could develop silicosis, lung cancer or COPD after long-term exposure
Hazards
Breathing in fine silica dust can cause serious and permanent lung damage, often years after exposure. The amount of silica depends on the brick and block products used, so check section 2 and the composition information in the supplier's Safety Data Sheets.
Controls
  1. Plan the work to reduce cutting, for example by using whole bricks and blocks and setting out the coursing to avoid cuts.
  2. Use the water-fed saw on every cut and keep the water supply working, and use on-tool extraction (M-class or H-class vacuum) on any drill or other tool used on masonry.
  3. Cut outdoors in a designated area away from windows, doors and the occupants' routes, and keep others away while cutting.
  4. Clean up with an H-class or M-class vacuum or by wet methods, never dry sweeping or compressed air.
  5. Limit the number of operatives cutting and the time spent cutting.
PPE
  • RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven
  • Eye protection to BS EN 166
  • Work clothes that are brushed or vacuumed down, not blown down, and washed regularly
Storage and disposal
Store cut bricks and blocks tidily, away from walkways. Collect slurry and dust waste in containers or bags and dispose of them as construction waste via the skip or licensed carrier. Do not let slurry reach drains.
First aid and spillage
If dust is breathed in, move the person to fresh air and seek medical advice if they have breathing difficulty. For eye contact, flush with clean water for at least 10 minutes. For dust spills, wet them or use an H-class or M-class vacuum, and do not dry sweep.
Health surveillance
Respiratory health surveillance is likely to be needed for operatives who are regularly exposed to silica dust. The supervisor and the contractor's occupational health provider confirm this against the risk assessment. Operatives report any cough or breathlessness early.
Check against the Safety Data Sheet
Before work starts, check the Safety Data Sheets or product information for the brick and block products for composition and silica content, and confirm the PPE and RPE specification. Take the workplace exposure limit from HSE EH40/2005. This assessment follows COSHH 2002, HSE's COSHH guidance (L5, the COSHH Approved Code of Practice) and CIS36 'Construction dust'.

5. Plant & equipment

  • Mobile access tower with proprietary working platform, guardrails, toe boards, braces and outriggers or stabilisers (PASMA-trained erectors)
  • Cement mixer (power source to be confirmed)
  • Water-fed cut-off saw or masonry bench saw
  • 110V transformer, RCD and protected cables if electric equipment is used
  • H-class or M-class vacuum for dust clean-up
  • Hand tools: trowels, levels, lines, bolsters, hammers, tape measures
  • Wheelbarrow, spreader boards and mortar boards
  • Fencing, signage and barriers for the exclusion zone
  • Wash station and eye wash bottle at the mixing area

6. Materials / COSHH

Materials: facing bricks, concrete blocks, cement, sand, wall ties, cavity insulation and DPC. Hazardous substances are wet cement and mortar (skin burns, dermatitis, eye damage) and respirable crystalline silica dust from cutting bricks, blocks and mortar. The cavity insulation type is to be confirmed, and its Safety Data Sheet or product information must be checked before it is cut or handled. Detailed COSHH assessments are given separately for cement and mortar and for silica dust, to COSHH 2002.

7. PPE

  • Safety helmet to BS EN 397 where there is a risk of falling objects or overhead work
  • Safety boots with steel or composite toecap and midsole (BS EN ISO 20345)
  • Hi-vis clothing
  • Cut-resistant gloves (BS EN 388) and waterproof, cement-resistant gloves for mixing and laying
  • Eye protection (BS EN 166)
  • Hearing protection (BS EN 352) when using the saw and mixer
  • FFP3 disposable RPE (BS EN 149) for cutting, face-fit tested and worn clean shaven
  • Long sleeves and trousers, and sunscreen in hot weather. PPE is the last line of defence, after the controls in the risk assessment.

8. Competence & training

All 3 operatives hold NVQ Level 2 Bricklaying and valid CSCS cards, and are PASMA trained for mobile access towers. The supervisor, D. Hargreaves, holds NVQ Level 2 Bricklaying and is the competent person for this RAMS. All operatives receive a site induction and briefing on this RAMS before starting and sign the briefing sheet. Anyone using the saw or mixer must be trained and competent on that equipment. Face-fit testing records for FFP3 RPE are checked before cutting begins. The supervisor confirms that the operative inspecting the tower is competent to do so.

9. Permits

  • No permit to work is expected for this job. Confirm with the client at the pre-start walk that none is needed.
  • Tower inspection record completed before first use, after any change or adverse weather and at least weekly, kept on site (Work at Height Regulations 2005).
  • Daily briefing sheet signed by all operatives.

10. Access & egress

Access is via the side gate to the rear garden work area. Occupants' routes are kept clear and separate from the work area by fencing, and the side gate is locked when no one is on site. The route past the house, the delivery point and the fire escape route from the house are agreed with Mr & Mrs Ellison at the pre-start walk. Access to the platform is by the tower's internal ladder or stair only, with no climbing of the frame. Keep the route clear of materials, cables and hoses at all times.

11. Welfare

The client's WC is available by arrangement with Mr & Mrs Ellison, to be confirmed at the pre-start walk. A site cabin and the operatives' own provisions cover rest breaks, drinking water, hand washing and eating. A wash station with clean water is kept at the mixing area for skin washing. Operatives wash their hands before eating, drinking or smoking, and the supervisor checks that facilities are kept clean and the household's property is respected.

12. First aid

A first aid kit is kept in the site cabin and a named first aider on the 3-person team is identified at the induction. The nearest A&E is found and recorded before start. A clean-water eye wash bottle is kept at the mixing area for splashes. Any injury, however minor, is reported to D. Hargreaves and recorded in the accident book. Serious accidents and reportable incidents are reported under RIDDOR 2013 by the contractor.

13. Emergency procedures

In an emergency, stop work, make the work safe if it can be done without risk, and call 999 if anyone is injured or there is a fire. Fall from the tower: do not move the casualty unless there is immediate danger, call 999 and give first aid. Fire: raise the alarm, evacuate to the agreed assembly point at the front of the property, and keep the household and operatives together and accounted for. Power cut or electric shock: isolate the supply if safe, and do not touch a casualty still in contact with live equipment. Suspect asbestos found: stop, keep people away, and report it to the supervisor and the client. The supervisor gives the postcode and site address (to be confirmed, LS8 2R**) to the emergency services. The emergency assembly point is agreed at the induction.

14. Environmental

Keep mortar and washings out of drains, soil and the neighbours' property, and wash out the mixer and tools in a designated area where the water can be contained. Collect cutting slurry and dust and dispose of it as construction waste. Segregate and remove waste in a skip or via a licensed waste carrier, with no burning on site. Keep noise down and work within normal working hours agreed with the client. Keep dust away from windows, doors and neighbours by using water suppression. Store materials tidily and cover them from rain to prevent run-off. Keep fuel and oil stored in a drip tray if petrol equipment is used. Leave the garden and access route clean and tidy at the end of the job.

This document was AI-generated as a drafting aid. It is not a substitute for professional health & safety advice. It must be reviewed, verified and made site-specific by a competent person before use, briefed to all operatives, and updated when site conditions or the method change. The provider accepts no liability for use of this document on site.

Bricklaying method statement: what it covers