First-fix carpentry method statement example: first-fix carpentry, new-build plot

HSE five steps · CDM 2015
You write this
First-fix carpentry to a new-build plot under construction: install floor joists, erect timber stud partitions and fit door linings, working from open floor edges and the leading edge.
You get this
Timberline Carpentry Contractors Ltd will carry out first-fix carpentry to a new-build plot under construction at Plot 14, Willowbrook Grange, Nottingham NG12 3H**, for Kestrel Homes (Principal Contractor), project reference TCC-4420. The work is to install floor joists, erect timber stud partitions and fit door linings, working from open floor edges and the leading edge. Start date is Tue 23 Jun 2026 for 5 days, with 2 CSCS carded carpenters. The work will be done under the Principal Contractor's permit to work, using the Principal Contractor's edge protection, site scaffold and stairs, and the controls set out in this document. Items to confirm before work starts: (1) the full site postcode, confirmed with Kestrel Homes at the induction; (2) the floor and wall construction (masonry, block, concrete or timber frame) and what the joist hangers, sole plates and door linings will be fixed into, confirmed with the Site Manager on the pre-start walk. This RAMS assumes some fixing into block or concrete, so the silica controls are included; (3) floor heights, stairwell and service openings, and the condition of the edge protection at each floor level, confirmed with the Site Manager on the pre-start walk; (4) the adhesive products to be used, with their Safety Data Sheets, confirmed by the Lead Carpenter before the adhesives are brought to site; (5) the fuel cell type for the gas nail gun, and where fuel cells may be stored on site, confirmed with the Site Manager at induction; (6) the Principal Contractor's rescue arrangements for a person who falls or is suspended, confirmed at induction.

Generated for an example job to show the format. Make your own site-specific version and have a competent person review it.

Document details
ContractorTimberline Carpentry Contractors Ltd
AuthorJ. Whitaker, Lead Carpenter (NVQ Level 3, CSCS Gold)
Client / Principal ContractorKestrel Homes (Principal Contractor)
SitePlot 14, Willowbrook Grange, Nottingham NG12 3H**
Project referenceTCC-4420
Start / durationTue 23 Jun 2026 / 5 days

1. Scope of works

Timberline Carpentry Contractors Ltd will carry out first-fix carpentry to a new-build plot under construction at Plot 14, Willowbrook Grange, Nottingham NG12 3H**, for Kestrel Homes (Principal Contractor), project reference TCC-4420. The work is to install floor joists, erect timber stud partitions and fit door linings, working from open floor edges and the leading edge. Start date is Tue 23 Jun 2026 for 5 days, with 2 CSCS carded carpenters. The work will be done under the Principal Contractor's permit to work, using the Principal Contractor's edge protection, site scaffold and stairs, and the controls set out in this document. Items to confirm before work starts: (1) the full site postcode, confirmed with Kestrel Homes at the induction; (2) the floor and wall construction (masonry, block, concrete or timber frame) and what the joist hangers, sole plates and door linings will be fixed into, confirmed with the Site Manager on the pre-start walk. This RAMS assumes some fixing into block or concrete, so the silica controls are included; (3) floor heights, stairwell and service openings, and the condition of the edge protection at each floor level, confirmed with the Site Manager on the pre-start walk; (4) the adhesive products to be used, with their Safety Data Sheets, confirmed by the Lead Carpenter before the adhesives are brought to site; (5) the fuel cell type for the gas nail gun, and where fuel cells may be stored on site, confirmed with the Site Manager at induction; (6) the Principal Contractor's rescue arrangements for a person who falls or is suspended, confirmed at induction.

2. Sequence of works

Method statement, safe system of work

  1. Before starting, the Lead Carpenter confirms the items listed in the scope with the Site Manager on the pre-start walk, and obtains the Principal Contractor permit to work and site induction for both operatives
  2. Check the Principal Contractor's edge protection, stair access and scaffold at each working level, and confirm it has been inspected and tagged. Do not start if guardrails, toe boards or covers are missing or damaged
  3. Hold a task briefing for both operatives covering this method statement, the edge and opening hazards, the stop-work rules, emergency arrangements and the rescue plan. Both sign the briefing record
  4. Mark off and sign the area below each working level as an exclusion zone, and agree with the Site Manager that no other trades work underneath while joists and partitions are being installed
  5. Set up a cutting area at ground level or on a stable bench in a well-ventilated spot, away from edges and openings, with the mitre saw connected to dust extraction. Pre-cut timber to length there so cutting at the edge is kept to a minimum
  6. Check all timber, joist hangers and fixings delivered. Confirm the load path for deliveries with the Site Manager, and store timber flat, supported and away from edges and stair openings so it cannot be knocked off or overload the deck
  7. Move joists and studwork to the working level by the agreed route, using mechanical aid where the Principal Contractor provides it, and by two-person lifts where it is not. Do not carry long lengths up ladders or alone
  8. Set out joist positions from the drawings. Fit joists and hangers working back from a protected edge, and fix each joist before the next is lifted. Do not stand or walk on unfixed joists
  9. Lay boards or deck sheets as a working platform as soon as joists are fixed, working progressively from the protected area so that operatives are never working on bare joists. Fix and brace sheets securely before use
  10. Where a gap or opening is left in the deck, cover it with a secured, marked cover or guard it with a guardrail before moving on. Only the Principal Contractor's edge protection may be altered, and only with the Site Manager's agreement under the permit. If it must be removed to load in or fit joists, stop, agree the arrangement and reinstate it before work continues
  11. At the leading edge, work only from the deck behind the Principal Contractor's guardrail or advance edge protection. If no suitable edge protection is in place for a task at the leading edge, stop work and report to the Site Manager. Do not lean over, reach out or work from the joist ends
  12. Mark out partition positions. Fix sole plates, using on-tool extraction on every drill that goes into block or concrete, and use fixings recommended for the base material
  13. Erect stud partitions section by section, plumbing and temporarily bracing each section before leaving it. Do not leave an unbraced partition standing unattended or overnight
  14. Fit door linings, using stable stepladders or a podium/low-level platform for work above reach, with someone footing or the equipment set on the deck clear of edges and openings. Do not use ladders to work near openings or the leading edge
  15. Use adhesives sparingly, following the Safety Data Sheet. Keep lids on containers when not in use, and take containers away from edges
  16. Keep the work area tidy throughout. Collect offcuts, packaging and nails at the end of each task and put them in the Principal Contractor's skip. Clean up dust with an M-class or H-class vacuum, never dry sweeping or compressed air
  17. Charge batteries only in the agreed safe area, and store fuel cells and flammable materials as agreed with the Site Manager. At the end of each shift, secure tools and materials, check edge protection and covers are in place, and report any damage
  18. On completion, inspect the work, remove all waste, leave the area clear and handover to the Site Manager. Return the permit to work and report any near misses or defects

3. Risk assessment

Built on the HSE five steps, MHSWR 1999 regulation 3 and the hierarchy of control.

  1. Working at height: fall from open floor edges and the leading edge while installing joists, partitions and linings

    Medium
    Who / how
    The 2 operatives, who could suffer fatal or life-changing injuries from a fall; others on the site if the person falling strikes them
    Existing controls
    Principal Contractor edge protection, site scaffold and stairs, permit to work, CSCS carded operatives
    L×S
    3×5=15
    Additional controls
    Under the Work at Height Regulations 2005, avoid work at height where possible: pre-cut and pre-assemble at ground level. Inspect edge protection before each shift and do not start if it is missing or damaged. Work only from a protected deck, behind guardrails, laying boards progressively as joists are fixed. Do not remove or alter edge protection without agreement under the permit, and reinstate it straight away. Stop-work rule at the leading edge where protection is not in place. Briefing on rescue arrangements before work starts. Suitable footwear and a hard hat are the last line of defence.
  2. Falls through floor openings, stairwell voids and gaps between unfixed joists before decking is laid

    Medium
    Who / how
    The 2 operatives; anyone below hit by the person or by falling materials
    Existing controls
    Site induction, edge protection by Principal Contractor
    L×S
    3×5=15
    Additional controls
    Do not walk on unfixed joists. Fix joists and lay a working deck progressively. Cover or guard all openings with secured, marked covers or guardrails before moving on. Agree with the Site Manager who is responsible for opening covers and check at the start of each shift. Hard hat and non-slip footwear as backup.
  3. Falling materials, tools and offcuts from the deck or leading edge

    Medium
    Who / how
    Anyone below, including other trades, site staff and visitors; head and impact injuries
    Existing controls
    Edge protection with toe boards, site rules on hard hats
    L×S
    3×4=12
    Additional controls
    Keep an exclusion zone below the work, agreed with the Site Manager, and no other trades below while joists and partitions are installed. Keep materials back from edges and stacked stably. Tool lanyards or a tool belt for hand tools. Remove offcuts regularly. Hard hats (BS EN 397) worn by all as the last line of defence.
  4. Instability or collapse of joists, unbraced stud partitions and stored timber

    Medium
    Who / how
    The 2 operatives and anyone nearby; crush injuries and falls
    Existing controls
    Competent carpenters; work to drawings
    L×S
    3×4=12
    Additional controls
    Fix joists and hangers fully before loading and build the deck progressively. Brace each partition section temporarily as it is erected and do not leave it unbraced. Limit stacked timber to what the deck can carry and keep it away from edges. Check structure is stable before the next stage. Safety footwear (BS EN ISO 20345) as backup.
  5. Manual handling of floor joists, long lengths of studwork, door linings and sheet material

    Low
    Who / how
    The 2 operatives; back, shoulder and hand injuries, and trips while carrying
    Existing controls
    Competent carpenters, 2 operatives available
    L×S
    4×3=12
    Additional controls
    Under the Manual Handling Operations Regulations 1992, reduce handling: have timber delivered close to the point of use, and use mechanical aid where the Principal Contractor provides it. Cut timber to smaller sections where the design allows. Two-person lifts for long or heavy lengths, with a clear route and a plan before lifting. Rotate tasks and take breaks. Gloves for grip and splinters as backup.
  6. Cuts and contact injuries from the cordless circular saw and mitre saw

    Medium
    Who / how
    The operator and anyone nearby; severe cuts, amputations, kickback injuries
    Existing controls
    Operatives trained on abrasive wheels, guards fitted on tools
    L×S
    3×4=12
    Additional controls
    Under PUWER 1998, use only tools with working guards, in good condition, with the correct blade for the material. Cut at a stable bench rather than on joists wherever possible and clamp the work. Remove the battery when changing blades. Keep others clear of the cutting area. Cut-resistant gloves are not worn when operating saws with a rotating blade because of entanglement risk. Eye protection (BS EN 166) as backup.
  7. Nail gun injuries: accidental discharge, ricochet, nails through timber, and fuel cell leaks

    Medium
    Who / how
    The operator and people nearby; puncture wounds to hands, feet and eyes
    Existing controls
    Operatives trained on the nail gun; tool manufacturer's guard
    L×S
    3×4=12
    Additional controls
    Under PUWER 1998, use the sequential trip setting where it is available, keep fingers away from the trigger when not firing, and disconnect the power source when clearing a jam. Never point at anyone or fire near the edge or at an unsupported workpiece. Keep fuel cells in the agreed store and away from heat. Hold work firmly and keep others clear. Eye protection (BS EN 166) and safety footwear as backup.
  8. Wood dust from sawing softwood joists, CLS studwork and door linings

    Medium
    Who / how
    The 2 operatives and others nearby; eye, nose and throat irritation, dermatitis and asthma
    Existing controls
    Cutting outdoors or in a ventilated area where possible
    L×S
    4×3=12
    Additional controls
    Under COSHH 2002, cut timber to length off site or at the supplier where possible. Use the mitre saw and circular saw with on-tool extraction connected to an M-class vacuum, and cut in a well-ventilated area. Clean up with a vacuum, never dry sweeping or compressed air. Limit the number of people nearby. Disposable respirators (FFP3 or as set by the risk assessment) and eye protection as backup.
  9. Respirable crystalline silica (RCS) dust

    Medium
    Who / how
    The operatives doing the work and anyone nearby breathing the dust; long-term lung disease including silicosis and lung cancer
    Existing controls
    None specific; work limited to fixings only
    L×S
    3×4=12
    Additional controls
    Under COSHH 2002 and HSE guidance CIS36 Construction dust, plan the work to cut down on drilling and fixing into masonry, block and concrete. Use on-tool extraction (M-class or H-class vacuum) or water suppression on every drill, chaser and saw used on these materials. Keep others away and clean up with an H-class or M-class vacuum, never dry sweeping or compressed air. Then use RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven. The workplace exposure limit for RCS is 0.1 mg/m3 (8-hour TWA) in HSE EH40/2005.
  10. Noise from saws, nail gun and drills, plus other trades working nearby

    Low
    Who / how
    The 2 operatives and nearby workers; hearing damage and tinnitus
    Existing controls
    Cordless tools, which are quieter than petrol equivalents
    L×S
    4×2=8
    Additional controls
    Under the Control of Noise at Work Regulations 2005, choose the quietest suitable tools and keep them maintained. Cut away from other trades and at times agreed with the Site Manager. Limit time on noisy tasks, and rotate if needed. Hearing protection (BS EN 352) to be worn where noise is high, with the type chosen to suit the task.
  11. Hand-arm vibration from drill/driver, circular saw and nail gun

    Low
    Who / how
    The 2 operatives; hand-arm vibration syndrome and white finger from repeated use
    Existing controls
    Cordless tools used for short periods
    L×S
    3×2=6
    Additional controls
    Under the Control of Vibration at Work Regulations 2005, select lower-vibration tools, keep blades and bits sharp, and share heavy-use tasks between both operatives. Take breaks from continuous use. Report numbness or tingling to the Lead Carpenter. Gloves to keep hands warm as backup.
  12. Slips, trips and falls on the same level from offcuts, packaging, nails, cables and uneven decking

    Low
    Who / how
    The 2 operatives and other trades; sprains, fractures and puncture wounds
    Existing controls
    Site housekeeping rules
    L×S
    4×3=12
    Additional controls
    Keep walkways, stairs and decks clear, and collect offcuts and packaging at the end of each task. Use cordless tools to avoid trailing leads. Remove or bend over protruding nails. Good lighting. Safety footwear with penetration-resistant midsole (BS EN ISO 20345) as backup.
  13. Other trades, deliveries and plant moving around the plot and plot access

    Low
    Who / how
    The 2 operatives, other trades, site staff and visitors; struck by vehicle or hit by falling materials
    Existing controls
    Principal Contractor site rules, induction, marshalled deliveries
    L×S
    3×4=12
    Additional controls
    Coordinate daily with the Site Manager on other trades working on the plot and deliveries. Keep an exclusion zone around the working area and sign it. Keep to designated pedestrian routes and keep clear of plant. Where a crane or telehandler lifts timber, the lifting is the Principal Contractor's responsibility under LOLER 1998. High-visibility clothing and safety footwear as backup.
  14. Work from stepladders, trestles or low-level platforms when fitting door linings above reach

    Medium
    Who / how
    The 2 operatives; falls from low height, particularly near openings
    Existing controls
    Competent carpenters
    L×S
    3×4=12
    Additional controls
    Under the Work at Height Regulations 2005, use a podium or low-level platform in preference to a stepladder wherever possible. Check equipment before use, set it on firm, level decking away from edges and openings, and do not overreach. Keep three points of contact if a stepladder is used for short, light tasks. Safety footwear with good grip as backup.
  15. Electric shock or fire from battery chargers and cordless tool batteries

    Low
    Who / how
    The 2 operatives and others on site; electric shock, burns and fire
    Existing controls
    Cordless tools reduce cable use
    L×S
    2×3=6
    Additional controls
    Under the Electricity at Work Regulations 1989, use only the manufacturer's chargers and batteries, with in-date PAT or inspection labels, and charge them in the agreed area away from combustible material, never overnight unattended. Inspect equipment for damage before use. Do not use damaged batteries or chargers. Fire extinguisher location confirmed at induction.
  16. Adverse weather: wind, rain and cold affecting the open frame, wet timber and exposed decks

    Low
    Who / how
    The 2 operatives; slips, falls from wind and cold-related illness
    Existing controls
    Drying room and welfare cabins provided by the Principal Contractor
    L×S
    3×3=9
    Additional controls
    Check the forecast at the start of each shift and do not work at the leading edge or lift sheet material in high wind. Cover timber and decking to keep it dry and remove standing water. Plan breaks to warm up and dry out. Appropriate waterproof and thermal clothing as backup.
  17. Skin and eye contact with adhesives and the fumes from them

    Low
    Who / how
    The operatives using the adhesives; skin irritation, dermatitis, eye damage and respiratory irritation
    Existing controls
    Used in small quantities
    L×S
    2×2=4
    Additional controls
    Under COSHH 2002, choose water-based or low-solvent adhesives where they are suitable and confirm the product's Safety Data Sheet before use. Use small quantities and keep containers closed, with the area ventilated. No eating or drinking where adhesives are used. Gloves and eye protection to the specification in the Safety Data Sheet as backup.

4. COSHH assessment

Built on COSHH 2002 regulations 6 and 7 and HSE guidance L5.

Check each entry against the supplier's Safety Data Sheet before work starts. Take workplace exposure limits from HSE EH40/2005.

Softwood timber dust from sawing joists, CLS studwork and door linings

Task or use
Produced when cutting, drilling and trimming softwood joists, studwork and door linings with the circular saw, mitre saw and hand tools
Route of exposure
Inhalation of airborne dust; skin and eye contact
Who could be harmed
The 2 operatives, and anyone nearby while cutting is going on, by irritation of the eyes, nose, throat and skin, and by breathing problems and asthma with repeated exposure
Hazards
Wood dust can irritate the eyes, nose, throat and skin, and can cause dermatitis and occupational asthma. If any timber has been treated or preserved, check section 2 of the supplier's Safety Data Sheet or product information for further hazards. Do not assume the timber is untreated.
Controls
  1. Elimination: have timber cut to length by the supplier or in a ventilated area off the working floor wherever possible
  2. Substitution: use pre-cut or pre-assembled components where the design allows
  3. Engineering: use on-tool extraction connected to an M-class vacuum on the saws, and cut in a well-ventilated area or outdoors
  4. Administrative: limit the amount of cutting on the deck, keep others away from the cutting area, clean up with a vacuum, never dry sweeping or compressed air, and wash hands before eating or drinking
PPE
  • Disposable respirator (FFP3 or as set by the risk assessment), face-fit tested
  • Eye protection (BS EN 166)
  • Gloves to protect against splinters and skin contact
Storage and disposal
Collect dust and offcuts in the Principal Contractor's skip or bags. Do not burn timber offcuts on site. Take any treated timber waste for separate disposal as the Principal Contractor directs.
First aid and spillage
Eyes: rinse with clean water or an eyewash for at least 10 minutes and seek medical help if irritation continues. Skin: wash with soap and water. If breathing problems develop, move to fresh air and seek medical advice. Clean up dust with a vacuum, not by sweeping or compressed air.
Health surveillance
Not expected for short, occasional exposure with extraction in use. If exposure becomes regular, the employer must review whether respiratory or skin health surveillance is needed. Operatives report any skin or breathing symptoms to the Lead Carpenter.
Check against the Safety Data Sheet
Confirm from the timber supplier's information, and the Safety Data Sheet for any treated timber, whether the timber has been treated and what the hazards are in section 2. Check the workplace exposure limit for wood dust in HSE EH40/2005 before work starts. Cite COSHH 2002 and HSE L5 (COSHH Approved Code of Practice).

Respirable crystalline silica (RCS) dust from drilling or fixing into masonry, block or concrete

Task or use
Produced when drilling or fixing sole plates, joist hangers, door linings or partition fixings into block, brick or concrete
Route of exposure
Inhalation of fine dust; eye contact
Who could be harmed
The operatives doing the work and anyone nearby breathing the dust, risking long-term lung disease
Hazards
Fine silica dust can damage the lungs over time, including silicosis, chronic lung disease and lung cancer. Exposure to the dust is not always visible, and harm builds up over years. The detail of the hazard is set out in the risk assessment row for RCS.
Controls
  1. Elimination: plan the work to reduce drilling into masonry, for example by using fixings and details that avoid it where the design allows
  2. Substitution: use low-dust fixing methods where they are suitable, such as impact fixings without drilling where the manufacturer allows
  3. Engineering: use on-tool extraction (M-class or H-class vacuum) or water suppression on every drill used on these materials
  4. Administrative: limit the time and number of fixings drilled, keep others away, clean up with an H-class or M-class vacuum, never dry sweeping or compressed air, and wash hands before eating
PPE
  • RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven
  • Eye protection (BS EN 166)
  • Disposable or washable overalls kept clean of dust
Storage and disposal
Collect dust in the vacuum's sealed bag or container and dispose of it as the Principal Contractor directs. Keep used overalls in a bag and wash them away from the home where possible. Do not blow dust off clothing.
First aid and spillage
Eyes: rinse with clean water for at least 10 minutes. If dust is inhaled, move to fresh air and seek medical advice if symptoms develop. Clean up settled dust with an H-class or M-class vacuum, never by dry sweeping or compressed air.
Health surveillance
Not expected for occasional, short-duration drilling with extraction. If operatives are regularly exposed, the employer must review whether respiratory health surveillance is needed. Any cough or breathing problems must be reported.
Check against the Safety Data Sheet
Confirm from the Safety Data Sheet or product information for the block, brick or concrete, and from HSE EH40/2005 for exposure limits, what the hazards are before work starts. Cite COSHH 2002 and HSE L5 (COSHH Approved Code of Practice).

Adhesives

Task or use
Used to bond door linings and timber fixings during first-fix carpentry
Route of exposure
Skin contact; eye contact; inhalation of vapour
Who could be harmed
The operatives using the adhesives, by skin and eye irritation, and by breathing in vapours in enclosed or poorly ventilated areas
Hazards
The hazards depend on the product. Many adhesives can irritate the skin and eyes, and some can cause allergic skin reactions or breathing problems. Check section 2 of the supplier's Safety Data Sheet for the hazards of the product actually used. Never assume they are low risk.
Controls
  1. Elimination: use mechanical fixings instead of adhesive where the design and manufacturer's guidance allow
  2. Substitution: choose a water-based, solvent-free or low-solvent product where it is suitable for the job
  3. Engineering: use in a well-ventilated area and apply with a cartridge gun rather than by hand to limit contact
  4. Administrative: use the smallest quantity needed, keep containers closed, keep others away, no eating, drinking or smoking where adhesive is used, and wash hands afterwards
PPE
  • Gloves to the specification in the Safety Data Sheet
  • Eye protection (BS EN 166)
  • RPE only if the Safety Data Sheet requires it, to the specification it states
Storage and disposal
Store in the original, labelled container with the lid closed, in the Principal Contractor's agreed storage area away from heat and ignition sources. Let empty or part-used cartridges and containers be disposed of as the Safety Data Sheet and the Principal Contractor direct. Do not pour into drains.
First aid and spillage
Skin: wash off with soap and water. Eyes: rinse with clean water for at least 10 minutes and get medical advice. If inhaled, move to fresh air. Spillage: wipe up small spills with absorbent material, put it in a sealed bag for disposal, and ventilate the area. Follow the Safety Data Sheet.
Health surveillance
None is expected for occasional use of non-sensitising products. If the Safety Data Sheet shows the product is a respiratory or skin sensitiser, speak to the Lead Carpenter before use about whether health surveillance is needed.
Check against the Safety Data Sheet
Before work starts, obtain the Safety Data Sheet for each adhesive and confirm the hazards in section 2, the PPE and RPE specification, storage, spillage and first-aid advice, and flammability. Check any workplace exposure limits in HSE EH40/2005. Cite COSHH 2002 and HSE L5 (COSHH Approved Code of Practice).

5. Plant & equipment

  • Cordless circular saw
  • Mitre saw with dust extraction
  • First-fix nail gun (gas/cordless) with fuel cells or batteries
  • Drill/driver with on-tool dust extraction for masonry fixings
  • Hand tools
  • M-class or H-class vacuum for dust extraction and clean-up
  • Stepladders or podium/low-level platform, as agreed with the Principal Contractor
  • Battery chargers, kept in the agreed charging area

6. Materials / COSHH

Materials in use: softwood timber joists, studwork CLS timber, door linings, joist hangers, fixings and adhesives. The substances covered by COSHH assessments are softwood dust from cutting, respirable crystalline silica dust from fixing into masonry or concrete, and the adhesives. Safety Data Sheets must be on site before the adhesives are used.

7. PPE

  • Hard hat (BS EN 397)
  • Safety footwear with penetration-resistant midsole (BS EN ISO 20345)
  • High-visibility clothing
  • Safety glasses or goggles (BS EN 166)
  • Hearing protection (BS EN 352) where noise is high
  • Gloves suited to the task, but not when using rotating saw blades
  • Disposable respirator (FFP3 or as set by the risk assessment), face-fit tested and worn clean shaven
  • Weatherproof and thermal clothing as needed

8. Competence & training

Both operatives are CSCS carded carpenters with NVQ Level 3 and are trained on abrasive wheels and nail guns. J. Whitaker, Lead Carpenter (NVQ Level 3, CSCS Gold), is the competent person for this RAMS. Before starting, both operatives attend the Principal Contractor's induction and the task briefing on this RAMS, and sign the briefing record. They must also have face-fit testing for the RPE they will use. Confirmation of face-fit testing and of any working at height training is to be given to the Site Manager at induction.

9. Permits

  • Principal Contractor permit to work, obtained before work starts and returned on completion
  • Hot works permit not required
  • Any alteration to edge protection or floor opening covers must be agreed with the Site Manager under the permit

10. Access & egress

Access and egress via the site scaffold and stairs provided by the Principal Contractor, with edge protection provided and maintained by the Principal Contractor. Keep stairs and walkways clear of materials. Do not use unfinished openings or the leading edge to get in or out. Report any damaged or missing guardrails, toe boards or covers to the Site Manager before using the route.

11. Welfare

Principal Contractor site welfare cabins, including WC, canteen and drying room, to be used. Wash hands before eating, drinking or smoking. Dusty clothing is to be cleaned with a vacuum before entering the cabins and not shaken out or blown down.

12. First aid

First-aider and first-aid point locations to be confirmed at the Principal Contractor's induction. For serious injuries, call 999 first. Any injury, however minor, is reported to the Site Manager and recorded in the accident book. Eyewash is available for dust and adhesive contact.

13. Emergency procedures

Follow the Principal Contractor's emergency arrangements, briefed at induction, including fire alarm, assembly point and site address for emergency services. In the event of a fall or a person hanging in a harness, call 999, do not move an injured person unless in immediate danger, and follow the rescue plan. In case of fire, raise the alarm, use an extinguisher only if safe, and evacuate to the assembly point. Stop work and report immediately if edge protection fails, a structure becomes unstable, or an unexpected hazard is found.

14. Environmental

Keep all timber offcuts, packaging and waste in the Principal Contractor's skips and segregate waste as directed. Do not burn waste. Keep adhesives and fuel cells away from drains and soil. Clean up dust with a vacuum and do not allow it to blow off the deck. Keep noise to the working hours agreed with the Principal Contractor. Return unused materials to the store.

This document was AI-generated as a drafting aid. It is not a substitute for professional health & safety advice. It must be reviewed, verified and made site-specific by a competent person before use, briefed to all operatives, and updated when site conditions or the method change. The provider accepts no liability for use of this document on site.

Carpentry method statement: what it covers