Install external rainscreen and insulated render cladding to the two-storey elevations of a commercial unit, working from an independent tied scaffold with MEWP access to restricted areas.
You get this
Frontline Facades Ltd will install external rainscreen and insulated render cladding to the two-storey elevations of a commercial unit, working from an independent tied scaffold with MEWP access to restricted areas. The site is Brookfield Business Park, Unit 4, Brookfield Business Park, Birmingham B37 7Y** (project reference FF-3315), for Kestrel Construction Ltd as Principal Contractor. Four operatives will start on Mon 06 Jul 2026 for about 3 weeks. The scaffold is provided by others. Work will be done from the scaffold and the MEWP, with a hoist or gin wheel for materials, inside a controlled exclusion zone at ground level. Plant, materials and work above head height will be managed to protect the public and other trades nearby. Items to confirm before work starts: (1) the postcode of the site and the exact elevations covered, to be confirmed with Kestrel Construction on the pre-start walk; (2) the backing wall construction (masonry, block, concrete or steel frame) and the age of the building, confirmed by R. Osei with Kestrel Construction from the client's asbestos register and drawings, because the dust controls and the asbestos check depend on them; (3) the scaffold design, tie positions and loading class, confirmed with the scaffold contractor at handover; (4) the MEWP type, the wind speed limit in the manufacturer's manual and the rescue arrangements, confirmed by the MEWP supplier and the IPAF-trained operatives; (5) the hoist or gin wheel position and safe working load, confirmed by R. Osei; (6) the Safety Data Sheets for the render, basecoat, carrier board and insulation, obtained from the suppliers by R. Osei; (7) the extent of the exclusion zone, deliveries route and other trades' working areas, agreed with Kestrel Construction at the pre-start meeting.

Generated for an example job to show the format. Make your own site-specific version and have a competent person review it.

Document details
ContractorFrontline Facades Ltd
AuthorR. Osei, Site Manager (SMSTS, CSCS Black Manager card)
Client / Principal ContractorKestrel Construction Ltd
SiteBrookfield Business Park, Unit 4, Brookfield Business Park, Birmingham B37 7Y**
Project referenceFF-3315
Start / durationMon 06 Jul 2026 / 3 weeks

1. Scope of works

Frontline Facades Ltd will install external rainscreen and insulated render cladding to the two-storey elevations of a commercial unit, working from an independent tied scaffold with MEWP access to restricted areas. The site is Brookfield Business Park, Unit 4, Brookfield Business Park, Birmingham B37 7Y** (project reference FF-3315), for Kestrel Construction Ltd as Principal Contractor. Four operatives will start on Mon 06 Jul 2026 for about 3 weeks. The scaffold is provided by others. Work will be done from the scaffold and the MEWP, with a hoist or gin wheel for materials, inside a controlled exclusion zone at ground level. Plant, materials and work above head height will be managed to protect the public and other trades nearby. Items to confirm before work starts: (1) the postcode of the site and the exact elevations covered, to be confirmed with Kestrel Construction on the pre-start walk; (2) the backing wall construction (masonry, block, concrete or steel frame) and the age of the building, confirmed by R. Osei with Kestrel Construction from the client's asbestos register and drawings, because the dust controls and the asbestos check depend on them; (3) the scaffold design, tie positions and loading class, confirmed with the scaffold contractor at handover; (4) the MEWP type, the wind speed limit in the manufacturer's manual and the rescue arrangements, confirmed by the MEWP supplier and the IPAF-trained operatives; (5) the hoist or gin wheel position and safe working load, confirmed by R. Osei; (6) the Safety Data Sheets for the render, basecoat, carrier board and insulation, obtained from the suppliers by R. Osei; (7) the extent of the exclusion zone, deliveries route and other trades' working areas, agreed with Kestrel Construction at the pre-start meeting.

2. Sequence of works

Method statement, safe system of work

  1. Before starting, R. Osei checks the client's asbestos register or management survey for each elevation and the fixing zones with Kestrel Construction. If the register does not cover the area, a refurbishment and demolition survey of that area is needed before any drilling or removal. No drilling, cutting or stripping of existing fabric starts until this check is signed off.
  2. Hold the pre-start walk with Kestrel Construction to agree the exclusion zones, deliveries route, hoist position, welfare, emergency arrangements and the confirmed backing wall construction and building age. Confirm the items listed in the scope.
  3. Check the scaffold handover certificate and the scaffold inspection register tag are in date. Walk the scaffold to check guardrails, toe boards, boards, ladders, bay access and ties. Do not start if anything is missing or damaged.
  4. Brief all four operatives on this method, the risk assessment, the emergency plan and stop-work rules. Everyone signs the briefing sheet. Check CSCS, IPAF and PASMA cards and manufacturer system training.
  5. Set up the exclusion zone at ground level with Heras fencing or barriers and signs under the work area. Put a banksman or a lookout on any gap where the public, other trades or vehicles could enter.
  6. Complete the MEWP permit to work and the daily pre-use check. Check the ground is firm and level for the MEWP, and clear of services, kerbs and drainage covers. Check the forecast and the wind speed limit before each shift and again at midday.
  7. Set up the hoist or gin wheel on a secured bracket or frame. Check the safe working load, the thorough examination certificate and the rope or chain. Keep the landing area clear and use a tag line and a banksman at ground level.
  8. Mark out the fixing positions for carrier rails and brackets on the first elevation, starting at the scaffold end furthest from the public. Keep a record of any scaffold ties that must be moved. Only the scaffold contractor moves or alters ties and scaffold components.
  9. Drill the fixings with cordless drills fitted with on-tool extraction connected to an M-class or H-class vacuum. Use the same extraction on every drill. If suspect material is found in the wall, stop, keep people away and report to R. Osei and Kestrel Construction before work carries on.
  10. Fix the aluminium carrier rails and brackets to the wall, then fit the mineral wool insulation behind the rails. Lift materials by hoist or gin wheel. Move long rails and panels with two people.
  11. Cut panels, rails and carrier board at a designated cutting station on the ground or scaffold deck, using the circular saw with dust extraction, edge guards and the correct blade. Stop the saw before putting it down. Keep the cutting station away from walkways and other trades.
  12. Hang the rainscreen cladding panels from the carrier rails, working top-down or bottom-up as the system manufacturer requires. Keep panels held in place with at least two people in wind. Stop and lay panels flat if wind rises.
  13. Fix the render carrier board where specified, then apply basecoat, mesh and topcoat render from the scaffold lift by lift. Mix in a designated area with water supply for washing. Cover or move the mixing area if it rains or if the weather could wash render onto people or drains.
  14. Use the MEWP for the restricted elevations that the scaffold cannot reach. Keep the harness clipped to the manufacturer's anchor point at all times. A trained ground person stays at the base with the emergency lowering controls and knows the rescue plan.
  15. Tidy as you go. Remove offcuts and packaging at the end of every shift. Clean up dust with an M-class or H-class vacuum, never dry sweeping or compressed air. Store panels flat and secured in the store area, not on the scaffold overnight unless the scaffold designer has agreed.
  16. At the end of each shift check the scaffold boards are clear, tools are secured, the hoist is locked and the MEWP is parked and keys removed. Leave the exclusion zone barriers in place and complete the daily checklist.
  17. On completion, hand back the work areas to Kestrel Construction. Remove all waste and waste packaging, and remove temporary fencing and signs when the zone is safe. Inform the scaffold contractor that the scaffold is ready for strike.

3. Risk assessment

Built on the HSE five steps, MHSWR 1999 regulation 3 and the hierarchy of control.

  1. Working at height: fall from the scaffold (edges, bay gaps, ladder access bays, work above the first lift)

    Medium
    Who / how
    The four operatives, from falls that could cause fatal or life-changing injury
    Existing controls
    Independent tied scaffold erected by a competent scaffold contractor with guardrails, mid rails, toe boards and ladder bays. Handover certificate and inspection tag. IPAF and CSCS carded operatives.
    L×S
    3×5=15
    Additional controls
    Avoid work at height where possible by pre-assembling panel sets and doing cutting at ground level. Check the scaffold handover certificate and the weekly inspection before the first shift and after high winds. Keep all guardrails and toe boards in place. If a guardrail has to be removed to fit cladding, the scaffold contractor agrees a safe method first, and it is put back straight away. Keep boards clear and loading within the scaffold's rated class. Never climb on guardrails or brackets. Stop work if the scaffold is damaged, a tie is missing or boards are loose. Work to the Work at Height Regulations 2005. Safety footwear and gloves worn as the last line of defence.
  2. MEWP use for restricted elevations: overturning, entrapment against the structure, ejection from the platform, collision, failure of the ground

    Medium
    Who / how
    The MEWP operative and anyone working at ground level or in the path of the machine
    Existing controls
    IPAF 3a/3b trained operatives and a MEWP permit to work.
    L×S
    3×5=15
    Additional controls
    Only trained and authorised operatives use the MEWP, with the supplier's familiarisation done before first use. Do the daily pre-use check and record it. Confirm the ground is firm and level and there are no voids or drains within the working area. Check the wind speed limit in the manufacturer's manual before use. Keep the MEWP away from overhead obstructions and use a ground person with a rescue plan and a means of emergency lowering. Keep all others out of the working radius. Operate in line with the Work at Height Regulations 2005 and PUWER 1998. Harness with a short lanyard clipped to the anchor point as a restraint.
  3. Scaffold ties and components interfering with the cladding fixing positions, so ties get removed or altered

    Medium
    Who / how
    Operatives on the scaffold and anyone below if the scaffold fails
    Existing controls
    Scaffold supplied and inspected by others. Handover certificate.
    L×S
    3×5=15
    Additional controls
    Plan tie positions with the scaffold contractor before starting so cladding can be fixed around them. Never remove, loosen or move a tie, brace or guardrail. If a tie must move, ask the scaffold contractor to move it and re-inspect before work resumes. Report any scaffold damage to R. Osei straight away, and do not use that bay until it is fixed. Do not store or stack materials on the scaffold above its loading class. Display a scaffold tag on the base and check it is current.
  4. Falling objects: tools, fixings, panels, offcuts and render dropping from the scaffold, MEWP or hoist

    Low
    Who / how
    Operatives, other trades, visitors and members of the public below, who could suffer head and other serious injuries
    Existing controls
    Toe boards on the scaffold. Exclusion zone planned.
    L×S
    3×4=12
    Additional controls
    Set a controlled exclusion zone under all work areas with barriers and signs. Keep it clear of other trades while work is overhead. Use tool lanyards, buckets and a tidy deck. Do not stack loose materials near the edge. Use brick guards or debris netting where the scaffold edge is above a walkway or access route. Lift materials by hoist or gin wheel only, with the area below cleared. Report any dropped item at once. Hard hats worn by all, as a last line of defence.
  5. Public and other trades nearby: pedestrians, vehicles, deliveries and other contractors on the business park entering the work zone or the MEWP path

    Low
    Who / how
    Members of the public, visitors to the units, Kestrel Construction staff, other trades and delivery drivers, who could be struck by objects, vehicles or the MEWP
    Existing controls
    Principal Contractor site rules and site induction.
    L×S
    3×4=12
    Additional controls
    Agree the exclusion zone and the pedestrian and vehicle routes with Kestrel Construction at the pre-start walk. Use fixed barriers, signs and a banksman at access gaps while overhead work or MEWP movement is going on. Schedule deliveries at quiet times, away from the work area. Brief other trades on the exclusion zone and the dust and noise they may notice. Do not leave the MEWP or any tool unattended outside the zone. Contractors in the zone wear hi-vis and hard hats.
  6. Manual handling of cladding panels, carrier rails, insulation, carrier board, render bags and tools

    Medium
    Who / how
    Operatives, from back, shoulder and hand injuries, and from dropping loads on others
    Existing controls
    Two-person lifts for long or heavy items. Manufacturer system training.
    L×S
    4×3=12
    Additional controls
    Eliminate carrying where possible by using the hoist or gin wheel, trolleys and the MEWP to move materials up. Order panels and render in manageable sizes and pack weights. Store materials close to the work area. Use two-person lifts for panels and long rails, and mechanical aids for loads above the safe lifting weight. Plan lifts to Manual Handling Operations Regulations 1992, with rotation of tasks to avoid repeated reaching and lifting above shoulder height. Gloves worn for grip and protection.
  7. Lifting with the hoist or gin wheel: overload, failure of rope or fixing, load swinging, loads dropped or trapping hands

    Medium
    Who / how
    The operative lifting, others below and anyone near the landing point
    Existing controls
    Hoist or gin wheel supplied and checked before use. Trained operatives.
    L×S
    2×5=10
    Additional controls
    Check the safe working load, thorough examination certificate and fixing before each shift. Fix the gin wheel to a bracket designed for the load, never to a scaffold guardrail unless the scaffold contractor agrees in writing. Keep the landing and the area below clear. Use a tag line, a banksman and tidy rope. Never lift people. Operate in line with the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER). Gloves and hard hats worn.
  8. Respirable crystalline silica (RCS) dust from drilling fixings and cutting or chasing masonry, block, concrete, mortar, render or carrier board

    Medium
    Who / how
    The operatives doing the work and anyone nearby, such as other trades or the public, breathing the dust. Long-term exposure can cause silicosis, lung cancer and other lung disease
    Existing controls
    Circular saw with dust extraction. Cordless drills.
    L×S
    4×4=16
    Additional controls
    Plan the work to reduce cutting and drilling by using pre-cut panels, set fixing positions and the manufacturer's system. Fit on-tool extraction (M-class or H-class vacuum) or use water suppression on every drill, chaser and saw used on these materials. Keep others away from the dust while work is going on and clean up with an H-class or M-class vacuum, never dry sweeping or compressed air. Work to the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE Construction Information Sheet CIS36 Construction dust. The workplace exposure limit for RCS is 0.1 mg/m3 (8-hour TWA) in HSE EH40/2005. Respiratory protective equipment with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven, as the last line of defence.
  9. Disturbing unidentified asbestos-containing materials when drilling into, cutting or removing existing walls, soffits, textured coatings or boxing (building age to be confirmed)

    Medium
    Who / how
    Operatives, other trades, building users and the public, from asbestos fibres that can cause serious lung disease years later
    Existing controls
    Principal Contractor site induction and any asbestos information held by the client.
    L×S
    2×5=10
    Additional controls
    Before any drilling or removal, R. Osei checks the client's asbestos register or management survey for each elevation and the fixing zones. If the register does not cover the area, a refurbishment and demolition survey of that area is needed first. This is the check required by the Control of Asbestos Regulations 2012 (Regulation 5, identifying asbestos before work). Do not start until the check is signed off. Stop-work rule: if suspect material is found, stop, keep people away, and report it to R. Osei and Kestrel Construction before work carries on. Do not try to sample or clean it up. Brief all operatives on this stop-work rule at the start of the job.
  10. Irritant dust and fibres from mineral wool insulation, carrier board and render cutting

    Low
    Who / how
    Operatives, causing skin, eye and throat irritation, and others nearby who may breathe the dust
    Existing controls
    Circular saw with dust extraction. Manufacturer system training.
    L×S
    4×2=8
    Additional controls
    Use pre-cut insulation and board sizes where possible, and cut with on-tool extraction in a defined cutting area. Do not cut in the wind where the dust blows onto others. Keep the product in its packaging until it is used and bag the offcuts. Vacuum up with an M-class or H-class vacuum, never brush or blow. Wash hands and face before eating. Long sleeves, gloves, goggles and a dust mask as the last line of defence. Follow the product Safety Data Sheets and COSHH 2002.
  11. Wet cement-based basecoat and topcoat render: skin burns, dermatitis, eye splashes

    Low
    Who / how
    Operatives mixing and applying render, with the risk of chemical burns and long-term skin disease
    Existing controls
    Welfare with washing facilities. Manufacturer system training.
    L×S
    3×3=9
    Additional controls
    Use ready-mixed or pre-bagged products where possible to cut mixing and dust. Mix in a designated area with an eye wash and clean water. Do not let render sit on skin. Wash off at once and use barrier cream if specified in the Safety Data Sheet. Check the skin of the hands and forearms for early signs of dermatitis and report it. Gauntlet gloves, waterproof sleeves, goggles and wellington boots to the specification in the Safety Data Sheet, as the last line of defence. Work to COSHH 2002.
  12. Noise and hand-arm vibration from cordless drills, circular saw and hammer action drilling

    Medium
    Who / how
    Operatives, from hearing damage and vibration white finger, and others nearby from noise
    Existing controls
    Cordless drills with cordless power. Tools in good order.
    L×S
    4×3=12
    Additional controls
    Choose low-vibration and low-noise tools and keep them maintained, with sharp bits and blades. Limit time on the highest vibration tasks and rotate operatives. Use anvil or rotary action rather than percussion drilling where the substrate allows. Warn others nearby of noisy work and ask Kestrel Construction to agree the times. Track trigger times against the exposure action values in the Control of Noise at Work Regulations 2005 and the Control of Vibration at Work Regulations 2005. Hearing protection to BS EN 352 worn where noise is high, as a last line of defence. Report numbness or tingling in the hands.
  13. Circular saw and sharp aluminium cladding edges: cuts, kickback, blade contact, flying fragments

    Low
    Who / how
    Operatives using the saw and handling panels, rails and brackets, and others nearby
    Existing controls
    Circular saw with dust extraction and guard. Trained operatives.
    L×S
    3×4=12
    Additional controls
    Use a designated cutting station with a stable bench or clamps. Keep guards fitted and use the correct blade for the material. Deburr and file edges after cutting before fixing. Disconnect or remove the battery when changing blades. Keep the cutting area tidy and away from walkways. Use tools in line with PUWER 1998. Cut-resistant gloves, safety glasses and safety footwear as a back-up.
  14. Weather and wind: high wind catching panels and sheeting like a sail, rain and cold making surfaces slippery, render drying or washing out, sun and heat

    Medium
    Who / how
    Operatives on the scaffold and MEWP, and people below, from falls, loss of control of loads or impact
    Existing controls
    Forecast checked on the day. Principal Contractor weather rules.
    L×S
    4×4=16
    Additional controls
    Check the forecast the day before and each morning. Stop work at height and lay panels flat when the wind exceeds the limit in the MEWP manual or the scaffold sheeting design, or when it is too strong to hold panels safely. Do not use the MEWP in high wind, and park it safely. Secure stored panels. Do not apply render in rain, frost or strong sun unless the manufacturer allows it. Use the drying room and take breaks in cold and wet weather. Wear waterproofs and warm layers as last line of defence.
  15. Electricity from temporary supplies, extension leads, battery chargers and 110V tools used outside in wet weather

    Low
    Who / how
    Operatives, from electric shock, burns or fire
    Existing controls
    Cordless tools used where possible. Tools checked before use.
    L×S
    2×4=8
    Additional controls
    Use battery tools where possible to avoid mains leads. For any mains supply use 110V centre-tapped earth supplies with a transformer and RCD protection, kept off the ground and away from water. Check cables and plugs by visual inspection before use and keep up-to-date PAT labels. Charge batteries in a dry, ventilated area, not on the scaffold. Do not use damaged equipment, and tag it out. Work in line with the Electricity at Work Regulations 1989. Rubber-soled footwear and insulated gloves where specified.
  16. Slips, trips and housekeeping: offcuts, packaging, cables, wet render and rain on scaffold boards and at ground level

    Low
    Who / how
    Operatives and others, from falls on the same level and falls from the scaffold
    Existing controls
    Tidy working practice. Site waste area.
    L×S
    4×2=8
    Additional controls
    Set up waste bins and tidy as you go, with a clean-down at the end of every shift. Keep boards, stairs and ladder bays clear. Route cables away from walkways and use hooks. Clean up spilled render straight away. Keep the ground-level exclusion zone free of clutter. Use anti-slip footwear as a last line of defence.

4. COSHH assessment

Built on COSHH 2002 regulations 6 and 7 and HSE guidance L5.

Check each entry against the supplier's Safety Data Sheet before work starts. Take workplace exposure limits from HSE EH40/2005.

Respirable crystalline silica (RCS) dust

Task or use
Created by drilling fixings and cutting or chasing masonry, block, concrete, mortar, render or carrier board during installation of carrier rails, brackets and cladding.
Route of exposure
Inhalation of fine dust. Eye contact with airborne dust.
Who could be harmed
Operatives doing the drilling and cutting, and anyone nearby, such as other trades or the public, breathing the dust. Long-term exposure can cause serious and irreversible lung disease.
Hazards
Breathing in fine silica dust over time can lead to silicosis, lung cancer and chronic lung disease. Eye irritation is possible. Check the product Safety Data Sheet for any material being cut, section 2.
Controls
  1. Plan the work to cut and drill as little as possible by using pre-cut components and set fixing positions.
  2. Fit on-tool extraction (M-class or H-class vacuum) or use water suppression on every drill, chaser and saw used on these materials.
  3. Limit the number of people near the work and the time spent in the dust, and keep other trades away while it is being created.
  4. Clean up with an H-class or M-class vacuum, never dry sweeping or compressed air.
  5. Work to the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE guidance L5 (the COSHH Approved Code of Practice).
PPE
  • Respiratory protective equipment with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven.
  • Safety glasses or goggles.
  • Disposable or washable overalls, washed at work or bagged for laundering.
Storage and disposal
Bag dust and waste in sealed, labelled bags and dispose through the Principal Contractor's waste route. Store used vacuum filters and bags sealed. Do not take dusty clothing home.
First aid and spillage
Move to fresh air if dust has been breathed in and seek medical advice if coughing or breathing is difficult. Rinse eyes with clean water for several minutes. Clean up dust spillage with an H-class or M-class vacuum, never by dry sweeping or blowing.
Health surveillance
Respiratory health surveillance may be needed for regular or high exposure. Confirm with the company's occupational health provider and the competent person whether it is required for these operatives.
Check against the Safety Data Sheet
Before work starts, check section 2 of the Safety Data Sheet for each material that will be drilled or cut. Take workplace exposure limits from HSE EH40/2005 and RPE specification from the Safety Data Sheet and HSE guidance. Confirm the backing wall construction with Kestrel Construction.

Basecoat, mesh and topcoat render

Task or use
Mixing and applying basecoat and topcoat render with mesh over the insulation and carrier board.
Route of exposure
Skin contact, eye contact (splashes) and inhalation of dust from dry powder. Ingestion if hands are not washed.
Who could be harmed
Operatives mixing and applying render, from skin and eye damage, and others nearby from dust or splashes.
Hazards
Cement-based products can burn skin, cause dermatitis and cause serious eye damage. Dust can irritate the nose and throat. The hazards depend on the product, so check section 2 of the supplier's Safety Data Sheet.
Controls
  1. Choose a ready-mixed, low-dust or pre-bagged product where the system allows, to reduce dust from mixing.
  2. Mix in a designated area with good ventilation, using mixing paddles that reduce dust. Pour powder carefully and slowly.
  3. Limit the quantity mixed at one time and the time spent in contact with wet render. Keep other people away from the mixing area and the area below.
  4. Provide clean water and an eye wash at the mixing area and wash off skin contact straight away.
  5. Work to the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE guidance L5 (the COSHH Approved Code of Practice).
PPE
  • Gloves and waterproof sleeves to the specification in the Safety Data Sheet.
  • Goggles or safety glasses, with a face shield if splashing is likely.
  • Waterproof boots and long sleeves. Dust mask or RPE if the Safety Data Sheet requires it.
Storage and disposal
Store bags dry, off the ground and under cover, and stack them securely. Dispose of waste and empty bags through the Principal Contractor's waste route. Do not wash into drains or watercourses.
First aid and spillage
Wash skin straight away with plenty of clean water. Rinse eyes for at least 10 minutes with clean water and seek medical help. Take the product Safety Data Sheet to hospital. Sweep up dry spills carefully with minimum dust and wipe or collect wet spills with absorbent material, then dispose of as waste.
Health surveillance
Skin checks for early signs of dermatitis are advised for operatives working with wet render regularly. No other health surveillance is expected.
Check against the Safety Data Sheet
Before work starts, get the Safety Data Sheet for each render product from the supplier. Confirm the hazards (section 2), PPE specification, first aid measures and disposal advice. Take workplace exposure limits from HSE EH40/2005.

Mineral wool insulation

Task or use
Cutting, handling and fitting insulation behind the carrier rails on the elevations.
Route of exposure
Skin contact, eye contact and inhalation of fibres and dust.
Who could be harmed
Operatives handling and cutting insulation, and others nearby if fibres blow in the wind.
Hazards
Fibres can irritate the skin, eyes, nose and throat and cause itching. The hazards depend on the product, so check section 2 of the supplier's Safety Data Sheet.
Controls
  1. Order insulation cut to size where possible and keep it wrapped until it is used.
  2. Cut in a designated area with extraction or in a position where fibres do not blow towards others.
  3. Limit handling time and the number of people nearby. Clean up with a vacuum, not brushing, and bag offcuts straight away.
  4. Wash hands and face before eating and at the end of the shift. Wash work clothes separately.
  5. Work to the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE guidance L5 (the COSHH Approved Code of Practice).
PPE
  • Gloves and long sleeves to the specification in the Safety Data Sheet.
  • Goggles or safety glasses.
  • Dust mask or RPE where the Safety Data Sheet or the assessed dust level requires it.
Storage and disposal
Store dry and wrapped, off the ground and secured against wind. Put offcuts in sealed bags and dispose of through the Principal Contractor's waste route.
First aid and spillage
Rinse skin with cool water and do not rub. Rinse eyes with clean water for several minutes and seek medical advice if irritation lasts. Move into fresh air if the throat is irritated. Clean up loose fibres with a vacuum.
Health surveillance
None is expected for this substance. Report any skin or breathing symptoms to R. Osei.
Check against the Safety Data Sheet
Before work starts, get the Safety Data Sheet for the insulation from the supplier. Confirm the hazards (section 2), PPE specification and disposal advice. Take workplace exposure limits from HSE EH40/2005.

Dust from cutting render carrier board

Task or use
Cutting the render carrier board to size with the circular saw with dust extraction, and drilling fixings through it.
Route of exposure
Inhalation of dust and eye contact. Skin contact.
Who could be harmed
Operatives cutting and fixing the board and anyone nearby breathing the dust.
Hazards
Board dust can irritate the nose, throat, eyes and skin. The hazards depend on what the board is made of, so check section 2 of the supplier's Safety Data Sheet. If the board contains cement or mineral content, the dust may be a silica risk, which is covered by the RCS assessment.
Controls
  1. Order board cut to size where the supplier offers it, to reduce site cutting.
  2. Cut only with on-tool extraction connected to an M-class or H-class vacuum, in a designated cutting area away from walkways and other trades.
  3. Limit the number of people nearby and the time spent cutting. Keep offcuts and dust bagged and removed each shift.
  4. Clean up with an M-class or H-class vacuum, never dry sweeping or compressed air.
  5. Work to the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE guidance L5 (the COSHH Approved Code of Practice).
PPE
  • RPE to the specification in the Safety Data Sheet, face-fit tested where it is a tight-fitting mask.
  • Safety glasses or goggles.
  • Gloves and long sleeves.
Storage and disposal
Store the board flat, dry and off the ground. Bag dust and offcuts and dispose of them through the Principal Contractor's waste route.
First aid and spillage
Move to fresh air if dust has been breathed in. Rinse eyes with clean water and wash skin with soap and water. Clean up dust with an M-class or H-class vacuum.
Health surveillance
None is expected for occasional cutting. If the board proves to be a source of silica, follow the surveillance advice in the RCS assessment.
Check against the Safety Data Sheet
Before work starts, get the Safety Data Sheet for the carrier board from the supplier and confirm its composition, the hazards (section 2) and the RPE specification. Take workplace exposure limits from HSE EH40/2005.

5. Plant & equipment

  • Independent tied scaffold (supplied by others) with handover certificate
  • MEWP (scissor or boom) with daily pre-use check and permit
  • Cordless drills with on-tool dust extraction
  • Circular saw with dust extraction and guard
  • M-class or H-class vacuum extractors
  • Hoist or gin wheel with valid thorough examination
  • Hand tools, tool lanyards and buckets
  • Mixing paddle and mixing station for render
  • Heras fencing, barriers and signs for the exclusion zone
  • Towers (PASMA trained operatives only) where used for low-level access

6. Materials / COSHH

Rainscreen cladding panels, aluminium carrier rails and brackets, mineral wool insulation, render carrier board, basecoat, mesh and topcoat render and fixings. The hazardous substances are the cement-based render products, the mineral wool, dust from cutting carrier board and respirable crystalline silica dust created by drilling and cutting. The full detail is in the COSHH assessments. Obtain the Safety Data Sheet for each product before work starts.

7. PPE

  • Hard hat to BS EN 397, with chin strap when working at height or on the MEWP
  • Safety footwear to BS EN ISO 20345 with good grip
  • High-visibility vest or jacket
  • Gloves to suit the task: cut-resistant for panels and rails, chemical-resistant for render
  • Safety glasses or goggles to BS EN 166
  • Hearing protection to BS EN 352 where noise is high
  • RPE: FFP3 or equivalent with an assigned protection factor of at least 20 for silica dust, face-fit tested and worn clean shaven
  • Full body harness and lanyard for the MEWP, to manufacturer's instruction
  • Long-sleeved clothing, and waterproofs and warm layers for bad weather

8. Competence & training

Four operatives, all CSCS carded installers with manufacturer system training. IPAF 3a/3b card holders operate the MEWP, and PASMA trained operatives use any towers. R. Osei, Site Manager (SMSTS, CSCS Black Manager card), supervises and briefs the team. All operatives attend the Principal Contractor's induction and sign the briefing for this method before starting. Operatives using the hoist or gin wheel are briefed on safe use. Face-fit testing is in date for everyone using tight-fitting RPE.

9. Permits

  • MEWP permit to work
  • Scaffold handover certificate (from the scaffold contractor) and a current inspection tag
  • Asbestos register or management survey check signed off by R. Osei and Kestrel Construction before any drilling or removal
  • Principal Contractor's own permits as required on the pre-start walk

10. Access & egress

Access to the work is by the scaffold ladder access bays, which must be kept clear, and by the MEWP for restricted elevations. The exclusion zone at ground level is entered only by authorised operatives through a controlled gap. Deliveries come in by the route agreed with Kestrel Construction and materials go up by hoist or gin wheel. Keep fire exits and routes for other occupiers clear at all times. Emergency egress from the scaffold is by the nearest ladder bay.

11. Welfare

Welfare is provided in the Principal Contractor's site cabins: WC, canteen and drying room. Wash facilities and clean water are available for skin contact with render. Operatives wash hands and face before eating, drinking and smoking. Eye wash is provided at the render mixing area.

12. First aid

A first aider is on site and the first aid kit is in the site cabins. An eye wash is kept at the render mixing area. Report all injuries and near misses to R. Osei and Kestrel Construction and record them in the accident book.

13. Emergency procedures

Follow the Principal Contractor's emergency plan and the fire assembly point shown at induction. In an emergency stop work, make safe and leave by the nearest ladder bay or lower the MEWP. For a person fallen, trapped or injured at height, call 999 and do not move them unless in danger. The ground person at the MEWP uses the emergency lowering controls under the rescue plan. Never use the MEWP for rescue unless trained. If suspect asbestos material is found, stop work, keep people away and report to R. Osei and Kestrel Construction. Tell the Principal Contractor if the scaffold is damaged or a tie has failed, and evacuate that area.

14. Environmental

Keep render, slurry and cement-based water out of drains and watercourses. Use a settling or collection point for washings and dispose of it through the Principal Contractor's waste route. Segregate waste (insulation, board, packaging, metal offcuts) in marked bins and keep it tidy. Do not burn waste. Cover stored materials and secure loose items against wind. Keep dust down with extraction and vacuum cleaning, and keep noisy work to the agreed hours.

This document was AI-generated as a drafting aid. It is not a substitute for professional health & safety advice. It must be reviewed, verified and made site-specific by a competent person before use, briefed to all operatives, and updated when site conditions or the method change. The provider accepts no liability for use of this document on site.

Cladding method statement: what it covers

Other samples:ElectricalGroundworksRoofingScaffoldingFlat roofingSee all 20

Want one like this for your job?

Get your RAMS– it's freeFirst document free, then £15 each. No subscription.