Drainage method statement example: foul and surface-water drainage, extension

HSE five steps · CDM 2015
You write this
Install new foul and surface-water drainage runs in shallow trenches (up to 1.2m deep) and connect to an existing manhole to serve a single-storey domestic rear extension, using a mini-excavator.
You get this
Groundline Drainage & Groundworks Ltd will install new foul and surface-water drainage runs in shallow trenches (up to 1.2m deep) and connect to an existing manhole to serve a single-storey domestic rear extension, using a mini-excavator. The site is 18 Beechwood Close, Bristol (project ref GDG-3116) for Hartley Residential. Work starts Tue 23 Jun 2026 and lasts 4 days with 3 operatives. The trenches will be set out, scanned for services, dug in stages with trench support, and the pipes laid, haunched where needed, connected, tested and backfilled. The manhole cover and frame will be set to level. Services are located and a permit to dig is in place before any digging. Excavations are supported, fenced and inspected. People nearby are kept clear of the work area. Items to confirm before work starts: (1) The postcode was given as BS16 4P**, so Hartley Residential must confirm the full postcode for the emergency plan and deliveries. (2) Building age, and whether the client has an asbestos register or management survey covering the rear extension area, drain runs and manhole. R. Fields confirms this with Hartley Residential before the pre-start walk. (3) Who owns the existing manhole, its depth and how the connection is to be made (benching, core, break-in). R. Fields confirms this on the pre-start walk. If it is a public sewer, the sewerage undertaker's approval must be in place. (4) Positions of electricity, gas and water services entering the house, plus any as-built or utility plans. Hartley Residential and R. Fields confirm these on the pre-start walk. (5) Ground conditions, water table and the depth and spacing of the trench support needed. The excavator operator and R. Fields confirm these on the first morning before any trench is opened. (6) Where spoil and materials are stored, spoil removal and the routes on the private driveway. R. Fields agrees these with Hartley Residential on the pre-start walk. (7) Which operative is the first aider, and the working hours agreed with the client and neighbours. R. Fields confirms these at the site induction.

Generated for an example job to show the format. Make your own site-specific version and have a competent person review it.

Document details
ContractorGroundline Drainage & Groundworks Ltd
AuthorR. Fields, Site Supervisor (NRSWA, EUSR Water Hygiene)
Client / Principal ContractorHartley Residential
Site18 Beechwood Close, Bristol BS16 4P**
Project referenceGDG-3116
Start / durationTue 23 Jun 2026 / 4 days

1. Scope of works

Groundline Drainage & Groundworks Ltd will install new foul and surface-water drainage runs in shallow trenches (up to 1.2m deep) and connect to an existing manhole to serve a single-storey domestic rear extension, using a mini-excavator. The site is 18 Beechwood Close, Bristol (project ref GDG-3116) for Hartley Residential. Work starts Tue 23 Jun 2026 and lasts 4 days with 3 operatives. The trenches will be set out, scanned for services, dug in stages with trench support, and the pipes laid, haunched where needed, connected, tested and backfilled. The manhole cover and frame will be set to level. Services are located and a permit to dig is in place before any digging. Excavations are supported, fenced and inspected. People nearby are kept clear of the work area. Items to confirm before work starts: (1) The postcode was given as BS16 4P**, so Hartley Residential must confirm the full postcode for the emergency plan and deliveries. (2) Building age, and whether the client has an asbestos register or management survey covering the rear extension area, drain runs and manhole. R. Fields confirms this with Hartley Residential before the pre-start walk. (3) Who owns the existing manhole, its depth and how the connection is to be made (benching, core, break-in). R. Fields confirms this on the pre-start walk. If it is a public sewer, the sewerage undertaker's approval must be in place. (4) Positions of electricity, gas and water services entering the house, plus any as-built or utility plans. Hartley Residential and R. Fields confirm these on the pre-start walk. (5) Ground conditions, water table and the depth and spacing of the trench support needed. The excavator operator and R. Fields confirm these on the first morning before any trench is opened. (6) Where spoil and materials are stored, spoil removal and the routes on the private driveway. R. Fields agrees these with Hartley Residential on the pre-start walk. (7) Which operative is the first aider, and the working hours agreed with the client and neighbours. R. Fields confirms these at the site induction.

2. Sequence of works

Method statement, safe system of work

  1. Before the pre-start walk, check the client's asbestos register or management survey for the rear extension area, drain runs and manhole. If the register does not cover the area, a refurbishment and demolition survey of that area is needed before any intrusive work. Confirm the items listed in the scope with Hartley Residential, and check the excavation permit, permit to dig and building control drainage connection approval are in place.
  2. Hold the pre-start walk with Hartley Residential. Agree the work zone, the access route off the private driveway, spoil and material storage, the positions of the cabin and welfare, and who else will be on site, such as the extension trades, the householders and neighbours.
  3. Brief all 3 operatives on this RAMS, the emergency plan and the stop-work rules. Everyone signs the briefing sheet. Check tickets and cards for the excavator operator and the others.
  4. Set up the work area. Put Heras or barrier fencing around the work zone and the excavator swing area, with warning signs, so that residents, visitors and other trades are kept clear. Set up the welfare and hand-washing area. Keep the driveway clear for emergency access.
  5. Obtain and review the service plans. Scan the whole route and the area around the manhole with the CAT and Genny, in two directions at right angles, and mark what is found on the ground. Treat anything unknown as live. Complete the permit to dig.
  6. Hand-dig trial holes with insulated or non-conductive digging tools to expose any services crossing or running along the runs, and confirm the pipe depths. Do not use the excavator within the agreed safe digging distance of any located service. Stop and re-plan if an unexpected service or suspect material is found.
  7. Carry out the daily pre-use checks on the mini-excavator, generator, compactor plate, leads and hand tools. Check the excavator quick hitch and attachment pin, and carry out a check for fuel leaks. Brief the banksman and agree hand signals.
  8. Dig the trenches in short sections, working back from the manhole end. Fit trench support as the depth increases. Keep spoil at least 1m back from the edge and keep the excavator and vehicles off the edge with stop blocks. Batter ends and fit a ladder at least 1m above the top of the trench where people have to get in. Do not let anyone enter an unsupported trench.
  9. A competent person inspects every excavation at the start of each shift, after rain, and after any collapse or change, before anyone goes in. Record the inspection. Rescan the trench as it deepens, and keep to the permit to dig.
  10. Do not enter the existing manhole. Check the connection point from outside and from the trench. Rod or test for blockages and gases only from ground level. Never go in the chamber. If entry is thought necessary, stop work and reassess, as that needs a separate confined space assessment and a rescue plan.
  11. Make the connection to the existing manhole. Use wet cutting or on-tool extraction to break in or core the chamber wall and benching, and keep others away while this is done. Form the channel and benching neatly and make the joint watertight. Wash hands and tools before taking breaks.
  12. Prepare the pipe bed with pea shingle or bedding material, to the gradients agreed on the drawings. Lay the 110mm and 160mm uPVC pipes and fittings working uphill from the manhole. Use two people to carry the longer lengths and mechanical lifting from the excavator only with a banksman and suitable lifting accessories. Keep people out of the swing area and out of the trench during lifting.
  13. Form the concrete haunching where specified. Use ready-mixed or bagged concrete mixed on a board away from drains. Keep skin off wet concrete and wash off straight away if it gets on skin. Keep hand tools clean.
  14. Set the new manhole cover and frame to level, as agreed. Lift using a suitable lifting aid, or two people with a lifting key. Do not lift it by hand alone.
  15. Arrange for the building control inspection and test of the drainage as required, and test the drains with water or air as specified. Release test pressure slowly and keep people clear of test plugs. Do not backfill until the work has been inspected and passed.
  16. Backfill in layers, with suitable fill around and above the pipes. Compact each layer with the compactor plate. Remove trench support progressively as backfilling rises and only when safe to do so. Keep others clear while plate compacting.
  17. Reinstate the area. Clean the driveway and the work area with a vacuum or wet methods, not dry sweeping. Remove waste and surplus material. Complete the waste transfer notes, and give the client the inspection and test records and as-built details.
  18. At the end of each day, make the trenches safe. Back-fill or cover and barrier the open excavations, remove the keys from the plant, lock away fuel, secure the site and close the gates.

3. Risk assessment

Built on the HSE five steps, MHSWR 1999 regulation 3 and the hierarchy of control.

  1. Live services (electricity, gas, water): striking buried or hidden services when digging trenches and breaking in at the manhole

    Medium
    Who / how
    Operatives and the excavator operator (electric shock, burns, explosion, fire, crush from flooded trench), householders and neighbours (loss of supply, gas escape, flooding)
    Existing controls
    CAT and Genny available, permit to dig, trained operatives
    L×S
    3×5=15
    Additional controls
    Get utility and service plans and meter positions from the client before starting. Plan the runs to avoid known services where possible. Scan the whole route with the CAT and Genny in two directions, mark the results, and rescan as the trench deepens and the spoil is dug. Hand-dig trial holes with insulated tools within the agreed safe digging distance of located services and where plans are unclear. Treat unknown services as live. No excavator work over located services. Keep a brief, a banksman and agreed stop-work rule for damage. Follow the Electricity at Work Regulations 1989 and HSE guidance HSG47 Avoiding danger from underground services. Operatives wear insulating gloves and eye protection when hand-digging near services as the last line of defence.
  2. Public / other trades nearby: householders, neighbours, visitors, delivery drivers and the trades building the rear extension entering the work area or the excavator swing zone

    Low
    Who / how
    Householders, children, neighbours, passers-by on the private driveway, delivery drivers and other trades (struck by plant, falling into trenches, trips over pipes and spoil)
    Existing controls
    Site cabin and access off the private driveway
    L×S
    3×4=12
    Additional controls
    Agree with Hartley Residential that the work zone is closed to the householders and other trades. Fit Heras or barrier fencing with signs around the open trenches, spoil and excavator swing area, and fit lit or reflective barriers if left overnight. Coordinate the sequence with the extension trades so that they are not working below or alongside the excavator. Keep a banksman for all plant movements and for deliveries. Tell neighbours when digging is under way and when the work will be noisy. Keep the driveway clear of materials so that emergency access is not blocked. Check the barriers daily. Operatives wear hi-vis clothing as the last line of defence. Follow CDM 2015 duties on coordinating and cooperating with others.
  3. Trench collapse in excavations up to 1.2m deep, including ground that is wet, loose or disturbed by earlier services

    Medium
    Who / how
    Operatives in the trench (burial, crush injuries, suffocation, fatal injury)
    Existing controls
    Trench support and shoring, excavation permit, battered ends
    L×S
    3×5=15
    Additional controls
    Do not enter any trench deeper than the ground allows unless it is supported, battered or benched to a safe angle. Fit trench support (boxes, props or sheets) as digging proceeds and keep it within the manufacturer's limits. Dig the shortest practical length and only open what can be laid and backfilled in the shift. Keep spoil and materials at least 1m from the edge. A competent person inspects at the start of each shift, after rain and after any change, and records it. Do not work alone in a trench. Follow CDM 2015 Regulation 22 on excavations. Operatives wear hard hats and safety boots as the last line of defence.
  4. Falling into open trenches, and unsafe trench access with ladders and battered ends

    Low
    Who / how
    Operatives, householders, children and other trades (broken bones, head injury)
    Existing controls
    Battered ends and a ladder for access
    L×S
    3×3=9
    Additional controls
    Put barriers or guard rails and toe boards around trenches, with the barrier set back from the edge. Use stop blocks for the excavator and vehicles. Leave a ladder secured, extending at least 1m above the top, and keep the ladder base clear. Keep trenches covered or fenced when not attended and at day end. Check access routes daily. Follow the Work at Height Regulations 2005 for ladders. Anti-slip boots and hard hats as the last line of defence.
  5. Mini-excavator (1.5t) operation: overturning, striking or crushing people, and hitting structures, and use of plant for lifting pipes and the manhole cover

    Medium
    Who / how
    Operatives, banksman, householders, other trades and the public (crush, impact, fatal injury)
    Existing controls
    Operator holds a CPCS or NPORS mini-excavator ticket
    L×S
    3×5=15
    Additional controls
    Confirm which operative is the nominated operator and check their ticket. Complete daily pre-use checks. Plan a one-way route and exclusion zone around the swing radius. Use a trained banksman whenever people are within the work area. Set stop blocks at trench edges and keep the machine level and on firm ground. Use the quick hitch properly with the safety pin fitted. Only lift with rated lifting points and accessories, with the load kept low, under LOLER 1998. Follow PUWER 1998. Operators wear seat belts and everyone near plant wears hi-vis and safety boots as the last line of defence.
  6. Undermining existing house foundations, the new extension footings and nearby structures when excavating close to them

    Medium
    Who / how
    Operatives, occupants and extension trades (structural movement, collapse, crush)
    Existing controls
    Trench support, excavation permit
    L×S
    2×4=8
    Additional controls
    Confirm foundation depths and positions from the client and the extension drawings before digging, and check the extension designer or building control for any digging near footings. Keep the trench bottom outside the line of the foundations where possible, or use extra support. Do not dig below the underside of existing footings without engineer advice. Check for signs of movement, such as cracks, each shift. Stop work and report to the Principal Contractor if there is any sign of movement.
  7. Manual handling of 110mm and 160mm pipes, bedding bags, concrete bags, manhole cover and frame, and trench support

    Medium
    Who / how
    Operatives (back, shoulder and hand injuries, crush injuries)
    Existing controls
    3 operatives available, mini-excavator on site
    L×S
    4×3=12
    Additional controls
    Avoid manual lifting where possible: deliver materials close to the work, use the excavator with a banksman and rated accessories for heavy items and use wheelbarrows. Break loads down and use two-person lifts for pipe lengths and the cover. Use lifting keys for the cover. Rotate tasks and take breaks. Follow the Manual Handling Operations Regulations 1992. Gloves and safety boots as the last line of defence.
  8. Noise and hand-arm vibration from the compactor plate, mini-excavator, and any hand-held breaking or coring tools

    Medium
    Who / how
    Operatives and nearby householders (hearing damage, hand-arm vibration syndrome)
    Existing controls
    Short 4-day duration
    L×S
    4×3=12
    Additional controls
    Choose low-vibration, well-maintained equipment and compact in thin layers so the plate runs for less time. Rotate operators and limit trigger time, using manufacturer's vibration figures. Keep others away from noisy work and tell the householders and neighbours when it will occur. Follow the Control of Noise at Work Regulations 2005 and the Control of Vibration at Work Regulations 2005. Hearing protection with a suitable rating as the last line of defence.
  9. Biological hazards from foul sewage and drain contents at the existing manhole and foul run, including leptospirosis, hepatitis A and gastro illness

    Medium
    Who / how
    Operatives (infection through cuts, splashes, hand-to-mouth contact)
    Existing controls
    Site cabin WC, wash facilities and hot water, EUSR Water Hygiene card
    L×S
    3×3=9
    Additional controls
    Avoid contact where possible: do not open the live drain more than needed and plan the connection to limit flow disturbance. Keep clean and dirty areas apart. Cover cuts with waterproof dressings. Wash hands and forearms with soap and hot water before eating, drinking, smoking or leaving. Do not eat in the work area. Clean tools and boots before the cabin. Report any flu-like illness to a doctor and say you work with sewage. Follow COSHH 2002. Waterproof gloves, eye protection and overalls as the last line of defence.
  10. Toxic or flammable gases and oxygen deficiency at the existing manhole (foul drain), and the risk of someone entering the chamber

    Medium
    Who / how
    Operatives (gas poisoning, collapse, death) and anyone trying a rescue
    Existing controls
    No manhole entry planned in this scope
    L×S
    2×5=10
    Additional controls
    No one enters the manhole or any confined chamber on this job. Lift the cover only with the correct key, keep ignition sources away and let the chamber vent. Work from ground level or from the supported trench. If entry is thought necessary, stop and reassess, as it needs a Confined Spaces Regulations 1997 assessment, a safe system of work and rescue arrangements. Do not do anything that would need breathing apparatus without a trained team.
  11. Respirable crystalline silica (RCS) dust from breaking in, coring or cutting the brick, concrete or mortar of the existing manhole and from cutting concrete or masonry

    Medium
    Who / how
    Operatives doing the work and anyone nearby breathing the dust (long-term lung disease, silicosis, lung cancer)
    Existing controls
    Work is outdoors in open air
    L×S
    3×5=15
    Additional controls
    Plan the connection to reduce cutting and coring, for example using existing openings or purpose-made fittings. Use on-tool extraction (M-class or H-class vacuum) or water suppression on every drill, corer, breaker and saw used on the manhole walls and benching. Keep others away and clean up with an H-class or M-class vacuum, never dry sweeping or compressed air. Then use RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven. Follow the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE Construction Information Sheet CIS36 Construction dust. The RCS workplace exposure limit is 0.1 mg/m3 (8-hour TWA) in HSE EH40/2005.
  12. Disturbing unidentified asbestos-containing materials (for example old pipework, sheeting, coatings or debris in the ground or at the existing manhole and extension tie-in) in a building where the age is not confirmed

    Medium
    Who / how
    Operatives, householders and other trades (asbestos fibre inhalation causing serious lung disease later in life)
    Existing controls
    Permit to dig and excavation permit
    L×S
    2×5=10
    Additional controls
    Before work starts, check the client's asbestos register or management survey for the work area, as required by Regulation 5 of the Control of Asbestos Regulations 2012. For intrusive work where the register does not cover the area, get a refurbishment and demolition survey of that area first. Record this check on the permit. Brief all operatives to recognise suspect materials. Stop-work rule: if suspect material is found, stop, keep people away, do not touch or sweep it up and report it to the Principal Contractor before work carries on.
  13. Wet concrete (haunching and bedding of the manhole frame): skin burns, dermatitis and eye damage

    Low
    Who / how
    Operatives (cement burns, dermatitis, eye injury)
    Existing controls
    Hot water and wash facilities in the cabin
    L×S
    3×3=9
    Additional controls
    Use ready-mixed concrete or pre-bagged mixes to reduce mixing and dust. Mix on a board, away from drains and watercourses, and stand upwind. Wash off splashes straight away and do not let wet concrete rest against skin or kneel in it. Keep skin covered and use barrier cream only as a supplement. Follow COSHH 2002 and the supplier's Safety Data Sheet. Alkali-resistant gloves, eye protection and waterproof boots as the last line of defence.
  14. Generator, electrical equipment and fuel: electric shock, fire, carbon monoxide, and fuel spills

    Low
    Who / how
    Operatives and nearby occupants (shock, burns, fire, poisoning, ground contamination)
    Existing controls
    Genny on site and wash facilities
    L×S
    3×4=12
    Additional controls
    Use 110V equipment or battery tools and RCD protection for any 230V item. Check leads, plugs and PAT labels, and keep leads off the ground and out of water. Run the generator outdoors, away from windows and doors, on a drip tray, and refuel only when it is switched off and cool. Keep fuel in approved containers in a locked safe place with a spill kit and a fire extinguisher on hand. Follow the Electricity at Work Regulations 1989 and PUWER 1998.
  15. Slips, trips and falls on muddy, uneven ground, spoil heaps, pipes and leads, and working in rain, wet trenches or hot sun

    Low
    Who / how
    Operatives, householders and other trades (sprains, fractures, heat illness, cold)
    Existing controls
    Site access off a private driveway, site cabin
    L×S
    4×2=8
    Additional controls
    Keep the work area tidy and store pipes, bedding and spoil in set places away from walkways. Use walkways or boards over soft ground and lay leads off the floor. Pump out water from the trench before work and stop work if heavy rain threatens the trench sides, with re-inspection before work starts again. Provide shelter, water and shade in hot weather, and warm rest breaks in cold weather. Anti-slip boots and waterproofs as the last line of defence.

4. COSHH assessment

Built on COSHH 2002 regulations 6 and 7 and HSE guidance L5.

Check each entry against the supplier's Safety Data Sheet before work starts. Take workplace exposure limits from HSE EH40/2005.

Concrete for haunching (wet cement)

Task or use
Mixing, placing and finishing concrete haunching around the drainage pipes and bedding the manhole cover and frame
Route of exposure
Skin contact, eye contact, and inhalation of dust when handling dry bags
Who could be harmed
Operatives mixing and placing concrete, who could get cement burns, dermatitis or eye injury. Others nearby from dust.
Hazards
Wet cement is alkaline and can cause skin burns, dermatitis and serious eye damage. Dry cement dust can irritate the nose, throat and lungs. Check section 2 of the supplier's Safety Data Sheet for the product's exact hazards.
Controls
  1. Eliminate or reduce use where possible, for example by limiting the amount of haunching to what is specified.
  2. Substitute with ready-mixed or low-dust pre-bagged concrete to reduce mixing and dust.
  3. Mix on a board away from drains, standing upwind, and open bags carefully with minimal dust.
  4. Wash off splashes straight away with clean water and do not let wet concrete sit against the skin or inside boots or gloves.
  5. Limit exposure time, keep others away from mixing and follow COSHH 2002 and HSE L5, the COSHH Approved Code of Practice.
PPE
  • Alkali-resistant gloves to the specification in the Safety Data Sheet
  • Eye protection
  • Waterproof boots and long sleeves
  • Dust mask if dry mixing creates dust, to the Safety Data Sheet specification
Storage and disposal
Store bags dry, off the ground and under cover. Do not wash tools or wash out into drains or the ground. Let waste concrete set and dispose of as construction waste under the waste duty of care.
First aid and spillage
Skin: wash off with plenty of clean water and seek medical advice if burns or irritation occur. Eyes: rinse with clean water for at least 10 minutes and get urgent medical help. Spills: let them dry, then collect and dispose of as waste. Do not hose into drains.
Health surveillance
Skin checks are advised for anyone who regularly handles wet cement, for early signs of dermatitis. For this short job, none is expected beyond reporting any skin problems.
Check against the Safety Data Sheet
Confirm from the supplier's Safety Data Sheet (section 2 hazards, section 8 exposure controls and PPE, sections 4 and 6 first aid and spillage), and check workplace exposure limits in HSE EH40/2005, before work starts. Follow COSHH 2002 and HSE L5.

Respirable crystalline silica (RCS) dust from breaking in, coring or cutting masonry, brick or concrete at the existing manhole

Task or use
Breaking in, coring or cutting the brick or concrete walls and benching of the existing manhole to make the drain connection
Route of exposure
Inhalation of fine dust. Eye contact with dust.
Who could be harmed
Operatives doing the work and anyone nearby, who can develop serious lung disease after long-term exposure.
Hazards
Fine dust from masonry, concrete, brick and mortar can be breathed deep into the lungs and can cause serious, irreversible lung disease. The harm builds up over time and the dust is often not visible. Check the material's details and the extraction equipment's data to confirm the hazard details.
Controls
  1. Eliminate or reduce the need to cut or core, for example by using existing openings or purpose-made fittings.
  2. Use water suppression or on-tool extraction (M-class or H-class vacuum) on every tool used on these materials.
  3. Limit the quantity of cutting, the time spent and the number of people nearby, and keep others away from the work.
  4. Clean up only with an H-class or M-class vacuum or wet methods, never dry sweeping or compressed air.
  5. Follow COSHH 2002, HSE L5 and HSE Construction Information Sheet CIS36 Construction dust.
PPE
  • Disposable FFP3 respirator or equivalent, face-fit tested and worn clean shaven, as the last line of defence
  • Eye protection
  • Disposable or washable overalls, and clean-up before breaks
Storage and disposal
Collect dust and slurry in the vacuum or by wet methods, double bag and dispose of as construction waste. Do not wash slurry into drains. Empty and clean vacuum filters carefully, outdoors.
First aid and spillage
Eyes: rinse with clean water. If breathing is affected, move to fresh air and get medical advice. Spilled dust: wet down or vacuum with an H-class or M-class vacuum, never dry sweep.
Health surveillance
Respiratory health surveillance is needed for anyone regularly exposed to silica dust, in line with the employer's occupational health advice. Occasional short exposure on this job is not expected to need it, but the employer should confirm.
Check against the Safety Data Sheet
Confirm the dust-control arrangements, RPE specification and any product data, and check the workplace exposure limits in HSE EH40/2005, before work starts. Follow COSHH 2002 and HSE L5.

Foul sewage and drain contents at the existing manhole and foul run (biological hazard)

Task or use
Connecting the new foul drain to the existing manhole and handling pipes, fittings and tools that may have been in contact with foul water
Route of exposure
Skin contact through cuts and grazes, eye splashes, ingestion by hand-to-mouth contact, and inhalation of splashes or aerosols
Who could be harmed
Operatives working at the manhole and foul run, who could get infections such as leptospirosis, hepatitis A, and stomach illness.
Hazards
Foul water can carry bacteria and viruses that cause illness, including Weil's disease, which can be serious. Gases can also be released from foul drains. No product data applies, so follow COSHH 2002 and HSE guidance on biological agents.
Controls
  1. Avoid contact: plan the connection to limit the time the drain is opened and avoid splashing.
  2. Eliminate the need to enter the chamber: work from ground level or from the supported trench.
  3. Keep clean and dirty areas apart, cover cuts with waterproof dressings and provide hot water, soap and drying facilities.
  4. Limit who is in the area and the time spent, and clean tools and boots before breaks.
  5. Brief operatives on the symptoms of Weil's disease and to report any illness and tell the doctor about the work. Follow COSHH 2002 and HSE L5.
PPE
  • Waterproof gloves
  • Eye protection or a face shield for splashes
  • Waterproof overalls and waterproof boots, washed or disposed of after use
Storage and disposal
Wash tools and boots at the wash point, not into surface-water drains. Dispose of contaminated disposable PPE and rags as waste. Keep clean clothes and food away from the work area.
First aid and spillage
Wash cuts and splashes at once with soap and clean water, cover the wound and report it. Eyes: rinse with clean water for at least 10 minutes. Spills: contain and clean with water into the foul system, not into surface-water drains.
Health surveillance
No routine health surveillance is expected. Operatives must report any flu-like illness, jaundice or stomach upset promptly and tell their doctor they work with sewage.
Check against the Safety Data Sheet
No Safety Data Sheet applies to sewage, so confirm the arrangements for hygiene, immunisation advice (such as hepatitis A) and the employer's procedure for reporting illness before work starts, and check workplace exposure limits in HSE EH40/2005 for any gases. Follow COSHH 2002 and HSE L5.

Fuel (diesel and petrol) for the mini-excavator and generator

Task or use
Refuelling and running the mini-excavator, generator and compactor plate
Route of exposure
Skin contact, eye contact, inhalation of vapour and fumes, and ingestion by accident
Who could be harmed
Operatives refuelling or handling fuel and anyone nearby, who could suffer skin irritation, fumes, or fire injuries.
Hazards
Fuel is flammable, can irritate skin and eyes, and its fumes can cause headaches and dizziness. Exhaust fumes from engines contain carbon monoxide. Check section 2 of the supplier's Safety Data Sheet for the exact hazards.
Controls
  1. Reduce the amount of fuel held on site and fill up from the minimum number of containers.
  2. Use approved, labelled fuel containers and a funnel or spill-free nozzle, and refuel only with engines off and cool, away from ignition sources.
  3. Run engines outdoors with good ventilation, never in enclosed spaces, and keep fuel and the generator on drip trays.
  4. Keep fuel stores locked and others away, with a spill kit and a fire extinguisher close by. Follow COSHH 2002 and HSE L5.
PPE
  • Nitrile or fuel-resistant gloves to the Safety Data Sheet specification
  • Eye protection when pouring
  • Overalls, changed if soaked in fuel
Storage and disposal
Store in approved, closed, labelled containers on a drip tray, locked, away from heat, and not in the cabin or house. Dispose of spilt fuel, contaminated absorbent and rags as hazardous waste through a licensed carrier.
First aid and spillage
Skin: wash with soap and water. Eyes: rinse with clean water for at least 10 minutes and get medical help. Swallowed: do not induce vomiting and seek urgent medical help. Spills: stop the source, contain with absorbent and keep out of drains, then dispose of as hazardous waste.
Health surveillance
None is expected for the short, occasional use on this job.
Check against the Safety Data Sheet
Confirm from the supplier's Safety Data Sheet the hazard classification, storage, PPE specification and first aid before work starts, and check workplace exposure limits in HSE EH40/2005. Follow COSHH 2002 and HSE L5.

5. Plant & equipment

  • 1.5t mini-excavator (CPCS or NPORS operator, daily checks)
  • CAT and Genny (cable avoidance tool and signal generator), used by a trained operative
  • Trench support and shoring (boxes, props or sheets, installed to the manufacturer's instructions)
  • Compactor plate
  • Generator
  • Hand tools including insulated hand-digging tools, shovels, spirit level and pipe cutters
  • Ladder for trench access
  • Barrier fencing, signs and stop blocks
  • Spill kit and fire extinguisher
  • M-class or H-class vacuum, water suppression or on-tool extraction for the manhole connection

6. Materials / COSHH

110mm and 160mm uPVC drainage pipe and fittings, pea shingle or pipe bedding, concrete for haunching, and a manhole cover and frame. Hazardous items assessed above are wet concrete, silica dust from breaking in at the manhole, foul sewage and drain contents, and fuel for the plant.

7. PPE

  • Hard hat to BS EN 397 near plant and lifting
  • Hi-vis clothing to BS EN ISO 20471
  • Safety boots with steel toecap and midsole to BS EN ISO 20345
  • Gloves suited to the task: general work, alkali-resistant for concrete, waterproof for sewage contact, to BS EN 388 or BS EN ISO 374 as relevant
  • Eye protection to BS EN 166
  • Hearing protection to BS EN 352 for the compactor plate and excavator
  • FFP3 respirator to BS EN 149, face-fit tested, for silica dust
  • Waterproofs and waterproof overalls
  • Insulating gloves for hand-digging near located services as the last line of defence

8. Competence & training

The excavator operator holds a CPCS or NPORS mini-excavator ticket, and the operatives hold an EUSR Water Hygiene card and NRSWA street works qualifications. R. Fields, Site Supervisor, is the competent person for the excavation inspections. The operative using the CAT and Genny must be trained in their use and in HSG47. All operatives are briefed on this RAMS and sign the briefing sheet. A banksman is briefed and named before plant moves. Which operative holds which ticket, and who is the trained first aider, is confirmed at the site induction.

9. Permits

  • Excavation permit
  • Permit to dig
  • Building control drainage connection approval
  • Sewerage undertaker approval if the existing manhole is on a public sewer, confirmed with Hartley Residential before work starts

10. Access & egress

Access to the site is off the private driveway, with a single agreed route for people and vehicles kept clear of the work zone. Trench access is by battered ends and a ladder secured and extending at least 1m above the top of the trench. Barriers are set back from the trench edge and the work zone is fenced. The driveway is kept clear for emergency vehicles. The excavator and delivery vehicles are guided by a banksman.

11. Welfare

Site cabin with WC and wash facilities and hot water for hygiene. Operatives wash hands and forearms with soap and hot water before eating, drinking, smoking and leaving site. Clean and dirty areas are kept apart. Drinking water and a place to eat away from the work area are provided. Wet and dirty PPE is kept separate from clean clothing.

12. First aid

A first aid kit is kept in the cabin and in the site vehicle. At least one operative is a trained first aider, confirmed at the site induction. All cuts and grazes are cleaned and covered with a waterproof dressing. Anyone with flu-like symptoms after sewage contact reports it and tells their doctor about the work. All accidents and near misses are recorded and reported to Hartley Residential.

13. Emergency procedures

Trench collapse: stop work, raise the alarm and call 999. Do not enter the trench to dig by hand unless it is safe to do so. Services strike: stop work and keep everyone well clear. Electricity: do not touch the plant or the cable, keep at least 10 metres away and call 999 and the electricity distributor on 105. Gas: stop engines, evacuate, remove ignition sources and call the National Gas Emergency Number 0800 111 999. Water: isolate where it is safe to do so and tell the client. Fire: raise the alarm, use an extinguisher only if safe and call 999. Agree the assembly point at the induction. Give the full postcode and the driveway access to the emergency services, confirming it with Hartley Residential first. R. Fields is the point of contact for the contractor.

14. Environmental

Keep concrete washout, silt and fuel away from drains and watercourses. Keep a spill kit on site, use drip trays and refuel away from drains. Do not wash slurry or sewage into the surface-water drainage. Keep spoil tidy and covered or damped down in dry weather, and clean the driveway after each shift. Sort and remove waste, with waste transfer notes, under the waste duty of care. Keep noisy work within hours agreed with the client and neighbours. Protect tree roots, hedges and the neighbours' boundaries.

This document was AI-generated as a drafting aid. It is not a substitute for professional health & safety advice. It must be reviewed, verified and made site-specific by a competent person before use, briefed to all operatives, and updated when site conditions or the method change. The provider accepts no liability for use of this document on site.

Drainage method statement: what it covers