Skip to content

Drylining method statement example: stud partitions and plasterboard, fit-out

HSE five steps · CDM 2015
You write this
Install metal-stud partitions and plasterboard, then tape and joint, in a commercial fit-out. The floor is unoccupied and handed over as a bare shell for the fit-out works.
You get this
Meridian Interiors Ltd will install metal-stud partitions and plasterboard, then tape and joint, in a commercial fit-out on the Second Floor, Kingsworth House, 40 Cavendish Street, Sheffield S3. The principal contractor is Kingsworth Fit-Out Contractors, project reference MI-4471. The floor is unoccupied and handed over as a bare shell for the fit-out works. Work starts Tue 23 Jun 2026 and is expected to take 10 days with 4 operatives, supervised by T. Osei. Work at height will be done from mobile access towers by PASMA trained operatives under a tower handover permit. Dust is controlled at source with on-tool extraction and clean-up with an M-class or H-class vacuum. Items to confirm before work starts: (1) the full site postcode, and the age of the building, to be confirmed by T. Osei with Kingsworth Fit-Out Contractors, who must also provide the asbestos register or management survey for the second floor at the pre-start meeting; (2) the floor and soffit construction and how track will be fixed to them, to be confirmed by T. Osei on the pre-start walk, because fixing into concrete changes the silica controls; (3) partition heights and the platform heights needed, to be confirmed by T. Osei on the pre-start walk; (4) the floor loading limit and where boards may be stacked, to be confirmed by Kingsworth with the permit to load; (5) lift capacity, booking arrangements, the stair core route, the assembly point and first aider cover, to be confirmed by Kingsworth at site induction; (6) which other trades will be working on the floor during the 10 days, to be confirmed by Kingsworth before the start date.

Generated for an example job to show the format. Make your own site-specific version and have a competent person review it.

Document details
ContractorMeridian Interiors Ltd
AuthorT. Osei, Drylining Supervisor (CSCS Gold, SSSTS)
Client / Principal ContractorKingsworth Fit-Out Contractors
SiteSecond Floor, Kingsworth House, 40 Cavendish Street, Sheffield S3 7R**
Project referenceMI-4471
Start / durationTue 23 Jun 2026 / 10 days

1. Scope of works

Meridian Interiors Ltd will install metal-stud partitions and plasterboard, then tape and joint, in a commercial fit-out on the Second Floor, Kingsworth House, 40 Cavendish Street, Sheffield S3. The principal contractor is Kingsworth Fit-Out Contractors, project reference MI-4471. The floor is unoccupied and handed over as a bare shell for the fit-out works. Work starts Tue 23 Jun 2026 and is expected to take 10 days with 4 operatives, supervised by T. Osei. Work at height will be done from mobile access towers by PASMA trained operatives under a tower handover permit. Dust is controlled at source with on-tool extraction and clean-up with an M-class or H-class vacuum. Items to confirm before work starts: (1) the full site postcode, and the age of the building, to be confirmed by T. Osei with Kingsworth Fit-Out Contractors, who must also provide the asbestos register or management survey for the second floor at the pre-start meeting; (2) the floor and soffit construction and how track will be fixed to them, to be confirmed by T. Osei on the pre-start walk, because fixing into concrete changes the silica controls; (3) partition heights and the platform heights needed, to be confirmed by T. Osei on the pre-start walk; (4) the floor loading limit and where boards may be stacked, to be confirmed by Kingsworth with the permit to load; (5) lift capacity, booking arrangements, the stair core route, the assembly point and first aider cover, to be confirmed by Kingsworth at site induction; (6) which other trades will be working on the floor during the 10 days, to be confirmed by Kingsworth before the start date.

2. Sequence of works

Method statement, safe system of work

  1. Before work starts, T. Osei checks the client's asbestos register or management survey for the second floor with Kingsworth Fit-Out Contractors. The building age is confirmed. If the register does not cover the areas to be fixed into or drilled, a refurbishment and demolition survey of those areas is needed first. Work does not start until this is done.
  2. Attend the site induction. Confirm the lift booking, stair core route, assembly point, first aider and welfare locations. Confirm the floor loading limit and the permit to load for stacked boards.
  3. T. Osei briefs all four operatives on this RAMS and they sign to confirm they have read and understood it. The briefing covers the stop-work rules for suspect asbestos materials, tower use, dust control and emergency arrangements.
  4. Walk the floor with the Principal Contractor. Check lighting, floor condition, setting out datum lines, services above the ceiling and in the slab, and where other trades are working. Agree exclusion zones and protected walkways.
  5. Check all plant before use: towers for PASMA tags and damage, cordless tools and chargers for damage and in-date inspection or PAT tests, vacuums for filter condition, and saw guards. Take any defective item out of use.
  6. Receive boards and studs through the building lift in manageable loads, using trolleys. Stack in the agreed area within the permitted floor loading, away from escape routes, laid flat and supported.
  7. Erect each mobile tower on firm, level floor, following the manufacturer's instructions and PASMA training. Fit all guardrails, toe boards and outriggers or stabilisers as needed. Inspect, tag and hand over the tower under the tower handover permit before anyone climbs it.
  8. Set out partition lines using a laser or chalk line. Fix floor and ceiling track to the confirmed substrate. Use extraction-fitted drills for any fixings into concrete or masonry, and wet-wipe or vacuum dust immediately.
  9. Cut studs and track to length at the designated cutting station using the chop saw. Deburr cut ends. Use the saw only with guards fitted and with others kept clear of the cutting area.
  10. Erect studs and fit noggins and any services supports. Fit acoustic insulation between studs, handling it as per the Safety Data Sheet.
  11. Board the first face of each partition. Cut boards by scoring and snapping with a cutter where possible, or use a drywall saw. Fix with cordless screwguns. Work from the tower for high boards, with two people lifting large sheets.
  12. Close the second face once other trades have signed off any first-fix inside the partitions. Fit all the boards and carry out an overall visual check of the stud work.
  13. Tape and joint the boards by hand, mixing only the quantity needed. Keep floors clear of spillage and dropped compound.
  14. Sand cured joints using the on-tool extraction sander connected to an M-class or H-class vacuum. Keep others out of the area while sanding. Wear the RPE specified.
  15. Clean as you go. Vacuum dust with an M-class or H-class vacuum, never dry sweep or use compressed air. Bag offcuts and take them to the agreed waste point.
  16. At the end of each shift, secure the towers with brakes on and a sign to prevent use, leave stacked boards stable, check cables and chargers are safely stowed, and keep escape routes clear.
  17. On completion, strike the towers in the reverse order of erection, clean the area and hand it back to Kingsworth Fit-Out Contractors, with the waste removed and the work area signed off.

3. Risk assessment

Built on the HSE five steps, MHSWR 1999 regulation 3 and the hierarchy of control.

  1. Working at height: fall from mobile access tower while boarding, fixing track and jointing

    Medium
    Who / how
    Drylining operatives on the towers, risk of serious or fatal injury from a fall; others below if a person lands on them
    Existing controls
    PASMA trained operatives, towers to manufacturer's instructions, edge protection fitted
    L×S
    3×5=15
    Additional controls
    Avoid work at height where it can be done from the floor, for example by pre-cutting and pre-assembling at ground level. Complete a tower handover permit and inspect and tag every tower before use and after any move or adverse weather. Use full guardrails and toe boards with a safe internal ladder or stair access. Never climb the outside of the frame or use ladders or stepladders as working platforms. Operatives never use the tower alone without a competent person aware. Work follows the Work at Height Regulations 2005. Suitable footwear.
  2. Mobile tower instability or overturning: moving with people or materials on it, soft or uneven floor, base ratio exceeded, striking by materials

    Medium
    Who / how
    Operatives on the tower and anyone nearby, risk of crush or fall injuries
    Existing controls
    PASMA training, manufacturer's instructions, brakes fitted
    L×S
    3×5=15
    Additional controls
    Check the floor is level, free of debris and capable of taking the tower load before erection. Apply castor brakes before use and fit outriggers or stabilisers where the manual calls for them. Do not move towers with anyone or any materials on them. Keep the platform height within the manufacturer's height to base ratio. Do not overreach, move the tower instead. Keep access routes clear for moving towers. Work follows the Work at Height Regulations 2005.
  3. Falling objects: tools, screws, offcuts or boards dropped from the tower

    Medium
    Who / how
    Operatives and other trades working or walking below, risk of head and impact injuries
    Existing controls
    Toe boards, tool lanyards available
    L×S
    3×4=12
    Additional controls
    Set up an exclusion zone at the foot of the tower using barriers and signs. Pass materials up and down by hand or rope, never throw. Keep tools in pouches or on lanyards and keep only essential materials on the platform. Brief other trades on the exclusion zone. Hard hats worn as the last line of defence.
  4. Manual handling: carrying plasterboard sheets, bundles of studs and track, and bags of jointing compound

    Medium
    Who / how
    All four operatives, risk of back, shoulder and hand injury, sprains and strains
    Existing controls
    Experienced operatives, mechanical aids available
    L×S
    4×3=12
    Additional controls
    Assess loads under the Manual Handling Operations Regulations 1992. Order boards in smaller sizes where practical. Use board trolleys and carriers for moving boards, and use two person lifts for long or heavy sheets. Stack close to where boards will be fitted to reduce carrying distance. Rotate tasks to avoid prolonged lifting overhead. Brief operatives on good handling technique. Gloves for grip and protection as backup.
  5. Delivery and vertical transport of materials by building lift and stair core: overloading, trapping, boards damaging the lift

    Low
    Who / how
    Operatives, other building users of the lift, risk of crush, strike and manual handling injuries
    Existing controls
    Lift booked with the Principal Contractor, protected stair core
    L×S
    3×3=9
    Additional controls
    Confirm the lift safe working load with the Principal Contractor and do not exceed it. Load boards flat on trolleys with materials secured, and never travel in the lift with loads that could shift. Keep stair and lift lobby routes clear of materials. The lift is used only under the arrangements set by Kingsworth. Where any lifting equipment is provided by the Principal Contractor, it is operated by competent persons in line with the Lifting Operations and Lifting Equipment Regulations 1998.
  6. Overloading the floor slab with stacked plasterboard and materials

    Low
    Who / how
    Operatives and people below the floor, risk of structural damage and serious injury
    Existing controls
    Permit to load in place
    L×S
    2×4=8
    Additional controls
    Obtain the floor loading limit and designated stacking zone from the Principal Contractor under the permit to load. Spread stacks across the floor and keep within the permitted limits. Do not stack against partitions or block escape routes. Bring in only the amount of board needed for each stage.
  7. Respirable crystalline silica (RCS) dust from drilling or fixing track and brackets into concrete slab, soffit, masonry or block

    Medium
    Who / how
    Operatives doing the work and anyone nearby breathing the dust, risk of silicosis, lung disease and lung cancer from long-term exposure
    Existing controls
    On-tool extraction available, M-class vacuum on site
    L×S
    4×4=16
    Additional controls
    Plan the work to reduce drilling, for example by using fewer fixings and shot-fired or cast-in fixings only where the Principal Contractor allows. Use on-tool extraction with an M-class or H-class vacuum or water suppression on every drill, chaser and saw used on concrete, masonry or block. Keep others away from the work area. Clean up with an H-class or M-class vacuum, never dry sweeping or compressed air. Then use RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven. Follow the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE guidance: Construction Information Sheet CIS36 Construction dust. The RCS workplace exposure limit is 0.1 mg/m3 (8-hour TWA) in HSE EH40/2005.
  8. Dust from cutting and sanding plasterboard and joint compound

    Low
    Who / how
    Operatives sanding and cutting, and others nearby, risk of eye, nose, throat and chest irritation and long-term lung effects from repeated exposure
    Existing controls
    On-tool extraction sander, vacuums on site
    L×S
    4×2=8
    Additional controls
    Use jointing products that need minimal sanding, and finish joints carefully to reduce sanding. Connect sanding and cutting tools to an M-class or H-class vacuum. Cut boards by scoring and snapping where possible. Keep others out of the work area while sanding. Clean up with a vacuum, not brushes or air lines. Open windows or use extract fans where the Principal Contractor allows. Follow COSHH 2002. Wear dust masks or RPE as specified in the Safety Data Sheet, and eye protection.
  9. Noise and hand-arm vibration from the chop saw, screwguns and sander

    Low
    Who / how
    Operatives using and standing near the tools, risk of hearing damage and hand-arm vibration syndrome
    Existing controls
    Cordless tools, limited sanding time
    L×S
    3×3=9
    Additional controls
    Cut studs and track at one designated station away from others, and use cordless tools that are quieter than petrol or corded ones where possible. Limit trigger time and rotate tasks to cut exposure. Keep tools maintained and blades sharp. Brief on noise and vibration under the Control of Noise at Work Regulations 2005 and the Control of Vibration at Work Regulations 2005. Report numb or tingling hands. Hearing protection used at the chop saw as the last line of defence.
  10. Cuts and lacerations from sharp metal stud and track edges, drywall saws and cutter blades

    Low
    Who / how
    Operatives handling studs, cutting boards and sheets, risk of cuts to hands and forearms
    Existing controls
    Experienced operatives, sharp tools used correctly
    L×S
    4×2=8
    Additional controls
    Deburr or file the cut ends of studs and track before installing. Use retractable blade knives and cutters, and always cut away from the body. Store and dispose of blades in a sharps box. Carry studs and track with ends covered or taped where practical. Cut-resistant gloves as backup, matching the task and to BS EN 388.
  11. Chop saw use: ejected sparks and metal fragments, blade contact, burrs and swarf

    Low
    Who / how
    The operative using the saw and anyone close by, risk of eye injury, cuts and burns
    Existing controls
    Guards fitted, trained operatives
    L×S
    3×4=12
    Additional controls
    Use the saw only with guards in place and the correct blade for metal studs, checked under the Provision and Use of Work Equipment Regulations (PUWER) 1998. Clamp material before cutting. Set up the saw at a stable bench away from walkways and other trades, and keep combustible material away from sparks. Clear swarf with a vacuum or magnetic sweeper, not by hand. Eye and face protection to BS EN 166 and gloves where appropriate, as backup.
  12. Electric shock or fire from cordless tool batteries, chargers and any temporary supply

    Low
    Who / how
    Operatives and others on the floor, risk of electric shock, burns and fire
    Existing controls
    Cordless tools used where possible
    L×S
    2×4=8
    Additional controls
    Use cordless tools to avoid trailing leads. Use only the supplied chargers, in designated charging areas away from combustible materials such as boards and bags. Do not leave batteries charging unattended or overnight. Inspect leads and chargers before use and keep any equipment on the site's reduced low voltage or RCD protected supply as required. Follow the Electricity at Work Regulations 1989. Remove damaged equipment from use.
  13. Striking concealed services when fixing into the floor slab or soffit, or boarding over existing services

    Low
    Who / how
    Operatives drilling and fixing, risk of electric shock, burns or damage to services
    Existing controls
    Principal Contractor service information
    L×S
    2×4=8
    Additional controls
    Obtain service drawings from the Principal Contractor and ask which services are isolated or live. Scan fixing positions with a cable and pipe detector before drilling and mark them. Keep fixings away from marked services. Stop work and report immediately if an unexpected service is found. Follow the Electricity at Work Regulations 1989.
  14. Slips, trips and falls on the same level: offcuts, packaging, cables, vacuum hoses, spilled joint compound, bare shell floor

    Medium
    Who / how
    All operatives and other trades on the floor, risk of sprains, fractures and cuts
    Existing controls
    Good housekeeping expected
    L×S
    3×3=9
    Additional controls
    Bag and remove offcuts and packaging at the end of each shift, and at the agreed waste point. Keep hoses and cables tidy and routed overhead or along walls. Mop up spilled compound immediately. Keep walkways and escape routes clear. Ensure there is adequate lighting for all areas worked in and stairs. Sturdy boots with good grip to BS EN ISO 20345.
  15. Other trades working on the same floor, in a bare shell fit-out: collisions, overhead work by others, services trades working close to partitions

    Medium
    Who / how
    Our operatives and other trades from the Kingsworth fit-out team, risk of impact injury, struck-by and disrupted work areas
    Existing controls
    Principal Contractor co-ordination, site induction
    L×S
    3×3=9
    Additional controls
    Agree work areas and sequence with the Principal Contractor at the pre-start walk, and attend any daily co-ordination meetings. Keep exclusion zones around towers, saw station and sanding. Barrier and sign areas where overhead work is happening. Report clashes to the Principal Contractor, in line with CDM 2015 duties for co-operation. High-vis clothing worn.
  16. Disturbing unidentified asbestos-containing materials when drilling, fixing or cutting into existing building fabric such as the ceiling, walls, floor, ducts or boxing

    Medium
    Who / how
    Operatives and anyone nearby, risk of long-term lung disease if asbestos fibres are released
    Existing controls
    Principal Contractor holds building information
    L×S
    2×5=10
    Additional controls
    Before work starts, check the client's asbestos register or management survey for the work area, as required by Regulation 5 of the Control of Asbestos Regulations 2012. If the register does not cover the areas to be drilled or disturbed, a refurbishment and demolition survey of the area is needed first. Only fix into areas the register shows are clear. Stop-work rule: if any suspect material is found, stop, keep people away, and report it to T. Osei and the Principal Contractor before work carries on. Do not restart until it has been assessed.
  17. Fire and emergency evacuation: combustible waste and packaging, materials blocking escape routes, towers and stacked boards in the way

    Medium
    Who / how
    All operatives and others on the floor, risk of burns, smoke inhalation and delayed evacuation
    Existing controls
    Principal Contractor fire arrangements, protected stair core
    L×S
    2×5=10
    Additional controls
    Hot works are not part of this job. Keep waste off the floor and removed daily. Keep stair lobbies, corridors and exits clear at all times. Stack materials away from fire doors and extinguishers. Attend the Principal Contractor's induction on alarms, assembly point and fire extinguishers. Do not use the building lift in a fire.
  18. Skin and eye irritation from joint compound, plasterboard dust and acoustic insulation fibres

    Low
    Who / how
    Operatives mixing, jointing, sanding and fitting insulation, risk of dermatitis, eye and skin irritation
    Existing controls
    Welfare facilities for washing
    L×S
    3×2=6
    Additional controls
    Choose premixed or low-dust products where available and check the Safety Data Sheet for each product before use. Cut insulation with a sharp knife, reduce handling and keep it in its packaging until needed. Wash hands before eating, drinking and at the end of each shift, and use skin cream. Follow COSHH 2002. Gloves, eye protection and long sleeves as the last line of defence.

4. COSHH assessment

Built on COSHH 2002 regulations 6 and 7 and HSE guidance L5.

Check each entry against the supplier's Safety Data Sheet before work starts. Take workplace exposure limits from HSE EH40/2005.

Respirable crystalline silica dust from drilling or fixing into concrete, masonry or block

Task or use
Created when drilling or fixing track, brackets and other fixings into the concrete slab, soffit or masonry on this job
Route of exposure
Inhalation of fine dust. Eye contact with airborne dust.
Who could be harmed
The operatives drilling and anyone nearby, risk of silicosis, lung disease and lung cancer after long-term exposure
Hazards
Fine dust from concrete, brick, block or stone can damage the lungs over time. Effects can be serious and may not show for years. Check section 2 of any product Safety Data Sheet for related hazards.
Controls
  1. Eliminate or reduce the dust at source by planning the work to need less drilling and fewer fixings, and by using non-drilled fixings where the Principal Contractor allows.
  2. Use on-tool extraction with an M-class or H-class vacuum or water suppression on every drill used on these materials.
  3. Keep others out of the work area and limit the number of people and time spent drilling.
  4. Clean up with an H-class or M-class vacuum, never dry sweeping or compressed air.
  5. Follow the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).
PPE
  • Face-fit tested RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), worn clean shaven, to the specification in the risk assessment
  • Eye protection to BS EN 166
  • Disposable or washable overalls
Storage and disposal
Collect dust in the vacuum container. Empty it carefully into sealed, labelled bags and dispose of as construction waste via the Principal Contractor's waste route. Do not blow or brush dust.
First aid and spillage
If dust gets in the eyes, rinse with clean water for at least 10 minutes and seek medical help if irritation persists. If someone is struggling to breathe, move them to fresh air and call for first aid or an ambulance. Clean settled dust with a vacuum or damp wipe, not a dry brush.
Health surveillance
Respiratory surveillance may be needed for regular or frequent exposure. This should be confirmed by Meridian Interiors Ltd's occupational health provider. None is expected for the short, controlled exposure expected on this job, but report any cough or breathing symptoms.
Check against the Safety Data Sheet
Silica dust has no product Safety Data Sheet. Confirm the workplace exposure limit in HSE EH40/2005. Confirm the Safety Data Sheet details for any fixings or cartridges used, and that the vacuum, drill extraction and RPE are suitable for this work.

Joint compound and the dust from sanding it

Task or use
Mixing, applying and sanding joint compound and tape over plasterboard joints and screw heads
Route of exposure
Inhalation of dust when mixing or sanding. Skin contact. Eye contact. Ingestion if hands are not washed.
Who could be harmed
Operatives mixing, jointing and sanding, and others nearby, risk of skin, eye and respiratory irritation
Hazards
Hazards depend on the product used. Dust from sanding can irritate the eyes, nose and throat. Check section 2 of the supplier's Safety Data Sheet for the hazards of the specific product.
Controls
  1. Choose a ready-mixed or low-dust joint compound where possible, and a finish that needs the least sanding.
  2. Use the on-tool extraction sander connected to an M-class or H-class vacuum.
  3. Mix only what is needed in a clean bucket and avoid pouring powder from height.
  4. Keep others out of the area while sanding and limit sanding time.
  5. Follow the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).
PPE
  • Dust mask or RPE to the specification in the Safety Data Sheet
  • Eye protection to BS EN 166
  • Gloves to the specification in the Safety Data Sheet
Storage and disposal
Store bags and tubs closed, dry and off the floor in the agreed storage area, as the Safety Data Sheet says. Let waste compound dry and put it in the general waste, unless the Safety Data Sheet says otherwise. Do not wash compound into drains.
First aid and spillage
For eyes, rinse with clean water for at least 10 minutes and get medical advice if irritation continues. For skin, wash with soap and water. Scoop up spilled wet compound and wipe clean. Vacuum dry powder, do not sweep.
Health surveillance
None is expected for the amount of use on this job. Report any skin problems such as redness, cracking or itching to the supervisor so they can be checked.
Check against the Safety Data Sheet
Before work starts, get the Safety Data Sheet for the joint compound used. Confirm the hazards in section 2, the PPE and RPE specification, storage and disposal advice, and any workplace exposure limit in HSE EH40/2005.

Plasterboard dust from cutting and boarding

Task or use
Created when cutting, snapping, sawing and fixing plasterboard
Route of exposure
Inhalation of dust. Eye contact. Skin contact.
Who could be harmed
Operatives cutting and fixing boards, and people nearby, risk of eye, nose and throat irritation
Hazards
Plasterboard dust can irritate the eyes, nose, throat and skin. Check the plasterboard supplier's Safety Data Sheet, or product information, section 2 for the details.
Controls
  1. Reduce cutting by ordering boards to suitable sizes where practical.
  2. Cut by scoring and snapping with a cutter where possible, and use a drywall saw only when needed.
  3. Cut in a designated area and use an M-class or H-class vacuum to clean up.
  4. Keep others away from cutting and clear dust daily.
  5. Follow the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).
PPE
  • Dust mask or RPE to the specification in the Safety Data Sheet
  • Eye protection to BS EN 166
  • Gloves
Storage and disposal
Store boards flat, dry and supported within the permitted floor loading. Collect offcuts and dust in bags and dispose through the Principal Contractor's waste route.
First aid and spillage
Rinse eyes with clean water for at least 10 minutes. Wash skin with soap and water. Clean up dust with a vacuum or damp wipe, not a dry brush.
Health surveillance
None is expected for this job. Report any breathing or skin symptoms to the supervisor.
Check against the Safety Data Sheet
Before work starts, confirm the supplier's Safety Data Sheet or product information for the boards, including section 2 hazards, PPE and RPE specifications, and workplace exposure limits for dust in HSE EH40/2005.

Acoustic insulation

Task or use
Cutting and fitting acoustic insulation between studs within partitions
Route of exposure
Skin contact. Eye contact. Inhalation of loose fibres or dust.
Who could be harmed
Operatives handling and fitting insulation, risk of itching skin, and eye, nose and throat irritation
Hazards
Hazards depend on the type of insulation. Some can cause itching and irritation to skin, eyes and the throat. Check section 2 of the supplier's Safety Data Sheet for the product.
Controls
  1. Choose a low-dust or low-irritant insulation product where this suits the specification.
  2. Leave insulation in its packaging until it is needed and cut it with a sharp knife on a clean surface to reduce loose fibres.
  3. Fit insulation after studs are in place to limit handling, and clear offcuts straight away into bags.
  4. Keep others away while it is being cut and use a vacuum for clean-up.
  5. Follow the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH guidance (L5, the COSHH Approved Code of Practice).
PPE
  • Gloves
  • Long sleeves
  • Eye protection to BS EN 166
  • Dust mask or RPE to the specification in the Safety Data Sheet
Storage and disposal
Keep packs dry, closed and off the floor. Bag offcuts and dispose of them through the Principal Contractor's waste route, as the Safety Data Sheet advises.
First aid and spillage
Rinse eyes with clean water for at least 10 minutes. Wash skin with cool water and soap without rubbing. Clean spilled fibres with a vacuum or damp wipe.
Health surveillance
None is expected for this job. Report any ongoing skin or breathing problems to the supervisor.
Check against the Safety Data Sheet
Before work starts, confirm the insulation type and get the supplier's Safety Data Sheet. Check the hazards in section 2, PPE and RPE specifications, disposal advice and any exposure limits in HSE EH40/2005.

5. Plant & equipment

  • Mobile access towers (PASMA, with tower handover permit and inspection tags)
  • Cordless screwguns
  • Plasterboard drywall saw and board cutter
  • On-tool extraction sander connected to M-class or H-class vacuum
  • Chop saw for track and stud, with guards
  • M-class or H-class vacuum
  • Drills with on-tool extraction for fixings into concrete or masonry
  • Cable and pipe detector
  • Board trolleys and carriers
  • Laser level, tape and chalk line
  • Battery chargers, RCD protected where powered from site supply
  • Barriers and signs for exclusion zones

6. Materials / COSHH

Materials in use are metal stud and track, plasterboard, jointing tape, joint compound, acoustic insulation and fixings. Hazardous substances are covered in the COSHH assessments: respirable crystalline silica dust from fixing into concrete or masonry, joint compound and sanding dust, plasterboard dust and acoustic insulation. Safety Data Sheets for each product must be on site and read before use.

7. PPE

  • Safety footwear to BS EN ISO 20345
  • Hard hat to BS EN 397, worn in tower and exclusion zones
  • High-visibility clothing
  • Cut-resistant gloves to BS EN 388, as backup after other controls
  • Eye protection to BS EN 166
  • Hearing protection when using the chop saw, as the last line of defence
  • Dust mask or RPE as the Safety Data Sheet specifies, and FFP3 face-fit tested RPE for silica dust tasks
  • Long sleeved overalls

8. Competence & training

All operatives are CSCS carded drylining operatives and PASMA trained for mobile towers. T. Osei is the Drylining Supervisor (CSCS Gold, SSSTS) and is responsible for briefing the team and checking compliance. Operatives must have a current site induction, have read and signed this RAMS, and be face-fit tested for FFP3 RPE. Chop saw and drill users must be trained and competent in the use of that equipment.

9. Permits

  • Permit to load / mobile tower handover
  • Hot works not applicable to this job

10. Access & egress

Access is by the building lift and the protected stair core to the second floor. Keep the lift and stair routes clear of materials and waste. Use trolleys for loads. Escape routes remain clear and unobstructed at all times. Walkways within the floor are agreed at the pre-start walk.

11. Welfare

The Principal Contractor's site welfare facilities will be used, including toilets, hand washing, drinking water and rest area. Operatives wash hands before eating and drinking, and at the end of each shift. Welfare locations are confirmed at the site induction.

12. First aid

First aid is provided by Kingsworth Fit-Out Contractors' first aiders and first aid facilities. Operatives are told where the first aid kit and first aider are at the site induction. All injuries, however minor, are reported to T. Osei and the Principal Contractor and recorded.

13. Emergency procedures

Follow the Principal Contractor's emergency procedures given at the site induction. On the alarm, stop work, make safe, leave via the nearest protected stair and go to the assembly point, and do not use the lift. T. Osei takes a head count. In an emergency call 999 and give the site address, 40 Cavendish Street, Sheffield S3, with the full postcode confirmed at induction, and the exact location on the second floor. For a person in difficulty on a tower, do not climb up unaided. Call for help, and keep the area clear. If suspect asbestos material is found, stop work, move people away and report it to T. Osei and the Principal Contractor.

14. Environmental

Keep waste in sealed bags, segregate plasterboard offcuts, metal and packaging, and remove them to the Principal Contractor's waste route daily. Do not wash joint compound or dust into drains. Use vacuum extraction to limit dust spread to other areas. Use cordless tools to limit noise and keep noisy tasks to the agreed working hours. Check any waste for asbestos suspicion before disposal and report suspect materials.

This document was AI-generated as a drafting aid. It is not a substitute for professional health & safety advice. It must be reviewed, verified and made site-specific by a competent person before use, briefed to all operatives, and updated when site conditions or the method change. The provider accepts no liability for use of this document on site.

Dry lining method statement: what it covers

Other samples:ElectricalGroundworksRoofingScaffoldingFlat roofingSee all 20

Want one like this for your job?

Get your RAMS– it's freeFirst document free, then £15 each. No subscription.