Painting & decorating method statement example: repaint occupied office + window frames

HSE five steps · CDM 2015
You write this
Prepare and repaint interior walls, ceilings and woodwork throughout occupied ground and first floor offices, including redecoration of external window frames reached from a ladder and mobile access tower.
You get this
Crown Finish Decorators Ltd will prepare and repaint interior walls, ceilings and woodwork throughout occupied ground and first floor offices, including redecoration of external window frames reached from a ladder and mobile access tower, at Kingsway House (Ground & First Floor Offices), 18 Kingsway House, Nottingham, for Beacon Facilities Management (project ref CFD-3312). Start date Tue 23 Jun 2026, duration 5 days, 3 operatives, supervised by S. Hargreaves. The offices stay occupied, so work will be done room by room and area by area, with each area handed over by the client before work starts and handed back when finished. External frame work will be done from a mobile access tower, with the leaning ladder used only for short, light tasks and for getting onto the tower where the PASMA method allows. External work will be carried out from a cordoned pavement and car park area under a permit to work. Asbestos is flagged as likely present, so no sanding, scraping or other disturbance of building fabric starts until the asbestos register or management survey for each work area has been checked. This RAMS supports the risk assessment required by Regulation 3 of the Management of Health and Safety at Work Regulations 1999 and the duties under CDM 2015. Items to confirm before work starts, with the Principal Contractor (Beacon Facilities Management) on the pre-start walk: (1) the postcode of the site, which is incomplete in the project details, and the building's age; (2) the asbestos register or management survey for every room, the stairwell, ceilings and external frames, and whether any area needs a refurbishment and demolition survey first; (3) the working height of the first floor external window frames and whether the mobile tower is to be used inside the stairwell or on ceilings, plus the type of low-level access (podium or platform) for internal ceilings; (4) ground conditions, level and bearing capacity under the tower base on the pavement and car park, and who has authority to close any public footway or car park bays; (5) which two-pack isocyanate-containing coatings are to be used and where, and whether a water-based or isocyanate-free alternative is acceptable; (6) the supplier Safety Data Sheets for every product; (7) the fire evacuation routes, assembly point and out-of-hours access arrangements; (8) the name of the first aider on the 3-person team, to be confirmed by S. Hargreaves; (9) whether any painted surfaces are old enough to need a lead paint check; (10) which sockets and fittings in the work areas the client will isolate or protect.

Generated for an example job to show the format. Make your own site-specific version and have a competent person review it.

Document details
ContractorCrown Finish Decorators Ltd
AuthorS. Hargreaves, Site Supervisor (NVQ Level 2 Painting & Decorating)
Client / Principal ContractorBeacon Facilities Management
SiteKingsway House (Ground & First Floor Offices), 18 Kingsway House, Nottingham NG1 6D**
Project referenceCFD-3312
Start / durationTue 23 Jun 2026 / 5 days

1. Scope of works

Crown Finish Decorators Ltd will prepare and repaint interior walls, ceilings and woodwork throughout occupied ground and first floor offices, including redecoration of external window frames reached from a ladder and mobile access tower, at Kingsway House (Ground & First Floor Offices), 18 Kingsway House, Nottingham, for Beacon Facilities Management (project ref CFD-3312). Start date Tue 23 Jun 2026, duration 5 days, 3 operatives, supervised by S. Hargreaves. The offices stay occupied, so work will be done room by room and area by area, with each area handed over by the client before work starts and handed back when finished. External frame work will be done from a mobile access tower, with the leaning ladder used only for short, light tasks and for getting onto the tower where the PASMA method allows. External work will be carried out from a cordoned pavement and car park area under a permit to work. Asbestos is flagged as likely present, so no sanding, scraping or other disturbance of building fabric starts until the asbestos register or management survey for each work area has been checked. This RAMS supports the risk assessment required by Regulation 3 of the Management of Health and Safety at Work Regulations 1999 and the duties under CDM 2015. Items to confirm before work starts, with the Principal Contractor (Beacon Facilities Management) on the pre-start walk: (1) the postcode of the site, which is incomplete in the project details, and the building's age; (2) the asbestos register or management survey for every room, the stairwell, ceilings and external frames, and whether any area needs a refurbishment and demolition survey first; (3) the working height of the first floor external window frames and whether the mobile tower is to be used inside the stairwell or on ceilings, plus the type of low-level access (podium or platform) for internal ceilings; (4) ground conditions, level and bearing capacity under the tower base on the pavement and car park, and who has authority to close any public footway or car park bays; (5) which two-pack isocyanate-containing coatings are to be used and where, and whether a water-based or isocyanate-free alternative is acceptable; (6) the supplier Safety Data Sheets for every product; (7) the fire evacuation routes, assembly point and out-of-hours access arrangements; (8) the name of the first aider on the 3-person team, to be confirmed by S. Hargreaves; (9) whether any painted surfaces are old enough to need a lead paint check; (10) which sockets and fittings in the work areas the client will isolate or protect.

2. Sequence of works

Method statement, safe system of work

  1. Before the start date, S. Hargreaves obtains and checks the client's asbestos register or management survey for every work area, the stairwell and the external window frames, as required by Regulation 5 of the Control of Asbestos Regulations 2012. If the register does not cover an area where fabric will be sanded, scraped, drilled or stripped, that area does not start until a refurbishment and demolition survey is done.
  2. Obtain the supplier Safety Data Sheets for every product, complete the COSHH assessments, and confirm whether any isocyanate-free or water-based alternative can be used instead of the two-pack coatings.
  3. Hold the pre-start walk with Beacon Facilities Management: confirm the items listed in the scope, agree the work areas and their order, the handover points, the cordon extent, welfare, fire routes and out-of-hours working for solvent and two-pack coating work.
  4. Brief all three operatives on this RAMS, the asbestos stop-work rule, the evacuation arrangements, tower and ladder rules and the COSHH controls. Everyone signs the briefing sheet.
  5. Complete the permit to work for external work at height and the area handover for the first work area before anything is set up.
  6. Set up the external cordon with barriers and signs on the pavement and car park area, clear of vehicle routes. Keep a clear walkway for the public and for office staff.
  7. Check ground and level, then erect the mobile access tower to the manufacturer's instructions by PASMA-trained operatives. Fit and extend outriggers or stabilisers, lock the castors, fit guardrails and toe boards, and complete and record the pre-use inspection before anyone climbs it.
  8. Inside, set up the first area: remove or move furniture with the client's staff, lay dust sheets, tape down edges and cables, put up wet paint and keep-out signs and close off the room from occupied areas.
  9. Check for suspect materials before any preparation. If suspect asbestos-containing material is found, or something not shown on the register, stop work, keep everyone away, close the area, report it to S. Hargreaves and the client, and do not restart until the client confirms in writing that it is safe.
  10. Prepare surfaces: dry rub down only with sanders connected to on-tool extraction (M-class or H-class vacuum), wet-scrape or wash down where possible, fill and make good. Carry out any lead paint check where the paint age or condition raises a doubt.
  11. Clean up using an H-class or M-class vacuum and damp wipes, never dry sweeping or compressed air. Bag dust and waste at the end of each shift.
  12. Apply primer, undercoat and emulsion by brush and roller. Use the smallest quantity of solvent-based gloss, eggshell and primer needed, keep lids on, ventilate, and only apply solvent-based and two-pack products in areas that are clear of other people, outside office hours where the client agrees.
  13. Apply any isocyanate-containing two-pack coating only if the Safety Data Sheet controls can be met: brush or roller only, no spraying, trained operatives only, RPE and gloves to the Safety Data Sheet, room segregated, and no re-entry by others until the clearance time in the Safety Data Sheet has passed.
  14. Carry out external frame preparation and painting from the tower. Use the leaning ladder only for short, light tasks, tied at the top, set at 1 in 4, with three points of contact. Stop if the wind, rain or ice makes the work unsafe.
  15. Keep tools on a tool tray or on lanyards, lift materials using a hoist line or bucket, and never throw or drop items. Keep the cordon in place any time there is work above it.
  16. At the end of each shift, put lids on all containers, take rags and waste to the agreed metal bin, lock solvent-based and two-pack products away in the agreed store, lower or secure the tower and remove trip hazards.
  17. On completion of each area, remove dust sheets, clean the area, check fire exits and cables are clear, leave wet paint signs where needed, and hand the area back to the client with a signed handover.
  18. At the end of the job, dismantle the tower in the reverse order of erection, take down the cordon, remove all waste and containers from site, and complete a final walkaround with the client.

3. Risk assessment

Built on the HSE five steps, MHSWR 1999 regulation 3 and the hierarchy of control.

  1. Falls from height: leaning ladder used to reach external window frames

    Medium
    Who / how
    Operatives using the ladder, with the risk of fractures, head injury or death from a fall or the ladder slipping
    Existing controls
    Operatives trained, ladder in good condition, tower available for longer tasks
    L×S
    3×5=15
    Additional controls
    Use the mobile tower for any sustained work. Use the ladder only for short-duration light tasks (Work at Height Regulations 2005, Schedule 6): check it before use, set at 1 in 4 on firm level ground, tie at the top and both stiles, or footed by a second operative if it cannot be tied. Keep three points of contact, no overreaching, no carrying paint pots up (use a hook or bucket on a line). Permit to work for external work at height completed before use. Safety footwear with good grip as a last line of defence.
  2. Mobile access tower collapse, overturning or fall from the platform when redecorating external window frames

    Medium
    Who / how
    Operatives on the tower and anyone below or beside it, with the risk of serious injury or death
    Existing controls
    PASMA-trained operatives, manufacturer's guide
    L×S
    3×5=15
    Additional controls
    Check the ground and level before erecting. Erect to the manufacturer's instructions in the PASMA method with outriggers or stabilisers fully extended, castors locked and braked, full guardrails, mid-rails and toe boards, platform fully boarded and a safe internal access ladder. Never move with people or materials on it. Inspect before first use, after any move, and after weather that could affect it, and keep a record, in line with the Work at Height Regulations 2005. Stop work above the manufacturer's stated wind limit. Do not use the tower where it may be struck by vehicles unless protected by barriers.
  3. Falling tools, materials and paint onto people below the external work

    Low
    Who / how
    Members of the public, office staff and other trades passing below, with the risk of head injury or bruising from falling objects
    Existing controls
    Cordoned pavement and car park area
    L×S
    3×4=12
    Additional controls
    Keep the cordon wide enough for the working height and keep it in place whenever work is overhead. Fit toe boards, use a tool tray, tethers and lanyards on tools, and use a hoist line for materials. No throwing items. Nobody enters the cordon unless authorised. Hard hats worn by anyone in the cordon or at the base of the tower as a last line of defence (BS EN 397).
  4. Public nearby: pedestrians and vehicles using the pavement and car park around the external work

    Medium
    Who / how
    Members of the public, visitors and drivers; operatives at the tower base, with the risk of being struck by vehicles or tripping over equipment
    Existing controls
    Cordon on the pavement and car park area
    L×S
    3×5=15
    Additional controls
    Set up barriers, signage and a clear, safe pedestrian route past the work, away from vehicle routes. Agree with the client which car park bays are closed and how vehicles are managed. Confirm who gives permission before any public footway is obstructed. Check the cordon at the start of each shift and after any wind or vehicle movement. Position the tower and equipment away from vehicle routes, and use a second person to watch the cordon while moving equipment. Hi-vis clothing worn as a last line of defence (BS EN ISO 20471).
  5. Occupied site: staff, visitors, cleaners and other trades in the offices working near the decorating

    Medium
    Who / how
    Office staff, visitors, cleaners, other trades and FM contractors, from dust, vapours, wet surfaces, trailing cables, ladders and equipment
    Existing controls
    Area handover with the client, work in occupied offices by arrangement
    L×S
    3×3=9
    Additional controls
    Work in agreed rooms and zones one at a time, with signed handover and hand back. Segregate each work area with barriers, closed doors and signs. Agree out-of-hours working for solvent-based and two-pack coatings. Keep corridors, stairs and fire exits clear at all times. Wet paint signs where needed. Brief client staff on the day. Keep all materials locked away when not in use. No unauthorised people in work areas. Daily liaison with the client.
  6. Disturbing asbestos-containing materials (asbestos likely present): sanding, scraping or making good existing walls, ceilings, boxing, textured coatings or window panels

    Medium
    Who / how
    Operatives, office staff and visitors, from breathing in asbestos fibres, which can cause fatal lung disease long after exposure
    Existing controls
    Operatives have asbestos awareness training
    L×S
    2×5=10
    Additional controls
    Treat asbestos as likely present. Check the client's asbestos register or management survey for each work area before starting, as required by Regulation 5 of the Control of Asbestos Regulations 2012. If the register does not cover an area where fabric will be disturbed, a refurbishment and demolition survey of that area is needed first. Operatives do not drill, cut, scrape or sand any material the register does not clear. Stop-work rule: if any suspect material is found or damaged, stop, keep people away, close the area, report to the supervisor and client, and do not restart until cleared in writing. Keep asbestos awareness training in date.
  7. Respirable crystalline silica (RCS) dust

    Medium
    Who / how
    The operatives doing the work and anyone nearby breathing the dust, with the risk of silicosis, lung cancer and other long-term lung disease
    Existing controls
    Sanders with on-tool extraction
    L×S
    3×4=12
    Additional controls
    Plan the work to reduce sanding and any cutting or drilling of plaster, render, masonry or cement-based filler, for example by washing down and scraping rather than sanding. Use on-tool extraction (M-class or H-class vacuum) or water suppression on every sander or other tool used on these materials. Keep others away and clean up with an H-class or M-class vacuum, never dry sweeping or compressed air. Then RPE with an assigned protection factor of at least 20 (FFP3 disposable or equivalent), face-fit tested and worn clean shaven. Comply with the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE Construction Information Sheet CIS36 'Construction dust'. The RCS workplace exposure limit of 0.1 mg/m3 (8-hour TWA) is in HSE EH40/2005.
  8. Solvent vapours from solvent-based gloss, eggshell, primers and white spirit

    Medium
    Who / how
    Operatives and office occupants, from headaches, dizziness, drowsiness, and irritation to the nose, throat and eyes
    Existing controls
    Ventilation of rooms, products kept with lids on
    L×S
    3×3=9
    Additional controls
    Under COSHH 2002, first see if water-based products can be used instead. Limit quantities taken into each room, open windows and use mechanical ventilation where possible, close off the work area, and apply solvent-based products out of hours where the client agrees. Keep lids on, clean brushes in a ventilated space. Allow ventilation time before staff return. Check section 2 and 8 of each Safety Data Sheet for the hazards and PPE. RPE to the Safety Data Sheet specification as a last line of defence.
  9. Isocyanate-containing two-pack coatings: breathing in vapour or mist

    Medium
    Who / how
    Operatives applying the coating, and anyone who enters the area afterwards, with the risk of occupational asthma and other respiratory sensitisation, which is serious and can be permanent
    Existing controls
    Training and competence of operatives
    L×S
    3×4=12
    Additional controls
    Under COSHH 2002, ask the client if an isocyanate-free or water-based alternative can be used. If they cannot, only trained operatives mix and apply, by brush or roller only, with no spraying. Do the work in a segregated room, out of hours, with ventilation or extraction, and nobody else present. No re-entry until the clearance time in the Safety Data Sheet. Health surveillance for respiratory health for anyone who works with isocyanates, arranged through an occupational health provider. RPE and gloves to the Safety Data Sheet specification, face-fit tested, as a last line of defence.
  10. Skin and eye contact with paints, primers, fillers and thinners

    Low
    Who / how
    Operatives, from dermatitis, skin irritation, and splashes to the eyes, especially when painting ceilings
    Existing controls
    Gloves and glasses available
    L×S
    3×2=6
    Additional controls
    Use low-splash rollers and brush for cutting in, keep lids on, decant away from other people, and use a pole or extension for ceilings. Provide an eyewash station and handwashing with soap and water. No solvent to be used to clean skin. Check Safety Data Sheets for hazards. Nitrile gloves to BS EN ISO 374 and safety glasses to BS EN 166 as a last line of defence.
  11. Dust from sanding old paint, including possible lead-based paint where the building age is not confirmed

    Low
    Who / how
    Operatives and others in the building, who may breathe in or swallow dust containing lead, with the risk of long-term harm to health
    Existing controls
    Sanders with on-tool extraction
    L×S
    2×4=8
    Additional controls
    Confirm the building age and ask the client if any lead paint is known. Where doubt remains, use a lead test kit before sanding. Prefer wet methods or chemical stripping to dry sanding, and always use on-tool extraction. Segregate the area and clean up with an H-class or M-class vacuum and damp wipes. Apply COSHH 2002, and the Control of Lead at Work Regulations 2002 if lead paint is confirmed. Disposable overalls (Type 5) and FFP3 RPE as a last line of defence. No eating, drinking or smoking in the work area.
  12. Fire from flammable solvent-based products, white spirit and solvent-soaked rags in an occupied building

    Medium
    Who / how
    Operatives, office staff, visitors and other trades, with the risk of burns, smoke inhalation and death
    Existing controls
    Client fire alarm, evacuation routes and extinguishers
    L×S
    2×5=10
    Additional controls
    Under the Dangerous Substances and Explosive Atmospheres Regulations 2002, keep only the day's quantity in the work area. Keep containers closed, store overnight in a locked, ventilated metal store agreed with the client, and put used rags in a lidded metal bin that is removed from the building daily. No ignition sources, no smoking, no hot works. Keep escape routes, fire doors and alarm points clear. Check the fire alarm and the evacuation routes at the handover. Fit-for-purpose extinguisher in the work area.
  13. Slips, trips and falls from dust sheets, trailing cables, wet floors, stairs and tools

    Low
    Who / how
    Operatives, office staff and visitors, from sprains, fractures and bruises
    Existing controls
    Dust sheets and housekeeping
    L×S
    3×3=9
    Additional controls
    Use non-slip or taped-down dust sheets, route cables overhead or along the wall and cover them where they cross routes, and keep stairs, corridors and exits clear. Wet paint signs and warning cones on wet floors. Tidy at the end of each shift. Keep the stairwell free of stored materials. Slip-resistant safety footwear as a last line of defence (BS EN ISO 20345).
  14. Manual handling of paint tins, tower components, ladder and equipment

    Low
    Who / how
    Operatives, from back, shoulder and arm injuries
    Existing controls
    Operatives trained
    L×S
    3×3=9
    Additional controls
    Under the Manual Handling Operations Regulations 1992, avoid lifting where possible: order smaller containers, use trolleys, decant at the point of use, and use two people for tower parts and long ladders. Plan routes and use lifts where available. Keep loads close to the body, with rest breaks and rotation of tasks. Gloves with good grip as a last line of defence.
  15. Electric shock or fire from sanders, extractors, leads and sockets in the offices

    Medium
    Who / how
    Operatives and office staff, from electric shock, burns and fire
    Existing controls
    Tools PAT tested
    L×S
    2×5=10
    Additional controls
    Under the Electricity at Work Regulations 1989 and PUWER 1998, use 110V tools or 230V tools through an RCD, check that tools and leads are in date for testing and undamaged before every use, route leads out of walkways, and keep leads away from wet areas. Do not paint over or around live fittings unless the client confirms they are isolated or protected. No repairs to electrical equipment by operatives. Faulty equipment is tagged and removed from use.
  16. Noise and hand-arm vibration from sanders and extraction units

    Low
    Who / how
    Operatives and office staff nearby, from annoyance, hearing damage and vibration-related injury with frequent use
    Existing controls
    Sanders with on-tool extraction, short use in each area
    L×S
    2×2=4
    Additional controls
    Under the Control of Noise at Work Regulations 2005, schedule noisy sanding away from occupied rooms where possible, rotate tasks to limit time on tools, and use well-maintained tools. Check the tool's noise level and vibration level from its handbook. Hearing protection to BS EN 352 if the noise level makes it necessary.
  17. Weather during external work on the tower and ladder: wind, rain and cold

    Low
    Who / how
    Operatives on the tower or ladder and people below, from slips, loss of balance and falling objects
    Existing controls
    Permit to work for external work at height
    L×S
    3×4=12
    Additional controls
    Check the forecast before each shift and stop external work if wind, rain, ice or poor light make the work unsafe, or if the tower's wind limit is reached. Do not paint in wet or damp conditions. Re-inspect the tower after storms. Plan external frames for the best weather days and reschedule internal work if needed. Warm and waterproof clothing as a last line of defence.
  18. Working at height inside: ceilings and stairwell walls reached from steps or low-level platforms

    Medium
    Who / how
    Operatives, from falls from steps, platforms or stairs, with the risk of fractures and head injury
    Existing controls
    Operatives trained, tower available
    L×S
    3×4=12
    Additional controls
    Under the Work at Height Regulations 2005, use a podium, hop-up or low-level platform for ceilings in preference to stepladders. Use the mobile tower with guardrails in the stairwell where the height needs it, not a ladder. Keep the base clear of people and furniture, keep floors clean and dry and work with the area closed off. Use stepladders only for light, short tasks. Check equipment before each use. Slip-resistant footwear as a last line of defence.

4. COSHH assessment

Built on COSHH 2002 regulations 6 and 7 and HSE guidance L5.

Check each entry against the supplier's Safety Data Sheet before work starts. Take workplace exposure limits from HSE EH40/2005.

Solvent-based gloss/eggshell and primers

Task or use
Brush and roller application to woodwork, metal and prepared surfaces, inside and on external window frames
Route of exposure
Inhalation of vapour, skin contact, eye contact, and ingestion through poor hygiene
Who could be harmed
The operatives applying it, and office staff or visitors who share the area or return before the room is ventilated, from headaches, dizziness, drowsiness, and skin and eye irritation
Hazards
Solvent-based paints can irritate the skin, eyes and airways and can affect the nervous system if vapour is breathed in. They are also flammable. The exact hazards depend on the product, so check section 2 of its Safety Data Sheet.
Controls
  1. Eliminate or substitute: use a water-based or low-solvent product where the specification allows.
  2. Engineering: ventilate the room with open windows or mechanical extraction, and apply in a closed-off area.
  3. Administrative: limit quantities taken into each area, keep lids closed, apply out of hours where agreed with the client, keep others out until the room is aired, and keep a record of products used.
  4. Administrative: no eating, drinking or smoking in work areas, and wash hands before breaks.
PPE
  • Gloves of the type and material specified in the Safety Data Sheet (BS EN ISO 374)
  • Safety glasses to BS EN 166
  • RPE to the Safety Data Sheet specification where ventilation does not control vapour, face-fit tested
  • Overalls
Storage and disposal
Keep in original, labelled, closed containers in a locked, ventilated store away from ignition sources, agreed with the client. Put used rags and brushes in a lidded metal bin and remove from the building daily. Dispose of waste paint and solvent-contaminated waste through a licensed waste carrier. Never pour it down drains.
First aid and spillage
Skin: remove contaminated clothing, wash with soap and water. Eyes: rinse with clean water for at least 10 minutes, hold eyelids open, and get medical help. If breathed in, move to fresh air and get medical help if unwell. Do not induce vomiting if swallowed. Small spills: remove ignition sources, ventilate, absorb with inert absorbent, and bag for disposal. Report large spills to the supervisor and client.
Health surveillance
No specific health surveillance expected for normal use. Operatives report skin problems or breathing problems to the supervisor. Confirm against the Safety Data Sheet.
Check against the Safety Data Sheet
Before work starts, confirm from the supplier's Safety Data Sheet: the hazards (section 2), the required gloves and RPE (section 8), first aid, fire, spillage and disposal advice, and whether a safer alternative exists. Take workplace exposure limits from HSE EH40/2005. Assess under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH Approved Code of Practice (L5).

White spirit

Task or use
Cleaning brushes and thinning solvent-based products
Route of exposure
Inhalation of vapour, skin contact, eye contact, ingestion
Who could be harmed
Operatives using it, and others nearby, from headaches, dizziness and skin dryness or irritation
Hazards
Breathing the vapour can cause headaches, dizziness and drowsiness. Contact can dry or irritate the skin and eyes. It is flammable and can be harmful if swallowed. Check section 2 of the Safety Data Sheet for the product-specific hazards.
Controls
  1. Eliminate or substitute: use water-based products and clean tools in water where possible, or a lower-hazard cleaner if the Safety Data Sheet permits.
  2. Engineering: use in a well-ventilated space only, away from occupied areas.
  3. Administrative: take only small amounts in a closed container, keep lids on, no decanting into unmarked containers, and keep ignition sources away.
  4. Administrative: never use it to clean skin.
PPE
  • Gloves of the type specified in the Safety Data Sheet (BS EN ISO 374)
  • Safety glasses to BS EN 166
  • RPE to the Safety Data Sheet specification if ventilation is not enough
Storage and disposal
Store in its original closed container in a locked, ventilated metal store away from heat, agreed with the client. Dispose of used solvent and soaked rags as hazardous waste through a licensed carrier. Not down drains.
First aid and spillage
Skin: wash with soap and water. Eyes: rinse with water for at least 10 minutes and get medical help. If breathed in, get fresh air. If swallowed, do not induce vomiting, and get medical help immediately. Spillage: remove ignition sources, ventilate, absorb with inert material, and bag for disposal.
Health surveillance
None expected for the short, occasional use on this job. Report any skin problems to the supervisor.
Check against the Safety Data Sheet
Before work starts, confirm from the Safety Data Sheet: the hazards (section 2), glove material and RPE needed (section 8), flammability and fire-fighting advice, and disposal. Take workplace exposure limits from HSE EH40/2005. Assess under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH Approved Code of Practice (L5).

Isocyanate-containing two-pack coatings

Task or use
Brush or roller application of a two-pack coating on the surfaces specified by the client, including mixing the two components
Route of exposure
Inhalation of vapour or mist, skin contact, eye contact
Who could be harmed
The operatives mixing and applying it, and anyone entering the area before it is cleared, with the risk of asthma-type respiratory sensitisation, skin sensitisation and irritation
Hazards
Isocyanates are known respiratory sensitisers. Once someone is sensitised, even very small exposures can trigger asthma attacks. They can also cause skin and eye irritation. Check section 2 of the product's Safety Data Sheet for the full hazards.
Controls
  1. Eliminate or substitute: ask the client to approve an isocyanate-free or water-based alternative before using the product.
  2. Engineering: apply only in a segregated room with mechanical ventilation or local extraction. No spraying, brush or roller only.
  3. Administrative: only trained operatives mix and apply. Mix in small batches, apply out of hours with nobody else in the area, display signs, and keep doors closed.
  4. Administrative: no re-entry by others until the clearance time in the Safety Data Sheet has passed. Anyone with a history of asthma is not to work with it, unless cleared by occupational health.
  5. Administrative: respiratory health surveillance for operatives who work with it, through an occupational health provider.
PPE
  • RPE to the type and protection factor specified in the Safety Data Sheet, face-fit tested and worn clean shaven
  • Gloves of the material specified in the Safety Data Sheet (BS EN ISO 374)
  • Chemical splash goggles or safety glasses to BS EN 166
  • Disposable overalls
Storage and disposal
Store in original, sealed, labelled containers in a locked, ventilated store away from moisture and heat, agreed with the client. Dispose of empty containers, mixed residues and contaminated rags as hazardous waste through a licensed carrier, following the Safety Data Sheet.
First aid and spillage
Skin: wash off with soap and water straight away. Eyes: rinse with water for at least 10 minutes and get medical help. If breathed in and there are breathing difficulties, get fresh air and call for medical help. Spillage: evacuate the area, ventilate, wear RPE and gloves from the Safety Data Sheet, absorb with inert material, and bag for hazardous waste disposal. Report to the supervisor and client.
Health surveillance
Yes. Regular exposure to isocyanates needs respiratory health surveillance, including a baseline and regular checks, arranged through an occupational health provider. Anyone who develops cough, wheeze or breathlessness at work must report it straight away.
Check against the Safety Data Sheet
Before work starts, confirm from the supplier's Safety Data Sheet: the hazards (section 2), the RPE type and protection factor, the gloves, safe re-entry or clearance time, mixing and application rules, and disposal. Take workplace exposure limits from HSE EH40/2005. Assess under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH Approved Code of Practice (L5).

Respirable crystalline silica dust from sanding or making good plaster, render, masonry and cement-based fillers

Task or use
Sanding and rubbing down existing walls, and sanding fillers and any cement-based or plaster repairs, and any drilling for fixings in masonry or plaster
Route of exposure
Inhalation, and eye contact
Who could be harmed
Operatives and anyone nearby breathing the fine dust, with the risk of silicosis, lung cancer and other chronic lung diseases from long-term exposure
Hazards
Fine silica dust can reach deep into the lungs and cause permanent, sometimes fatal, disease after repeated exposure. It can also irritate the eyes and nose. Check the Safety Data Sheet for any filler or repair product for product-specific hazards (section 2).
Controls
  1. Eliminate: plan work to reduce sanding, for example by washing down, scraping or using pre-mixed fillers that sand with less dust.
  2. Substitute: use low-dust or ready-mixed fillers where the specification allows.
  3. Engineering: on-tool extraction (M-class or H-class vacuum) on every sander, or water suppression.
  4. Administrative: keep others out of the area, restrict the time spent sanding, and clean up with an H-class or M-class vacuum, never dry sweeping or compressed air.
  5. Administrative: asbestos check of the register before any sanding or disturbance (see the risk assessment).
PPE
  • FFP3 disposable respirator or equivalent (assigned protection factor of at least 20), face-fit tested and worn clean shaven
  • Disposable overalls (Type 5)
  • Safety glasses to BS EN 166
Storage and disposal
Keep dust in sealed bags or in the H-class or M-class vacuum bag and remove from site daily as non-hazardous construction waste unless the client's survey says otherwise. Empty vacuums carefully, in a controlled way, and wipe down surfaces with damp cloths.
First aid and spillage
Eyes: rinse with clean water. If breathing is affected, move to fresh air and get medical advice. Dust deposits: do not sweep dry or use compressed air. Vacuum with an H-class or M-class vacuum and wipe with damp cloths.
Health surveillance
Regular exposure to silica dust may need respiratory health surveillance. The supervisor will confirm with an occupational health provider whether it applies to these operatives, based on how often they do this work. For this 5-day job the exposure is expected to be low.
Check against the Safety Data Sheet
Before work starts, confirm from the Safety Data Sheets of any filler or repair product what the product contains and the recommended controls (sections 2 and 8). Take workplace exposure limits from HSE EH40/2005. Assess under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH Approved Code of Practice (L5), and follow HSE Construction Information Sheet CIS36.

Emulsion paint and fillers

Task or use
Brush and roller application of emulsion to walls and ceilings, and filling holes and cracks
Route of exposure
Skin contact, eye contact, inhalation of dust when sanding fillers, and ingestion through poor hygiene
Who could be harmed
Operatives, from skin and eye irritation and dust irritation
Hazards
Water-based emulsions are generally low hazard but can contain preservatives that irritate the skin or eyes or cause allergic reactions in some people. Fillers can create irritant dust when sanded. The exact hazards depend on the product, so check section 2 of each Safety Data Sheet.
Controls
  1. Substitute: choose low-odour, low-VOC water-based products where the specification allows.
  2. Engineering: use sanders with on-tool extraction and ventilate rooms.
  3. Administrative: use low-splash rollers, limit the time spent sanding, keep lids closed, provide handwashing, and keep the area clear of other people while sanding.
  4. Administrative: no eating or drinking in the work area.
PPE
  • Gloves to the Safety Data Sheet specification (BS EN ISO 374)
  • Safety glasses to BS EN 166 for ceiling work and sanding
  • Dust mask or RPE to the Safety Data Sheet specification when sanding
Storage and disposal
Store in closed, labelled containers in the agreed store. Let small amounts of waste emulsion dry out and dispose of as the Safety Data Sheet advises. Never pour into drains. Wash brushes in the designated place, not into surface water drains.
First aid and spillage
Skin: wash with soap and water. Eyes: rinse with clean water for at least 10 minutes and get medical help if irritation continues. Spills: contain with absorbent material, wipe up and dispose of as non-hazardous waste unless the Safety Data Sheet says otherwise.
Health surveillance
None expected. Operatives report any rashes or skin problems to the supervisor.
Check against the Safety Data Sheet
Before work starts, confirm from the Safety Data Sheets: the hazards (section 2), any sensitisers, PPE (section 8), and disposal advice. Take workplace exposure limits from HSE EH40/2005. Assess under the Control of Substances Hazardous to Health Regulations (COSHH) 2002 and HSE's COSHH Approved Code of Practice (L5).

5. Plant & equipment

  • Mobile access tower (PASMA method, manufacturer's guide on site, outriggers or stabilisers)
  • Leaning ladder, inspected before use, for short light tasks only
  • Podium, hop-up or low-level platform for internal ceilings (type to be confirmed)
  • Sanders with on-tool extraction, connected to an M-class or H-class vacuum
  • H-class or M-class vacuum for clean-up
  • Hand tools: brushes, rollers, scrapers, extension poles, filling knives
  • Dust sheets and masking tape
  • Barriers, cones and signage for the cordon and work areas
  • Metal lidded bin for rags and locked metal store for solvent-based products
  • Fire extinguisher and eyewash
  • Trolley for materials

6. Materials / COSHH

Emulsion, solvent-based gloss and eggshell, primers, fillers, isocyanate-containing two-pack coatings and white spirit, plus dust from sanding. Full detail is in the COSHH assessments. Safety Data Sheets for every product are to be on site before use.

7. PPE

  • Safety footwear with slip-resistant sole (BS EN ISO 20345)
  • Hi-vis clothing (BS EN ISO 20471), if the client requires it
  • Hard hat (BS EN 397) at the tower base and inside the cordon
  • Nitrile gloves, or the glove material specified in each Safety Data Sheet (BS EN ISO 374)
  • Safety glasses (BS EN 166)
  • Disposable overalls (Type 5) for sanding
  • FFP3 respirator (BS EN 149), face-fit tested, for sanding dust
  • RPE to the Safety Data Sheet specification for solvent-based and isocyanate-containing products
  • Hearing protection (BS EN 352) if noise levels need it

8. Competence & training

Operatives hold NVQ Level 2 Painting & Decorating and CSCS cards. Operatives erecting and using the mobile tower are PASMA trained. All operatives have asbestos awareness training (UKATA or equivalent), in date. Anyone using FFP3 or other tight-fitting RPE must be face-fit tested for that type. Operatives working with isocyanate-containing coatings must be trained for it and covered by respiratory health surveillance. S. Hargreaves (NVQ Level 2 Painting & Decorating) is the supervisor and competent person. All operatives are briefed on this RAMS and sign the briefing sheet before work starts. Training certificates are to be available on site.

9. Permits

  • Permit to work for external work at height, completed before the tower or ladder is used
  • Hot-desk or area handover with the client for each work area, at start and finish
  • Confirmation of the asbestos register or management survey for each work area before work starts
  • Confirmation from the client or highway authority for any closure of pavement or car park bays, if needed (to be confirmed at the pre-start walk)
  • Client permission for out-of-hours working for solvent-based and two-pack coating work, if used

10. Access & egress

Operatives enter through the client's main entrance and use the stairwell between floors, keeping them clear of materials and equipment. External work is carried out from a cordoned pavement and car park area, with a safe pedestrian route kept past the cordon. Materials are brought in through the agreed route, and carried by trolley where practicable. Fire exits, escape routes and fire doors are to be kept clear at all times. The tower is placed so that it does not block any exit or vehicle route.

11. Welfare

The client's office WC and kitchen are to be used by arrangement, to be confirmed at the pre-start walk. Operatives wash hands with soap and water before eating, drinking or smoking and at the end of each shift. No eating or drinking in the work areas. Overalls and dusty clothing are changed or cleaned before using the client's kitchen. Clean drinking water is available. Operatives keep welfare areas clean and report any problems to the supervisor.

12. First aid

A first aid kit and eyewash are kept in the work area. The name of the first aider on the team is to be confirmed by S. Hargreaves before work starts. Client first aiders and the location of their first aid facilities are to be noted at the handover. Any injury, near miss or dangerous occurrence is reported to the supervisor and client and recorded, and reported to the HSE under RIDDOR 2013 where it applies.

13. Emergency procedures

All operatives are shown the client's fire alarm, evacuation routes and assembly point at the handover. On the alarm, stop work, put lids on any open containers if safe, leave the building by the nearest safe exit and go to the assembly point, and the supervisor takes a head count. Do not use a tower or ladder in an emergency without checking the area is safe. For a fall or serious injury, call 999, give first aid within competence, do not move the casualty unless in danger, and tell the client. If a fall or tower incident happens, the supervisor stops all work at height until the cause is understood. If suspect asbestos is found or disturbed, stop work, keep people away, close the area and report to the supervisor and client at once. For a chemical spill or fire involving solvents, evacuate and call 999 if a fire cannot be put out safely by a trained person using the extinguisher. The supervisor's mobile number is on the site briefing sheet.

14. Environmental

Waste is segregated: hazardous waste (solvent-based and two-pack coatings, white spirit, contaminated rags and empty tins) is kept separate and removed by a licensed carrier with transfer notes, in line with the waste duty of care under the Environmental Protection Act 1990. Small amounts of dry emulsion waste are disposed of as the Safety Data Sheet advises. Nothing goes down drains or onto the ground. Brushes and rollers are washed out in the designated place. Dust sheets and floor protection are used to protect surfaces, and dust is collected with H-class or M-class vacuums. Noisy work is kept to reasonable hours and agreed with the client. Operatives leave the work areas and external area clean and tidy at the end of each shift, and take all waste off site.

This document was AI-generated as a drafting aid. It is not a substitute for professional health & safety advice. It must be reviewed, verified and made site-specific by a competent person before use, briefed to all operatives, and updated when site conditions or the method change. The provider accepts no liability for use of this document on site.

Painting and decorating method statement: what it covers

Other samples:ElectricalGroundworksRoofingScaffoldingFlat roofingSee all 20

Want one like this for your job?

Get your RAMS– it's freeFirst document free, then £15 each. No subscription.